Global City Gurugram, Dwarka Expressway
Global City Gurugram RERA status: the Dwarka Expressway township, its projects and how to check
As of 28 November 2026, Global City Gurugram, the government township beside the Dwarka Expressway, has no RERA registration. No housing project on its land appears on HRERA Gurugram's register either. That is expected: Global City is a land township, not a housing project, so homes can only come later through developer projects that must register first.
The developer is the Haryana State Industrial and Infrastructure Development Corporation (HSIIDC), wholly owned by the Haryana government. It is building out about 1,000 acres in parts of Sectors 36, 36B, 37 and 37B, laying trunk roads and services and selling large parcels by e-auction to companies. Individuals cannot buy land from it.
This page sets out what the register shows, what the RERA Act asks of whoever builds homes here, which approvals are on record and which are only reported, and how to run your own check.
- Township RERA registration
- None on HRERA Gurugram, 28 November 2026
- Projects on Global City land
- 0 in HRERA Gurugram list of 1,108 rows
- HSIIDC's own HRERA registrations
- 2, both Express Greens, IMT Manesar
- Developer
- HSIIDC, 100% owned by Haryana government
- Environmental clearance
- Reported May 2024; official record not published
- Last PIL on the land
- Dismissed by High Court, 19 January 2023
The short answer
- HRERA Gurugram's registered-projects list, read on 28 November 2026, held 1,108 rows and no project in Global City.
- HSIIDC is a registered promoter in Gurugram only for two Express Greens certificates in IMT Manesar, dated 19 September 2022.
- Section 3(1) of the RERA Act bars any promoter from advertising, booking or selling units before registering the project.
- HSIIDC's bid document of 20 September 2023 makes every allottee comply with the RERA Act 2016 and the Haryana RERA Rules.
- The High Court dismissed the last PIL on the land on 19 January 2023, but a later writ, CWP No. 6797 of 2023, has no published outcome.
- An environmental clearance was reported in May 2024, but no official clearance letter or number has been published.
Is Global City RERA registered?
No. HRERA Gurugram's registered-projects list, read on 28 November 2026, held 1,108 rows and none of them was a Global City project or a Global City registration by HSIIDC. RERA, the Real Estate (Regulation and Development) Act 2016, registers projects that sell plots, flats or buildings to buyers, and HSIIDC sells none of those to the public here.
HRERA is the Haryana Real Estate Regulatory Authority, and its Gurugram bench keeps the register for the district. HSIIDC does appear on it as a promoter, but only twice. Both certificates, dated 19 September 2022, cover Express Greens housing in IMT Manesar Sectors M1 and M1A. Neither touches Global City.
In Global City, HSIIDC sells whole land parcels, freehold, to firms. Its 2023 offers ran from a 4.84-acre school site to an 86.05-acre mixed-use parcel. No HRERA ruling on whether such parcel sales need registration has been published, so this page makes no claim either way. The overview explains how the township is set up.
| Item | Status | Source |
|---|---|---|
| Global City township (HSIIDC) | Not on the registered-projects list | HRERA Gurugram list, 28 November 2026 |
| Projects in Global City or Sectors 36B, 37A, 37B | None (0 of 1,108 rows) | HRERA Gurugram list, 28 November 2026 |
| HSIIDC as promoter in Gurugram | 2 certificates, Express Greens, IMT Manesar, 19 September 2022 | HRERA Gurugram list, 28 November 2026 |
| Projects naming the Global City villages | None in our copy of the register | Property Nivesh count, 9 October 2026 |
| Application for registration on Global City land | None on record | HRERA Gurugram list and HSIIDC notices, 28 November 2026 |
| Allotment of a Global City parcel to a developer | No official result published | HSIIDC; reports conflict |
Is any project on Global City land registered or waiting for registration?
None on record. Neither the register nor any HSIIDC notice, court order or news report shows a project on Global City land that is registered or has applied. A project can only follow once a developer holds an allotted parcel, and no allotment has been officially published so far.
HSIIDC ran e-auction rounds in 2023, but no result, winner or bid amount has been published. Reports conflict. The Daily Jagran said on 13 April 2025 that three tenders in two years drew no bids. ThePrint on 14 August 2026 quoted an unnamed officer saying developers had shown interest in or acquired parcels. On 21 November 2026, The Times of India quoted minister Rao Narbir Singh as saying land allotment to investors would follow phase-one works. Our timeline tracks each date.
Neighbours on the register are not Global City
Registered projects do sit close by. Max Estates' Estate 361 is on HRERA Gurugram's register at Village Harsaru, Sector 36; the developer calls the location Sector 36A, and its map marks a 'Planned Global City' nearby. No source places that project on Global City land.
