Global City Gurugram review: pros, cons and HSIIDC's record on Dwarka Expressway

This Global City Gurugram review weighs a government township beside the Dwarka Expressway on facts, not hype. In its favour: a state-owned developer, land cases that largely ended in early 2023, and trunk works well under way. Against it: no auction result is published, no home project is on HRERA Gurugram's register as of 28 November 2026, and completion targets have moved.

Global City covers parts of Sectors 36, 36B, 37 and 37B of Gurugram. HSIIDC (Haryana State Industrial and Infrastructure Development Corporation, fully owned by the Haryana government) builds the main roads and services and sells large land parcels to companies by e-auction. It has no flats of its own.

Below we set out the pros and cons, the promises against progress, the court record, HSIIDC's record on other estates, and who should simply keep watching.

By Preeti Pandey, Property Nivesh Team Reviewed by Rakesh Mahajan Published Updated
Developer
HSIIDC, 100% owned by the Haryana government
Land
More than 1,000 acres (HSIIDC)
Sectors
Parts of Sectors 36, 36B, 37 and 37B, Gurugram
HRERA projects inside Global City
None on the register as of 28 November 2026
Phase one progress
80% (CM, Aug 2026); about 70% (minister, Nov 2026)
Auction results
Not published by HSIIDC for any round

The short answer

  • HSIIDC is fully owned by the Haryana government, and its project site puts Global City at more than 1,000 acres.
  • The Punjab and Haryana High Court dismissed the last land PIL as infructuous on 19 January 2023, after two related writs ended in November 2022.
  • HSIIDC's September 2023 bid document says that auction was subject to the outcome of writ petition CWP No. 6797 of 2023, whose final status is not on public record.
  • The phase-one completion target of October 2026, given by HSIIDC's MD in September 2023, has moved to December 2026.
  • As of 28 November 2026, HRERA Gurugram's register shows no housing project on Global City land, so there is nothing for a home buyer to book.
  • No official result, winner or winning bid has been published for any Global City e-auction, and news reports on the outcome conflict.

Is Global City a good project?

Global City is not yet a project you can judge like a housing society. It is a township where the state lays roads and services, then sells land to developers. On record, the land is in state hands and works are well advanced. Still missing: auction results, any registered home project and confirmed completion of phase one.

So the fair question is narrower. Is the land clean, is the infrastructure real, and does the developer deliver? The sections below answer each one with dates and sources. We give no rating, because nothing has been built for residents to rate.

No resident reviews exist yet

Any online 'review' of homes in Global City is describing something else. No developer project on Global City land is on HRERA Gurugram's register as of 28 November 2026. See our RERA status page for how to check this yourself.

Global City pros and cons at a glance

Here is the balance sheet in one place. Each point on both sides comes from a named source, mostly HSIIDC's own bid documents, Haryana government press notes and court orders. Where the evidence is a news report rather than a record, we say so. Read the two columns together, because most strengths come with a matching caveat.

Global City Gurugram: what is in its favour and what is against it (as of 28 November 2026)
TopicIn its favourAgainst it
DeveloperHSIIDC, 100% state-owned (HSIIDC bid document, 20 Sep 2023)HSIIDC accounts audited only up to 2021-22 (Haryana Finance Department, Mar 2026)
Land titleLast land PIL dismissed 19 Jan 2023; two writs withdrawn or not pressed in Nov 2022CWP No. 6797 of 2023 made the 2023 auction subject to its outcome; status not published
Road frontageAbout 400 m on Dwarka Expressway and 700 m on Pataudi Road (HSIIDC, 2023)Underpass, cloverleaf and NH-48 entry are still plans or under consideration
WorksPhase one: 587 acres, Rs 940 crore (CM, Apr 2025)CM said 80% (Aug 2026); minister said about 70% (Nov 2026)
AuctionsReserve prices, FAR and terms published in 2023 bid documentsNo result, winner or bid published; reports conflict
HomesBid documents require allottees to follow the RERA ActNo HRERA-registered project in Global City (28 Nov 2026)
UpkeepHSIIDC maintains the township at no extra cost until 31 Dec 2033Allottees pay actual maintenance cost from 2034
TransitProposed Sector 56 to Panchgaon metro names Global City as a stop (PTI, Sep 2026)Revised DPR ordered; no metro line serving it is approved
Compiled by Property Nivesh from HSIIDC, Haryana government, court and news sources listed at the foot of this page.
An illustrative picture of the edge of a partly developed township with finished roads beside empty plots on the Dwarka Expressway side of Gurugram Illustrative image
Illustrative image, not a picture of Global City Gurugram.

