Elevate Vista, Sector 63A Gurgaon

Elevate Vista payment plan, Sector 63A Gurgaon: draft stages and what you'd pay when

Elevate Vista in Sector 63A Gurgaon has no final payment plan yet. What exists is a draft allotment letter filed with HRERA Gurugram, the Haryana Real Estate Regulatory Authority's Gurugram office, and uploaded on 2 November 2026. It shows two options: a 10:40:50 down payment plan, or a construction-linked plan with eight stages.

Treat both as draft terms. HRERA approved the application on 2 November 2026 subject to conditions, but no registration number had been issued on 23 November 2026. Until one is, the project can't be sold and no one can lawfully take money for a flat.

No price has been published either, so this page works the stages out per Rs 1 crore of total price. Scale it up once a real figure exists.

By Divyangna Pathak, Property Nivesh Team Reviewed by Rakesh Mahajan Published Updated
Plan status
Draft only, inside the HRERA application
Down payment plan (draft)
10% booking, 40% on BBA, 50% on possession
Construction-linked plan (draft)
8 stages; the last six add up to 80%
Booking amount (draft)
Up to 10% of total price; no rupee figure
Price
Not published by the developer or in the filing
RERA status
Approved 2 Nov 2026; no number on 23 Nov 2026

The short answer

  • The only Elevate Vista payment terms on record are in a draft allotment letter uploaded to HRERA Gurugram on 2 November 2026.
  • The draft down payment plan is 10% on booking, 40% on BBA and 50% on possession.
  • The draft construction-linked plan fixes six stages that add up to 80% and leaves the first two as '<10%' each.
  • The booking amount is defined as up to 10% of the total price, which mirrors the RERA ceiling on money taken before an agreement for sale.
  • No price, rate per sq ft or rupee booking figure has been published by the developer or in the filing.
  • On 23 November 2026 the project had HRERA approval subject to conditions but no registration number, so no sale or booking is permitted.

What is the payment plan of Elevate Vista?

The only payment plan on record for Elevate Vista sits in a draft allotment letter inside the promoter's HRERA application. It offers a down payment plan of 10% on booking, 40% on BBA and 50% on possession, or a construction-linked plan, 'OR Any other plan duly approved by HARERA'. Elevate Homes has published no plan itself.

BBA means builder buyer agreement, the document RERA calls the agreement for sale. The promoter is Elevate Edition Realtech Private Limited, the company filing this Elevate Homes project. Because the letter is a draft and the registration certificate is still pending, the final plan could differ. Our RERA page tracks the certificate.

The two draft plans in the HRERA filing
PlanHow the money falls dueBasis
Down payment plan10% on booking, 40% on BBA, 50% on possessionDraft allotment letter, uploaded 2 November 2026
Construction-linked planEight calls from booking to possession, tied to building milestonesDraft allotment letter, uploaded 2 November 2026
Any other planOnly if approved by the authorityWording of the same draft letter
Developer's published planNoneElevate Homes website, read 23 November 2026
Draft terms from a pending application. Nothing here is a final offer.

Is the plan construction linked?

One of the two draft options is. The construction-linked plan in the filing has eight instalments, from booking through to possession, most of them tied to a building milestone such as the sub-structure or the finishing. The other option, the down payment plan, is tied to paperwork and possession instead of site progress.

  1. At booking, along with the allotment letter: shown as '<10%'
  2. After signing and registration of the agreement for sale, on commencement of construction: shown as '<10%'
  3. On completion of sub-structure, the work below ground: 7.5%
  4. On completion of super-structure, the frame above ground: 25%
  5. On completion of MEP, meaning mechanical, electrical and plumbing work: 10%
  6. On completion of finishing: 20%
  7. On completion of internal development works: 12.5%
  8. On possession: 5%

The sums don't close yet

The last six stages add up to 80%. That leaves 20% for the first two, yet each is written as less than 10%, and two figures below 10% can't reach 20%. It reads like a placeholder. The final allotment letter has to state exact percentages, so ask for them in writing.