A register search for 'Global City' also returns nine certificates named 'Signature Global City 37D', in Sector 37D, village Gadauli Kalan. Those are Signature Global's own colonies and have nothing to do with HSIIDC's township.
Illustrative image Do projects inside Global City need RERA registration?
Yes, if they sell homes or other units to buyers. Section 3(1) of the RERA Act bars any promoter from advertising, marketing, booking, selling or offering for sale any plot, apartment or building in a project in a planning area without first registering it. A developer building flats on an auctioned Global City parcel is such a promoter.
- Public bodies can be promoters: section 2(zk)(iii) counts a development authority or other public body as a promoter for allottees of plots it owns or that the government places at its disposal.
- Each phase stands alone: the explanation to section 3 treats every phase of a phased project as a separate project that needs its own registration.
- Small projects are exempt: registration is not needed where the land does not exceed 500 sq m or the project has no more than eight apartments, counting all phases.
Global City's parcels are far beyond that exemption. The smallest site HSIIDC offered in 2023 was the 4.84-acre school plot, printed beside a figure of 29,352 sq m. A housing project on any of the mixed-use parcels would sit well above 500 sq m.
HSIIDC also writes RERA into its own terms. Its bid document for Parcel C2, dated 20 September 2023, obliges the allottee to comply with the RERA Act 2016, the Haryana RERA Rules, the Haryana Building Code 2017 and the Haryana Apartment Ownership Act 1983. So the registration duty for homes sits with the developer that builds them.
What must happen on a Global City parcel before homes can be sold
Several HSIIDC conditions come before any sale. The allottee needs a zoning plan from HSIIDC and then an approved building plan, and cannot build before both. It may sell or lease built space only after paying in full for the land phase where that space lies. RERA registration comes on top of these steps.
- HSIIDC accepts a bid and issues a Regular Letter of Allotment (RLA). The allottee signs acceptance and the agreement within 90 days, extendable by 30 days with approval.
- HSIIDC offers possession only once a motorable road, water, sewerage and construction power reach the site. Physical possession of a phase follows full payment for that phase.
- The allottee obtains a zoning plan from HSIIDC and an approved building plan.
- Buildings must be certified GRIHA (Green Rating for Integrated Habitat Assessment) 4-star or 5-star, with no extra FAR, or floor area ratio, for the rating.
- Before advertising or taking money for homes, the developer registers each phase with HRERA Gurugram.
- Completion of each phase is due within 5 years of physical possession, extendable under Haryana's urban areas law on a renewal fee.
A parcel can change hands only with HSIIDC's prior permission, after full payment and a conveyance deed, and the new owner inherits third-party commitments and RERA approvals. HSIIDC keeps first charge on mortgaged land for its dues. The payment plan page explains the instalments behind the full-payment rule.
Which approvals does the township have?
On record are a land title the High Court left undisturbed in January 2023, a 2018 development plan revision approved in principle, a phase-one works contract reported as awarded, and an environmental clearance that was reported but whose official letter is not public. Each carries a different level of proof, shown in the table.
| Approval or step | What the record shows | Status | Source and date |
|---|---|---|---|
| Land title | Reliance Haryana SEZ returned the land to HSIIDC by deed of 29 August 2014 | On record | Punjab and Haryana High Court order, 19 January 2023 |
| Gharauli Khurd PIL (CWP-8814-2007) | Dismissed as infructuous | Closed | High Court order, 19 January 2023 |
| Writs by Ajay Chautala and Kuldeep Bishnoi | Withdrawn; disposed of as not pressed | Closed, 15 and 21 November 2022 | Hindustan Times, 21 January 2023 |
| CWP No. 6797 of 2023 | 2023 auction made subject to its outcome (order of 25 May 2023) | Outcome not published | HSIIDC C2 bid document, 20 September 2023 |
| GMUC-2031 plan revision (Special Zone, mixed use, 300% global FAR) | Approved in principle; public objections invited to 30 November 2018 | Final notification not published | Government of Haryana, 13 November 2018 |
| Environmental clearance | Reported granted by the Union environment ministry | Official record not published | Moneycontrol report, 10 May 2024 |
| Phase-one infrastructure contract | Reported awarded at about Rs 940 crore | Contractor not named | Construction World, 26 September 2023 |
| Roads to Pataudi Road and CPR | Tender formalities completed | Works not yet reported | UNI, 11 November 2026 |
| HRERA registration | None for the township or any project | Not registered | HRERA Gurugram, 28 November 2026 |
The land history is a matter of record. HSIIDC acquired the land between 2003 and 2006 for a special economic zone, conveyed 1,383.68 acres to Reliance Haryana SEZ on 26 April 2007, and took it back by deed on 29 August 2014 after the SEZ was shelved. The reviews page covers the cases and HSIIDC's wider record.
