Elevate Vista booking, Sector 63A Gurgaon: steps, amount, documents and refund terms
Booking for Elevate Vista in Sector 63A Gurgaon had not opened on 23 November 2026. HRERA Gurugram approved the Phase I application on 2 November 2026 subject to conditions, but no registration number had been issued. Under RERA, a project cannot be sold or advertised before it is registered.
What does exist is a draft allotment letter that the promoter filed with HRERA. It shows how a booking would work: a booking amount of up to 10% of the total price, 30 days to respond and sign the agreement, and a ninety-day refund clock after cancellation. These are draft terms, not an offer.
This page goes through each step, the paperwork and the refund rules. Elevate Vista is the Sector 63A project of Elevate Homes, the housing platform of Hines and Conscient.
- Booking status
- Not open on 23 November 2026
- HRERA status
- Approved 2 November 2026; certificate pending
- Booking amount (draft)
- Up to 10% of the total price; no rupee figure
- EOI amount
- None published
- Time to respond after allotment (draft)
- 30 days from dispatch of the allotment letter
- Refund of balance on cancellation (draft)
- Within ninety days; booking amount can be forfeited
The short answer
- On 23 November 2026 Elevate Vista had HRERA approval subject to conditions but no registration number, so no booking could lawfully be taken.
- The draft allotment letter defines the booking amount as up to 10% of the total price, and no price or EOI amount has been published.
- Under the draft, the buyer has 30 days from the allotment letter to send consent and the amount due, and to sign and register the agreement for sale.
- If a buyer cancels, the draft lets the promoter forfeit the booking amount and delayed-payment interest, and return the balance within ninety days.
- Stamp duty and registration charges are outside the total price in the draft and are paid when the agreement and conveyance deed are registered.
- Environment clearance, one of the listed annexures to the allotment letter, was applied for on 23 June 2026 and had not been received at filing.
Can you book Elevate Vista in Sector 63A Gurgaon today?
No. On 23 November 2026 HRERA Gurugram's project page showed Elevate Vista as 'approved and ready for certificate issuing process', with the registration number field still empty. HRERA is the Haryana Real Estate Regulatory Authority. It enforces RERA, the 2016 law that governs sales of homes under construction. Until the certificate is issued, no booking can lawfully be taken.
The certificate is tied to conditions from the 2 November 2026 hearing: corrections to the filed forms, and three separate security deposits of Rs 25 lakh each, which the order allows as demand drafts. We also read the live list of registered projects on 23 November 2026. Neither Elevate Vista nor its promoter, Elevate Edition Realtech Pvt Ltd, was on it. Our RERA page tracks the certificate, and the launch date page covers timing.
What this means for a buyer
The developer had announced no sales, EOI or price as of 23 November 2026. If someone asks for a cheque for this project before a registration number shows on HRERA's register, that request has no basis in anything the developer or the regulator has published.
How do I book a home in Elevate Vista? Steps from enquiry to registration
Once the project is registered, the route in the draft allotment letter is short. You pay the booking amount and receive an allotment letter. You send consent and the instalment due within 30 days, then sign and register the agreement for sale. The table sets each stage against what is actually on record.
| Step | What normally happens | On record for Elevate Vista (23 November 2026) |
|---|---|---|
| 1. Enquiry | Buyer asks for price sheet, plans and RERA details | No price, brochure or registration number published |
| 2. Site visit and document check | Buyer sees the site and reads the filed documents | Site is in village Ullawas, Sector 63A; filing gives likely construction start as 1 January 2027 |
| 3. EOI or application | Buyer applies with a token or booking amount | No EOI announced; no sale allowed before registration |
| 4. Allotment letter | Promoter allots a specific flat | Draft: consent and amount due within 30 days of dispatch, by cheque, demand draft or RTGS |
| 5. Agreement for sale | Agreement signed and registered | Draft: within 30 days of allotment; stamp duty and registration extra |
| 6. Instalments | Paid as per the chosen plan | Draft: down payment plan or construction-linked plan, or any plan HRERA approves |
| 7. Possession and conveyance deed | Handover, then title transfer | Draft: proposed possession 30 November 2034; conveyance deed within 3 months of receiving the total price |
Two things stand out. The draft gives the same 30 days for the buyer's consent and for the agreement for sale, so the window after allotment is tight. And the draft agreement itself, filed as the builder-buyer agreement or BBA, is a separate document we have not read. Ask for it before paying anything.