What is in Global City's favour

The strongest points are about ownership, land and infrastructure. A government agency holds the land, the main legal challenges have ended, and the state has committed close to Rs 1,000 crore to phase one. The buyer protections written into HSIIDC's 2023 bid documents also matter for anyone who later buys from a developer.

  • A state developer. HSIIDC describes itself as a 100% state-owned agency of the Haryana government, and HSIIDC builds the trunk network itself.
  • Settled land history. The land was returned to HSIIDC by a conveyance deed of 29 August 2014, and the High Court ended the Gharauli Khurd PIL on 19 January 2023.
  • Real money on works. The CM said in April 2025 that Rs 940 crore was being spent on a first phase of 587 acres.
  • Services planned at scale. The CM spoke in April 2025 of a 10.7 km utility tunnel and a 350-million-litre reservoir on 18 acres with seven days of backup.
  • Green rules. HSIIDC's bid documents require every building to be GRIHA 4-star or 5-star rated (GRIHA is India's green building rating).
  • Free upkeep for years. HSIIDC says it will run operation and maintenance at no extra cost until 31 December 2033.
  • RERA written in. Allottees must comply with the RERA Act 2016 and Haryana's RERA rules, so any home project on a plot must register before sale.

The road frontage is also on record in HSIIDC's 2023 bid document: about 400 m on the eight-lane Dwarka Expressway and about 700 m on Pataudi Road. Our location page covers each access road and its status.

What is against Global City

The weak points are about evidence and timing. Nobody outside HSIIDC can say which parcels have sold, if any. Targets for auctions and works have slipped more than once. Several links that matter to daily life, such as the underpass and a metro, are still announcements rather than sanctioned works.

  • Auction outcomes are unknown. The Daily Jagran reported on 13 April 2025 that three tenders in two years drew no bids. ThePrint said on 14 August 2026 that auctions were held in November and December 2023, quoting an unnamed officer that developers had shown interest in or acquired parcels. No source names a winner.
  • Allotment is later. The minister told The Times of India on 21 November 2026 that land allotment to investors would follow phase-one completion.
  • Progress claims differ. The CM said on 12 August 2026 that 80% of physical work was done; the minister put phase one at about 70% on 21 November 2026.
  • Access is still on paper. The Dwarka Expressway tunnel was due to start in December 2026, per TOI; the NH-48 entry near Kherki Daula is at the alignment stage with legal issues.
  • Metro is a statement. The CM said in August 2026 that 'A Namo Bharat Metro train will also operate in the city', but no route, agency or sanction stands behind it.
  • Waterlogging nearby. Pataudi Road was among Gurugram's worst-hit roads on 7 July 2026, and neighbouring Sectors 37C and 37D still lacked their planned GMDA drain in October 2026. No source says Global City itself floods.

There is also supply around it. ANAROCK counted 10,770 unsold homes on the Dwarka Expressway corridor in H1 2026, nearly 95% of them under construction. Our investment page puts those corridor figures in context.

Have there been delays? Promises vs progress

Yes. Since 2022, auction targets and the phase-one completion date have both moved. The first auction target of end-November 2022 was missed, the first bid documents came in March 2023, and the October 2026 completion date became December 2026. One news report even gives June 2027. Each step is dated below.