An illustrative picture of premium high-rise residential towers under construction with cranes and machinery on Golf Course Extension Road in Sector 63A Gurugram Illustrative image
Illustrative image, not a picture of Elevate Vista.

How much is paid at booking?

The draft says the booking amount is 'up to 10% of the Total Price'. No rupee figure exists because no price exists. Under the down payment plan the booking stage is a flat 10%; under the construction-linked plan it's shown as less than 10%. The developer has announced no EOI, an expression of interest collected ahead of a launch.

The draft also sets a sequence. The allottee sends consent and the amount due by cheque, demand draft or RTGS within 30 days of the allotment letter's dispatch, and the agreement for sale is signed within 30 days of allotment. A collection account at HDFC Bank in the promoter company's name appears in both the draft letter and the application form. The booking page walks through that paperwork.

Nothing is payable today

The project is not RERA registered. Under RERA no booking or advertising is allowed before registration, so the steps above describe a draft, not a live process. Be careful with anyone asking for a cheque or transfer in this project's name before the certificate is issued.

Elevate Vista payment schedule on a sample price

With no price list, a per-crore schedule is the honest way to show the stages. On every Rs 1 crore of total price, the draft down payment plan asks Rs 10 lakh at booking, Rs 40 lakh at the agreement and Rs 50 lakh at possession. The construction-linked plan spreads the same sum over eight calls.

Draft stages worked on Rs 1 crore of total price (a unit for arithmetic, not a quoted price)
PlanStageShareAmount per Rs 1 croreCumulative
Down paymentOn booking10%Rs 10 lakh10%
Down paymentOn BBA40%Rs 40 lakh50%
Down paymentOn possession50%Rs 50 lakh100%
Construction-linkedBooking, with allotment letter<10% (draft)Under Rs 10 lakhNot fixed
Construction-linkedAgreement registered, construction starts<10% (draft)Under Rs 10 lakh20% if the plan totals 100%
Construction-linkedSub-structure complete7.5%Rs 7.5 lakh27.5%
Construction-linkedSuper-structure complete25%Rs 25 lakh52.5%
Construction-linkedMEP complete10%Rs 10 lakh62.5%
Construction-linkedFinishing complete20%Rs 20 lakh82.5%
Construction-linkedInternal development works complete12.5%Rs 12.5 lakh95%
Construction-linkedOn possession5%Rs 5 lakh100%
Cumulative figures for the construction-linked plan assume the first two stages total 20%, which the draft does not state.

Two things stand out. The down payment plan puts half the price with the promoter by the agreement, years ahead of the proposed possession date of 30 November 2034 in the draft letter. The construction-linked plan reaches a similar level, 52.5%, only when the super-structure is complete.

Multiply the table by your own number once a price is out. Our price page records what is and isn't published, and the floor plan page has the carpet areas any rate would apply to.

What does RERA say about advances?

RERA is the Real Estate (Regulation and Development) Act. Its Section 13 stops a promoter from taking more than 10% of a flat's cost before the agreement for sale is in place. The draft letter's booking cap of 'up to 10% of the Total Price' sits exactly at that ceiling, not above it.

Look at how each draft plan lines up with the rule. In the down payment plan, the 40% falls due 'on BBA', so it arrives with the agreement and not ahead of it. In the construction-linked plan, the second call comes after signing and registration of the agreement. When real demand letters appear, check they keep that order.

There's an earlier gate too. Before registration, the 10% rule doesn't even come into play, because no booking is allowed at all. On 23 November 2026, HRERA's page for the application read 'APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS' and showed no registration number. The authority's list of registered projects, read the same day, did not include Elevate Vista.

An illustrative picture of a laptop and neatly stacked blank papers on a home dining table in warm light Illustrative image
Illustrative image, not a picture of Elevate Vista.

What does the total price include, and what is extra?

The draft allotment letter defines the Total Price as inclusive of IDC and EDC, car parking usage charges, PLC, government fees, taxes and levies, common areas and GST. Stamp duty, registration charges and other associated charges are stated as extra, payable when the agreement for sale and the conveyance deed are registered.