Illustrative image How much is the Elevate Vista booking amount, and is there an EOI amount?
No rupee figure exists. The draft allotment letter defines the booking amount only as 'up to 10% of the Total Price', and no price has been published by the developer or in the filing. No EOI amount has been announced either. An EOI, or expression of interest, is a pre-launch token some developers collect.
That 10% ceiling matches the law. RERA does not let a promoter collect more than 10% of the price before the agreement for sale. In the draft down payment plan the split is 10% on booking, 40% on the BBA and 50% on possession. The draft also carries a construction-linked option, and the payment plan page sets out both.
The draft says the total price is meant to include EDC and IDC (external and infrastructure development charges paid to the state), car parking usage charges, PLC (preferential location charges for a better floor or view), common areas, government levies and GST. Since the rate field in the draft is blank, the price page explains what is and isn't known.
What documents are needed to book Elevate Vista?
The buyer-side list, meaning the application form and identity papers, hasn't been published. Ask the developer for it once sales open. What the HRERA filing does show is the set of documents the promoter is supposed to attach to the allotment letter. Treat that list as your checklist of what to receive.
| Annexure | Status on record |
|---|---|
| Payment plan | Draft plans filed; final plan needs HRERA approval |
| HRERA-approved schedule of development | Filing shows construction from 1 January 2027 and completion by 31 December 2034 |
| Location plan | Site in revenue estate of village Ullawas, Sector 63A |
| Floor plan | Tower floor plans are in the HRERA application |
| Licence | DTCP Licence No. 43 of 2026 dated 10 March 2026, valid up to 9 March 2031 |
| Building plan approval | Phase I plans approved 6 October 2026, valid up to 5 October 2031 |
| Environment clearance | Applied 23 June 2026; not yet received at filing |
| Draft agreement for sale | Filed with HRERA; not read by us |
| Board resolution | Not seen by us |
| Specifications and amenities | Listed in Form REP-I |
DTCP is Haryana's Department of Town and Country Planning, which issues the licence and approves building plans. One annexure deserves a second look. Environment clearance was applied for on 23 June 2026 and had not come through when the application was filed. HRERA wants it within 6 months of registration.
Match the flat on any allotment letter to the filed drawings. The floor plan page lists the carpet areas, and the brochure page explains which documents are public.
Can the booking amount be refunded?
Under the draft terms, not necessarily. If the allottee cancels, the promoter may forfeit the booking amount, which is up to 10% of the total price, plus any interest owed on delayed payments. Whatever else has been paid is to be returned within ninety days of the cancellation.
| Money paid | Draft treatment |
|---|---|
| Booking amount (up to 10% of total price) | May be forfeited by the promoter |
| Interest on delayed payments | May be forfeited |
| Balance paid beyond the booking amount | Returned within ninety days of cancellation |
| EOI or pre-launch token | Not covered; none announced |
So the booking amount is the sum at risk. Take a buyer who has paid 10% on booking and 40% on the BBA under the down payment plan. On cancelling, that buyer could lose up to the first 10% and wait up to ninety days for the rest. Late instalments attract interest at State Bank of India's highest marginal cost of lending rate plus two percent.
What the draft doesn't cover is an EOI, because none has been announced. If a pre-launch token is ever offered, get its refund terms and timeline in writing from the promoter.
Illustrative image Which RERA rules protect an Elevate Vista buyer at booking?
Four rules matter most at this stage. A project can't be sold or advertised before registration. No more than 10% can be collected before the agreement for sale. Homes are sold on carpet area. And the terms a buyer signs should follow the documents the promoter has filed with the regulator.
- Registration first: HRERA said the certificate will be issued after form corrections and three security deposits of Rs 25 lakh each are submitted.
- The 10% cap: the draft's booking amount of up to 10% sits inside the legal limit.