Global City: what was promised or stated, and what the record shows
When saidWho said itPromise or statementStatus as of 28 Nov 2026
Oct 2022Construction World reportAuction 250 acres by end-November 2022Missed; first bid document issued 16 Mar 2023
Jan 2023HSIIDC officials (Hindustan Times)Parcels to e-auction by end-February 2023First e-auction set for 19 May 2023 (B2, tentative)
Mar 2023The TribuneAmenity works to start in July 2023Phase-one contract reported awarded Sep 2023
Sep 2023HSIIDC MD Yash GargPhase-one infrastructure done by October 2026Not met; target now December 2026
Apr 2025CM Nayab Singh SainiFirst phase complete by end of 2026Not yet due
Aug 2026CM Nayab Singh Saini80% done; rest by December 2026; three-month plan for power and waterMinister said about 70% on 21 Nov 2026; no report that the plan was met
Aug 2026News24 reportPhase one targeted for June 2027Conflicts with the December 2026 target
Mar 2026NHAI official (TOI via Swarajya)Underpass work to start within three monthsTOI (21 Nov 2026): start in December 2026; not confirmed
Each row is a statement by the named person or outlet, not our forecast. Full dated history on the timeline page.

For every milestone in order, from the 2003 acquisition notice onward, see our timeline page. Our news note on the third access road explains why that link is still a plan.

An illustrative picture of a wide new road with fresh landscaping and young trees at dusk on the Dwarka Expressway side of Gurugram Illustrative image
Illustrative image, not a picture of Global City Gurugram.

Disputes: land history and court cases

The land was acquired for an SEZ (special economic zone), passed to a Reliance company in 2007 and returned to HSIIDC on 29 August 2014. Three writs and a PIL challenged the acquisition; all ended between November 2022 and January 2023. One later writ, from 2023, still has no published outcome.

HSIIDC told the High Court that the acquisition award covered 1,590 acres and 2,632 landowners, that 1,909 of them had taken compensation, and that it had incurred Rs 2,117.656 crore on the land. It conveyed 1,383.68 acres to Reliance Haryana SEZ Ltd by a deed of 26 April 2007. The SEZ was shelved and the land came back in 2014.

Court cases touching Global City land: counts and status only
CaseWhat it challengedOutcomeDate
CWP-8814-2007 (PIL, Gram Panchayat Gharauli Khurd)Acquisition and transfer to the SEZ companyDismissed as infructuous19 Jan 2023
Writ petition (Ajay Chautala)Acquisition of the landAllowed to be withdrawn15 Nov 2022
Writ petition (Kuldeep Bishnoi)Acquisition of the landDisposed of as not pressed21 Nov 2022
Landowner petitions under section 24(2)Lapse of acquisitionAdjourned sine die in 2016 with status quo; later status not published2016
CWP No. 6797 of 2023Not stated in the bid documentHigh Court order of 25 May 2023 made the auction subject to its outcome; final status not published25 May 2023
CWP No. 14996 of 2018 (landowner)Access path inside the projectDisposed of; HSIIDC to give access to a 60 m road12 Sep 2024
Sources: Punjab and Haryana High Court orders; Hindustan Times; HSIIDC Site C2 bid document of 20 Sep 2023.

Unverified court claim

A claim circulating online that the High Court quashed another PIL on 10 July 2026 is not backed by any court order or reputable news report on record. Treat it as unverified.

What is HSIIDC's track record?

HSIIDC runs industrial estates across Haryana and sells land by auction. Its record is mixed but documented: one large estate now hosts a working car plant, courts have backed its right to reject auction bids, and an Assembly committee has questioned extensions given on one Gurugram plot. Its finances are profitable but recent years are unaudited.