EDC and IDC are external and infrastructure development charges, levies tied to the licence from DTCP, Haryana's Department of Town and Country Planning. PLC is a preferential location charge, a premium for a better-placed flat. An all-in definition is helpful on paper. Confirm the final agreement keeps it and adds no separate heads.

Haryana stamp duty and registration fee per Rs 1 crore of value
BuyerStamp duty rateDuty per Rs 1 croreRegistration fee
Man7%Rs 7 lakh1%, capped at Rs 50,000
Woman5%Rs 5 lakh1%, capped at Rs 50,000
Joint (man and woman)6%Rs 6 lakh1%, capped at Rs 50,000
These sit outside the Total Price in the draft letter. They are standard Haryana rates, not project figures.

For your own figure, use our stamp duty calculator once a price is known.

Home loan disbursal and pre-EMI on these plans

A lender usually releases a home loan in parts, against each demand the builder raises, so the plan you choose decides how fast the loan is drawn. Until possession, many borrowers pay pre-EMI, which is interest only on the amount disbursed so far. Neither the filing nor the developer names any lender for Elevate Vista yet.

Under the draft down payment plan, 50% is due by the agreement. If a loan funds that, interest starts early on a large sum and runs through a build the filing dates from 1 January 2027 to 31 December 2034. Under the construction-linked plan the loan is drawn as the towers rise, so interest builds more slowly, though it depends on actual site progress.

  • Has the bank approved this project for lending? That can only follow registration.
  • How much of your own money must go in before the first disbursal?
  • Is it pre-EMI or full EMI during construction, and can you choose?
  • Does the bank release money on the builder's demand alone, or after checking the stage on site?
  • What happens to your interest cost if a stage is late?

You can test numbers with our home loan EMI calculator and check borrowing capacity with the eligibility calculator.

What to check in the builder buyer agreement

The draft letter already shows the clauses that matter most for your money: late payment interest, forfeiture on cancellation, a carpet area tolerance and the conveyance timeline. A separate draft builder buyer agreement also sits in the HRERA application. We haven't read it yet, so match every clause below against the final registered version.

  • Late payment: the draft charges interest at 'State Bank of India highest marginal cost of lending rate plus two percent'. Ask whether the promoter pays the same rate if possession is late.
  • Cancellation by you: the promoter may forfeit the booking amount, up to 10% of the total price, plus delayed-payment interest. The balance is to be returned within ninety days. On each Rs 1 crore, up to Rs 10 lakh is at stake.
  • Carpet area, the usable area inside the flat's walls and the measure RERA uses: it may change by up to 5% after final plans, adjusted at the same rate per sq ft. On a 2,194.5 sq ft home that is about 109.7 sq ft; on 1,608.3 sq ft, about 80.4 sq ft.
  • Dates: the draft proposes the OC (occupation certificate, the permission to occupy) by 30 September 2034, possession by 30 November 2034 and completion by 31 December 2034. See which payment stage hangs on which date.
  • Conveyance deed: within 3 months of the promoter receiving the total price, and 'no administrative charges will be charged' except as stated.
  • Annexures: the payment plan and the HRERA-approved schedule of development are listed as attachments. Make sure every percentage in the plan is filled in, not left as a placeholder.

Milestone-based plans only work as well as the builder's pace. Our reviews page sets out the delivery record of the earlier Elevate projects, and the launch date page follows the timeline for this one.

What is still not published about the payment plan

Quite a lot. As of 23 November 2026 there is no price, no rate per sq ft, no rupee booking amount and no developer-issued payment plan for Elevate Vista in Sector 63A Gurgaon. The filing's own rate and total price fields are blank. Everything on this page rests on draft documents inside a pending application.

  • The exact percentages for the first two construction-linked instalments
  • Whether the final plan matches the draft, or is 'any other plan' the authority approves
  • Any EOI amount or process
  • Any lender tie-up or bank approval for the project
  • Any terms for Phase II, which is kept for future development

Who each draft plan would fit

On the draft terms alone, the down payment plan asks for more money sooner, so it fits buyers with funds ready. The draft shows no discount attached to it. The construction-linked plan ties most payments to visible progress, which usually sits better with loan-funded buyers. Neither is a recommendation; the final terms decide.