- Carpet area: this is the usable floor inside the flat's walls. The draft allows it to change by up to 5% after final plans, adjusted at the same per sq ft rate as the agreement.
- Payment plans: the draft allows the two filed plans or 'any other plan duly approved by HARERA', so an unapproved scheme has no standing.
- Conveyance deed: due within 3 months of the promoter receiving the total price, and the draft says 'no administrative charges will be charged' except as stated.
The filing also names where money goes: a master collection account in the promoter's name at HDFC Bank's Sector 14, Gurgaon branch. The same account appears in Form REP-I and in the draft allotment letter. Check any payment instruction against the account printed in the registered documents.
What do you pay when the agreement is registered?
Stamp duty and registration charges sit outside the total price in the draft. They fall due when the agreement for sale, and later the conveyance deed, are registered. Haryana's stamp duty is 7% for a male buyer, 5% for a female buyer and 6% for joint ownership, plus a registration fee of 1% capped at Rs 50,000.
| Charge | Rate |
|---|---|
| Stamp duty, male buyer | 7% |
| Stamp duty, female buyer | 5% |
| Stamp duty, joint ownership | 6% |
| Registration fee | 1%, capped at Rs 50,000 |
When a price does exist, our stamp duty calculator and home loan EMI calculator will do the arithmetic.
What to check before paying anything for Elevate Vista
Start with the name and the number. The project's name in the HRERA application is Elevate Vista (Phase I), and the promoter is Elevate Edition Realtech Pvt Ltd. Unofficial labels such as 'Conscient Elevate 3.0' are in circulation in the market. They don't appear anywhere in the filing.
- Look for a registration number on HRERA Gurugram's list of registered projects. An approved application is not enough.
- Ask for the HRERA-approved payment plan and compare it with the draft.
- Ask for a price sheet that shows what the total price includes and what is extra.
- Read the draft agreement for sale before the booking cheque, since you'd have only 30 days to sign it.
- Confirm the bedroom count in writing. The filed unit table doesn't label BHK; our 3 BHK and 4 BHK reading comes from the floor plans, and the developer hasn't confirmed it.
- Check the payee name and account against the registered documents.
The promoter company itself declares no projects launched in the past five years. The platform's earlier record in Sector 59 and Sector 62 is on the reviews page.
Who do these draft booking terms suit?
On the draft terms this is a long commitment. Proposed possession is 30 November 2034, about eight years from now. The down payment plan asks for 50% by the agreement stage, which suits buyers with funds in hand. The construction-linked option spreads payments across building stages. Neither is final until HRERA approves the plan.
For the wider picture, start at the Elevate Vista overview or the FAQs. Other registered and upcoming projects are on our new project launches page.
Questions people ask
Is Elevate Vista booking open in Sector 63A Gurgaon?
No. On 23 November 2026 HRERA Gurugram had approved the Phase I application subject to conditions, but had not issued a registration number. RERA does not allow a project to be sold or advertised before registration. The developer had announced no sales, EOI or price. Check HRERA's list of registered projects for the project name before treating any offer as real.
What is the Elevate Vista booking amount?
There is no rupee figure yet. The draft allotment letter filed with HRERA describes the booking amount as up to 10% of the total price, and the price fields in that draft are blank. The developer has published no price list. The 10% ceiling is in line with RERA, which bars collecting more than 10% before the agreement for sale.
Is there an EOI amount for Elevate Vista?
None has been published. An EOI, or expression of interest, is a token some developers take before launch. Nothing in the HRERA filing mentions one, and the developer had announced none by 23 November 2026. The draft refund clause covers only cancellation after allotment, so any pre-launch token would need its own written refund terms from the promoter.
What documents should come with the allotment letter?
The draft lists ten annexures: the payment plan, HRERA-approved schedule of development, location plan, floor plan, licence, building plan approval, environment clearance, draft agreement for sale, board resolution, and specifications and amenities. Environment clearance was applied for on 23 June 2026 and had not been received at filing. The buyer's own application form and identity document list has not been published.
Can I get my booking amount back if I cancel?