  • IMT Kharkhoda: Autocar India reported in July 2026 that Maruti Suzuki's 800-acre plant at HSIIDC's estate started production in February 2025.
  • Express Greens, IMT Manesar: HSIIDC holds two HRERA Gurugram registrations as promoter, both dated 19 September 2022, for this housing in Sectors M1 and M1A.
  • IMT Sohna: in a 2022 plot auction with a reserve of Rs 11,050 per sq m, HSIIDC declined the highest bids; the High Court upheld that on 4 December 2024, saying the highest bidder has no right until a bid is accepted.
  • Sector 16, Gurugram: HSIIDC auctioned a 12.2-acre commercial plot on 11 June 2010 for Rs 587.56 crore. The Assembly's Committee on Public Undertakings, citing CAG, said in February 2024 that later extensions amounted to undue favour of over Rs 57.77 crore and sought a vigilance inquiry.
  • Manesar land: the Supreme Court in March 2018 annulled the state's 2007 and 2010 decisions to drop an acquisition and vested that land in HUDA or HSIIDC. That case concerned state government decisions, not Global City.
HSIIDC finances (Rs crore, approximate; accounts audited only up to 2021-22)
Item2023-242024-25
Turnoverabout 3,736about 3,660
Profit after interest and taxabout 949about 494
Reserves and surplusabout 4,400about 4,919
Total loansabout 5,216about 2,325
Converted from Rs lakh in the Haryana Finance Department's Profile of State Public Enterprises 2023-24 and 2024-25 (March 2026). Figures are unaudited.

How HSIIDC sells land in other estates, with EMD (earnest money deposit) and payment rules, is explained in our HSIIDC plot scheme guide.

Who Global City suits, and who should only watch

Today Global City suits large, well-capitalised firms that HSIIDC's rules allow to bid. For home buyers, NRIs and small investors it is something to follow, not something to buy, because there is no registered project. Nearby homes in neighbouring sectors are a separate decision with their own checks.

Who the current stage fits

  • Companies, firms or consortia of up to three members that meet HSIIDC's net-worth test. In 2023 it ranged from Rs 273.51 crore (Parcel B2) to Rs 327.25 crore (Parcel C2).
  • Developers prepared to build all internal infrastructure, since HSIIDC's bid documents leave that to the allottee and bar sub-division of a parcel.
  • Long-horizon observers who want to track auction notices and the first project launches.

Who it does not fit yet

  • Individual home buyers: HSIIDC sells whole parcels of 4.84 to 86.05 acres, not homes or small plots.
  • NRIs wanting a ready or near-ready home: no project exists on Global City land, so there is no possession date to weigh.
  • Anyone offered an early 'Global City' flat or plot by an agent: with nothing on HRERA's register, such an offer cannot be a registered sale.
  • Buyers who need a metro line nearby soon: no line serving the township is approved.

If you want to hear when HSIIDC notifies an auction or the first project registers, you can ask for alerts through our contact page. For homes that already exist on the corridor, see our Dwarka Expressway locality guide.

How to check any Global City claim yourself

Most confusion comes from marketing that borrows the Global City name. A few checks settle most claims within minutes. Start with HRERA's register, then HSIIDC's own notices, then the court record. If a claim cannot be traced to one of these, treat it as unconfirmed until it can.

  1. Search HRERA Gurugram's registered-projects list for the project name and its sector; as of 28 November 2026 nothing sits inside Global City.
  2. Ask the seller for the HSIIDC allotment letter for the parcel; no allottee has been named publicly.
  3. Check that the parcel number matches HSIIDC's catalogue (A, B1, B2, C2 or PSP1.A in 2023) on our plot sizes page.
  4. Read HSIIDC's bid-document terms on our payment plan page: built space can be sold only after the phase is fully paid.
  5. Ask for any court order a seller cites, with case number and date.
  6. Compare stated works with the CM's and minister's latest figures on our infrastructure page.

For the full picture of the township, start from our Global City overview, and for quick answers see the Global City FAQs.

Questions people ask

Is Global City Gurugram a good project to invest in?

We do not advise on buying. On facts, the land is held by state-owned HSIIDC, the main land cases ended by January 2023, and phase-one works are well advanced. But no auction result is published and no home project on Global City land is on HRERA Gurugram's register as of 28 November 2026, so there is nothing for an individual to buy.

What are the main pros and cons of Global City?

Pros: a government developer, about 400 m of Dwarka Expressway frontage, Rs 940 crore committed to phase one (CM, April 2025) and free HSIIDC upkeep until 31 December 2033. Cons: no published auction outcome, conflicting progress figures (80% in August 2026 against about 70% in November 2026), slipped targets and access roads that are still plans.