An OC, or occupation certificate, is the permission to live in a finished building, issued in Haryana by DTCP, the Directorate of Town and Country Planning. No building in Global City is anywhere near that stage.
Illustrative image Which records are missing or unconfirmed?
Four items stop the paperwork looking complete: the final notification of the 2018 plan revision, the environmental clearance letter, the status of CWP No. 6797 of 2023, and the result of any auction. None is a red flag by itself, but each is a fair question to put to HSIIDC or a future developer.
- Planning: GMDA's 2018 proposal gave a 300% global FAR, and The Tribune described the township as FAR 3.0 in October 2026, while HSIIDC's 2023 parcels carried FARs of 3.00 to 6.17. No final notification is public. The master plan page explains the layout figures.
- Environment: news reports say the Union environment ministry granted clearance in May 2024, but no clearance number, date or conditions are public.
- Courts: HSIIDC's September 2023 bid document says the auction is subject to the outcome of CWP No. 6797 of 2023. Who filed it and where it stands are not public.
- Allotment: no winner, winning bid or allotment letter for any Global City parcel has been published.
Papers to request later
When a developer does launch here, ask for HSIIDC's allotment letter, proof of payment for the phase, the zoning plan and the approved building plan, alongside the HRERA certificate. The brochure and documents page explains which papers bind an allottee.
How does a buyer check a project on HRERA Gurugram?
Start from the regulator, not the advert. Find the project on HRERA Gurugram's list of registered projects, then match the promoter, address, sector and village with what you were told. For anything sold as Global City, also confirm the land is an HSIIDC parcel and that the developer has paid for its phase.
- Note the exact project name, developer and registration number from the sales material. If no number is printed, ask for it in writing.
- Open the registered-projects list on HRERA Gurugram's own website. Search by promoter name and by sector, not only by the marketing name.
- Read the address. Global City lies in parts of Sectors 36, 36B, 37 and 37B, in the villages Khandsa, Narsinghpur, Mohammadpur Jharsa, Garauli Khurd and Garhi Harsaru.
- Check that the certificate is current; the list also carries lapsed and superseded certificates.
- Compare the phase, units and completion date on the certificate with the offer. Each phase needs its own registration.
- Ask the developer for HSIIDC's allotment letter and zoning plan for the parcel, and see who is named as landowner.
- Before any payment, confirm the agreement for sale states carpet area, the usable floor area within the walls that RERA uses, and that no more than 10% of the price is sought before that agreement is signed.
Our guide to HSIIDC's plot scheme explains how its land sales work across Haryana, which helps when reading a developer's land papers. For registered projects along the wider corridor, see our Dwarka Expressway locality page.
Warning signs while no Global City project is registered
Until a registration appears, read any offer of a flat, plot or pre-launch unit said to be inside Global City with care. Section 3(1) bars advertising, booking or selling before registration, and no project on this land is registered. A token, cheque or EOI (expression of interest) amount paid against such an offer would go to an unregistered project.
- The project is called Global City, but its HRERA address shows Sector 37D, 36A or another sector. It may be a genuine nearby project, but it is not on HSIIDC's land.
- A small plot in Global City is offered to an individual. HSIIDC's 2023 sites ran from 4.84 to 86.05 acres, sold only to firms passing a net-worth test, and parcels cannot be subdivided.
- A seller names a developer as the parcel's winner. No official auction result has been published.
- A per sq ft price is quoted for Global City homes. No home project exists here, so no home price exists either.
The how to bid page sets out the company route through HSIIDC's e-auction and the separate route a home buyer will take once a registered project exists.
When could a Global City project appear on the register?
No one has published a date, and we won't guess one. The minister quoted on 21 November 2026 said allotment to investors would follow phase-one works. After allotment come possession, a zoning plan, building plans and then RERA registration, so the register is the last place a project will show up, not the first.
The status table reflects HRERA Gurugram's list as of 28 November 2026 and will be updated when a Global City project appears. If you would like an alert when HSIIDC notifies an auction or a project on Global City land is registered, leave your details through our contact page. Common questions are gathered on the FAQs page.
Questions people ask
Is Global City Gurugram RERA registered?
No. HRERA Gurugram's registered-projects list, read on 28 November 2026, had 1,108 rows and no Global City project or township registration by HSIIDC. HSIIDC is a registered promoter in Gurugram only for two Express Greens certificates in IMT Manesar. Global City itself is a land township whose parcels are sold by e-auction to companies, so homes there will need their own developer registrations.
Can I buy a flat in Global City today?
Not inside the township. No project on Global City land is on HRERA Gurugram's register, and no auction result naming a developer has been published. Homes can only come through a developer project on an auctioned parcel, registered with HRERA Gurugram before any sale. Anything offered as a Global City flat today has no registration on the register.
Must a developer register its Global City housing project under RERA?