For the full picture, start at the Elevate Vista overview or scan the FAQs. If you'd like the filed documents explained, get in touch with Property Nivesh.

Questions people ask

What is the Elevate Vista payment plan?

No final plan exists. A draft allotment letter in the HRERA application, uploaded on 2 November 2026, shows two options: a down payment plan of 10% on booking, 40% on BBA and 50% on possession, or a construction-linked plan in eight stages. The letter also allows any other plan approved by the authority. Elevate Homes hasn't published a plan of its own.

How much is the Elevate Vista booking amount?

The draft allotment letter describes the booking amount as 'up to 10% of the Total Price'. There's no rupee figure because no price has been published by the developer or in the filing. As a unit for arithmetic, 10% works out to Rs 10 lakh on every Rs 1 crore of price. Nothing is payable while the project remains unregistered.

Is there a construction-linked plan at Elevate Vista?

Yes, as one of two draft options. It runs from booking to possession in eight calls. Six are fixed: 7.5% at sub-structure, 25% at super-structure, 10% at MEP, 20% at finishing, 12.5% at internal development works and 5% at possession. Those total 80%. The first two are each shown as '<10%', so the exact split is still open.

Can money be paid for Elevate Vista now?

No. HRERA approved the application on 2 November 2026 subject to conditions, but no registration number had been issued on 23 November 2026. RERA doesn't allow booking or advertising before registration. The draft letter names a collection account, yet that only becomes relevant after the certificate. Treat any earlier request for a cheque or transfer with caution.

Does the Elevate Vista total price include GST, parking and EDC?

According to the draft allotment letter, yes. Its Total Price is described as inclusive of IDC and EDC, car parking usage charges, PLC, government fees, taxes and levies, common areas and GST. Stamp duty and registration charges are extra. In Haryana, stamp duty is 7% for men, 5% for women and 6% for joint buyers, with a registration fee capped at Rs 50,000.

What happens to my money if I cancel after booking?

The draft letter lets the promoter forfeit the booking amount, described as up to 10% of the total price, along with any delayed-payment interest. The remaining money paid is to be returned within ninety days of cancellation. On every Rs 1 crore of price, that puts up to Rs 10 lakh at stake. Check the final registered agreement for the same wording.

How does a home loan work with these draft plans?

Lenders generally release a loan in parts against the builder's demands, so the plan sets the pace. The draft down payment plan needs 50% by the agreement, which means early, large disbursal. The construction-linked plan draws the loan as the building rises. Before possession, borrowers often pay pre-EMI, interest on the disbursed amount only. No lender tie-up is published for this project.

More on Elevate Vista

Related on Property Nivesh

Talk to an advisor about Elevate Vista

Tell us what you are looking for in Elevate Vista. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.

Unbiased advice. Your data is never sold to builders or brokers.

Sources

  • HRERA Gurugram (promoter upload), Draft allotment letter, Elevate Vista Phase I, uploaded 2 November 2026
  • HRERA Gurugram, Comprehensive Project Details, Elevate Vista (status and hearing proceedings of 2 November 2026), read 23 November 2026
  • HRERA Gurugram, Form REP-I preview for Elevate Vista Phase I, submitted 7 October 2026, read 23 November 2026
  • HRERA Gurugram, Registered projects register (Gurugram), read 23 November 2026
  • Elevate Homes, website home and projects pages, read 23 November 2026
  • Construction World, Elevate Homes to Develop Premium Project in Gurugram, 2 September 2026

Property Nivesh is an independent property research and advisory site. This guide is not the website of Elevate Homes (platform of Hines and Conscient Infrastructure) and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.

Chat with Us +91 79824 13588
A couple going through a price list with a property advisor

Latest price list

Get the latest price list for Elevate Vista

Prices and payment plans change often. Our advisor shares the current Elevate Vista price list and books a site visit if you want one.

Unbiased advice. Your data is never sold to builders or brokers.

Prefer WhatsApp? Chat with Us: +91 79824 13588