What is HSIIDC's track record with other estates?

Maruti Suzuki's 800-acre plant at HSIIDC's IMT Kharkhoda began production in February 2025. The High Court upheld HSIIDC's rejection of top bids at IMT Sohna in December 2024. An Assembly committee citing CAG questioned extensions on a Sector 16 Gurugram plot in February 2024. HSIIDC's accounts are audited only up to 2021-22.

Has Global City been delayed?

Yes. A target to auction 250 acres by end-November 2022 was missed. HSIIDC's MD gave October 2026 for phase-one infrastructure in September 2023; the CM later set December 2026. A News24 report in August 2026 mentioned June 2027. The minister said about 70% of phase one was done on 21 November 2026.

Are there any pending court cases on Global City land?

The Gharauli Khurd PIL was dismissed on 19 January 2023, and two writs by politicians ended in November 2022. HSIIDC's September 2023 bid document says that auction was subject to the outcome of CWP No. 6797 of 2023, and no final order in that case has been published. Ask any seller for the latest order.

Has any developer won a plot in Global City?

No official result has been published. The Daily Jagran reported in April 2025 that three tenders drew no bids, while ThePrint quoted an unnamed officer in August 2026 saying developers had shown interest in or acquired parcels. The minister said in November 2026 that allotment would follow phase-one completion. No source names a winner.

Can I read resident reviews of Global City?

Not yet. No homes exist inside the township, and no housing project on its land is registered with HRERA Gurugram as of 28 November 2026. Reviews you find online usually describe projects in neighbouring sectors that only use the Global City name nearby. Check the HRERA register entry before trusting any such review.

More on Global City

Related on Property Nivesh

Talk to an advisor about Global City

Tell us what you are looking for around Global City. Our advisor calls you with what is confirmed so far on auctions, projects and prices, and answers your questions.

Unbiased advice. Your data is never sold to builders or brokers.

Sources

  • HSIIDC, Bid Document/Brochure (Site C2, 58.11 acres), Global City, Gurugram, 20 September 2023
  • Punjab and Haryana High Court, CWP-8814-2007, Gram Panchayat Gharauli Khurd v. Union of India, order of 19 January 2023
  • Government of Haryana (DIPRL), Press note 52 and Press notes 293 on Global City, 11 April 2025 and 12 August 2026
  • HRERA Gurugram, Registered projects list, Gurugram, read 28 November 2026
  • Government of Haryana, Finance Department, Profile of State Public Enterprises 2023-24 and 2024-25 (HSIIDC), March 2026
  • The Times of India, Global City roads to link Dwarka Expressway, Delhi-Gurgaon eway, Pataudi Road, 21 November 2026
  • ThePrint, The long road to Gurugram's ambitious 'city within a city', 14 August 2026
  • The Tribune, Probe HSIIDC ex-MD's decisions: House panel, 28 February 2024

Property Nivesh is an independent property research and advisory site. This guide is not the website of HSIIDC or the Government of Haryana and is not connected with them or with any developer. Facts are as of 28 November 2026 and come from the sources listed on each page. Pictures marked "Illustrative image" are AI-generated and do not show Global City.

Chat with Us +91 79824 13588
A family looking at a scale model of new residential towers

Auction and launch alerts

Get Global City auction and launch alerts first

Leave your number and our advisor calls you when the next Global City auction is notified or a project on its land opens for booking.

Unbiased advice. Your data is never sold to builders or brokers.

Prefer WhatsApp? Chat with Us: +91 79824 13588

Free property updates

Never Miss a Property Opportunity!

Get the latest property news, investment opportunities, new launches and government plot scheme updates directly.

Where would you like to receive updates?
Send me

Free. Only updates worth your time, and you can stop any time. We never sell or share your number or email. By subscribing you agree to get Property Nivesh updates on the channel you chose. Stop updates

Rent, sell or advertise

Tell us what you need

Pick one, answer a few questions, and our team calls you back. It is free.

What would you like to do?