Yes. Section 3(1) of the RERA Act bars advertising, booking or selling units before registration, and each phase counts as a separate project. HSIIDC's bid document of 20 September 2023 also obliges allottees to follow the RERA Act, the Haryana RERA Rules, the Haryana Building Code 2017 and the Haryana Apartment Ownership Act 1983.
Are registered projects in Sector 36A or 37D part of Global City?
No source says so. Estate 361 is registered at Village Harsaru, Sector 36, and no source puts it on Global City land. The nine certificates named Signature Global City 37D are in Sector 37D, village Gadauli Kalan, and belong to Signature Global, not HSIIDC. Global City lies in parts of Sectors 36, 36B, 37 and 37B.
Does Global City have environmental clearance?
It was reported. A Moneycontrol report of 10 May 2024, carried by other trade sites, said the Union environment ministry had granted clearance to the project. The clearance letter, its number, date and conditions are not in public official records. Ask HSIIDC, or any developer that later launches on the land, for a copy before relying on it.
Are there court cases on Global City land?
The main ones ended. The High Court dismissed the Gharauli Khurd PIL on 19 January 2023, and two writs were withdrawn or not pressed in November 2022. HSIIDC's September 2023 bid document, however, made that auction subject to the outcome of CWP No. 6797 of 2023, and no outcome for that writ has been published.
How will I know when a Global City project is registered?
Check HRERA Gurugram's registered-projects list, searching by sector, village and promoter rather than by a marketing name. Global City sits in parts of Sectors 36, 36B, 37 and 37B. This page will be updated when a project appears, and readers can ask through our contact page for an alert when an auction is notified or a project registers.
More on Global City
- Global City: overview What Global City is, who builds it, where it stands today and who can buy what, in one place.
- Global City: price Every Global City reserve price on record, per acre and per sq yd, and why no flat price exists yet.
- Global City: payment plan HSIIDC's 2023 terms: 2% EMD, 10% in 15 days, then a lump sum with 8% rebate or instalments with interest.
- Global City: location Sectors, villages, roads open and planned, metro status and stated travel times for Global City.
- Global City: timeline Dated timeline of Global City Gurugram: land history, 2023 auction rounds, moved targets and what is next.
- Global City: reviews Global City weighed on facts: pros, cons, slipped targets, court cases and HSIIDC's record elsewhere.
- Global City: brochure What HSIIDC actually publishes for Global City, which papers bind, and how to spot a marketing copy.
- Global City: how to bid How HSIIDC's Global City e-auction works, who can bid, deposits and refunds, and how home buyers will book.
- Global City: master plan Land, phases, the reported land-use split, parcel FAR and coverage rules, and what the plan leaves out.
- Global City: plot sizes Every Global City parcel HSIIDC has offered, 4.84 to 86.05 acres, with FAR, permitted uses and conversions.
- Global City: infrastructure Roads, utility tunnel, water and green areas in Global City: what is on record and what is only announced.
- Global City: highlights Ten sourced facts on Global City Gurugram, sorted into what is on record and what is only announced.
- Global City: investment Corridor prices, rents, labelled analyst views and the real risks for Global City investors, with checks.
- Global City: faqs 25 plain answers on Global City: what it is, location, reserve prices, auctions, RERA and home buying.
Related on Property Nivesh
Talk to an advisor about Global City
Tell us what you are looking for around Global City. Our advisor calls you with what is confirmed so far on auctions, projects and prices, and answers your questions.
✓
Request received
A senior property advisor will reach you within 4 working hours. No spam, no builder hand-offs — your details stay with our advisory desk only.
You'll also get our property updates on WhatsApp, from +91 79824 13588.
Sources
- HRERA Gurugram, Registered projects list, Gurugram (1,108 rows read), 28 November 2026
- Government of India, Real Estate (Regulation and Development) Act 2016, Gazette, 26 March 2016
- HSIIDC, Bid Document/Brochure (Site C2, 58.11 acres), Global City, Gurugram, 20 September 2023
- Punjab and Haryana High Court, CWP-8814-2007, Gram Panchayat Gharauli Khurd v. Union of India, order of 19 January 2023
- Government of Haryana, DIPRL, GMDA public consultation on revising the FDP GMUC-2031 for Global City, 13 November 2018
- Moneycontrol, Global City project in Gurugram gets environment clearance from MoEF (as reposted by NAREDCO), 10 May 2024
- The Times of India, Global City roads to link Dwarka Expressway, Delhi-Gurgaon eway, Pataudi Road, 21 November 2026
Property Nivesh is an independent property research and advisory site. This guide is not the website of HSIIDC or the Government of Haryana and is not connected with them or with any developer. Facts are as of 28 November 2026 and come from the sources listed on each page. Pictures marked "Illustrative image" are AI-generated and do not show Global City.