Under the draft, the promoter may forfeit the booking amount, which is up to 10% of the total price, along with interest on delayed payments. The balance of what you have paid is to be returned within ninety days of cancellation. These are draft terms from the HRERA filing. The registered agreement for sale will be the binding document, so read its cancellation clause.
How long do I get to sign the agreement after allotment?
The draft allotment letter gives 30 days. Within that period the allottee sends consent and the amount due under the payment plan by cheque, demand draft or RTGS, and signs and registers the agreement for sale. Stamp duty and registration charges are payable at that point and are extra to the total price, so the funds need to be ready.
Who would I be paying if I book Elevate Vista?
The promoter in the HRERA application is Elevate Edition Realtech Pvt Ltd, applying with the licensees Smt. Sangeeta Bhatia and Sh. Laksh Bhatia. The filing names a master collection account in the promoter's name at HDFC Bank's Sector 14, Gurgaon branch. Elevate Homes, the Hines and Conscient platform, appears in the filing through its website, office address and CEO.
Are stamp duty and registration included in the total price?
No. The draft says the total price includes EDC and IDC, car parking usage charges, PLC, government fees and taxes, common areas and GST. Stamp duty, registration charges and associated charges are extra. In Haryana, stamp duty is 7% for men, 5% for women and 6% for joint owners, with a registration fee of 1% capped at Rs 50,000.
More on Elevate Vista
- Elevate Vista: overview Elevate Vista at a glance: who builds it, where, what is filed and where it stands today.
- Elevate Vista: price No price list yet: see RERA carpet sizes, what the draft price includes and stamp duty sums.
- Elevate Vista: payment plan Draft 10:40:50 and construction-linked stages from the HRERA filing, worked per Rs 1 crore.
- Elevate Vista: location Address, roads on the approved plan and what no source states yet about distances from Sector 63A.
- Elevate Vista: launch date Dated timeline from licence to HRERA approval, plus the filed 2034 possession dates and next steps.
- Elevate Vista: rera No RERA number yet: what HRERA approved on 2 November 2026 and how to check the status yourself.
- Elevate Vista: reviews Pros, cons, the Elevate Homes delivery record and any complaints, from filings only.
- Elevate Vista: brochure No official brochure yet: what the HRERA file holds and how to check any copy you receive.
- Elevate Vista: floor plan Filed carpet areas for the 3 and 4 BHK homes, room sizes from the HRERA plans, and how to read them.
- Elevate Vista: master plan Land, phases, towers, floors and open area: the Elevate Vista site plan read as a whole.
- Elevate Vista: amenities Club house, parks, sports block and safety features on record, plus what the filing leaves unsaid.
- Elevate Vista: highlights Ten sourced facts that define Elevate Vista, split into on record and claimed.
- Elevate Vista: investment Area price trend, missing rent data, buying costs and the real risks for Elevate Vista investors.
- Elevate Vista: faqs 29 buyer questions on Elevate Vista, from price and RERA to possession, answered from the filing.
Related on Property Nivesh
Talk to an advisor about Elevate Vista
Tell us what you are looking for in Elevate Vista. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.
✓
Request received
A senior property advisor will reach you within 4 working hours. No spam, no builder hand-offs — your details stay with our advisory desk only.
Sources
- HRERA Gurugram, Comprehensive Project Details for Elevate Vista (status and 2 November 2026 hearing proceedings), read 23 November 2026
- HRERA Gurugram (promoter upload), Draft allotment letter, Elevate Vista Phase I, uploaded 2 November 2026
- HRERA Gurugram, Form REP-I preview for Elevate Vista Phase I, submitted 7 October 2026, read 23 November 2026
- HRERA Gurugram, Registered projects register (Gurugram), read 23 November 2026
- HRERA Gurugram, Public notice of application for registration of Elevate Vista, 13 October 2026
- HRERA Gurugram (promoter upload), Typical floor plans for Tower A and Tower C, uploaded 2 November 2026
- Construction World, Elevate Homes to Develop Premium Project in Gurugram, 2 September 2026
Property Nivesh is an independent property research and advisory site. This guide is not the website of Elevate Homes (platform of Hines and Conscient Infrastructure) and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.