Sobha City Gurgaon, Sector 108 Gurgaon
Sobha City Gurgaon RERA, Sector 108 Gurgaon: registration numbers, status and how to check
Yes, Sobha City in Sector 108 Gurgaon is RERA registered, but not under one number. HRERA Gurugram, the Haryana Real Estate Regulatory Authority's Gurugram office, holds seven registrations across six phases. They run from 86 of 2017 for Towers A1, B1 and C1 to 95 of 2022 for the final phase, sold as Vista Residences.
The number that applies to you depends on your tower. Together the phases cover 1,548 apartments in 20 towers on 39.375 acres licensed by DTCP, Haryana's Department of Town and Country Planning.
Sobha says every home is sold, so most purchases today are resales. This page lists each registration, sets occupation certificates against the RERA dates, and shows how to read the record yourself.
- First registration
- 86 of 2017, dated 23 August 2017
- Latest registration
- 95 of 2022, dated 19 October 2022
- Phase-6 (Vista Residences) validity
- 31 December 2028
- Homes registered
- 1,548 apartments in 20 towers, six phases
- DTCP licence
- No. 107 of 2008, 39.375 acres
- Most recent OC on record
- Towers D2 and Z1, 29 September 2026
The short answer
- Sobha City carries seven HRERA registration numbers across six phases, because Phase-1 was registered in two parts in August 2017.
- Vista Residences is Phase-6: registration 95 of 2022, dated 19 October 2022, valid to 31 December 2028, covering 396 homes in Towers D1 to D4, Z1 and Z2.
- The apartment counts on the seven registrations add up to 1,548, the same total Sobha reports as sold out.
- DTCP occupation certificates on record cover 12 towers and 942 homes; the OC status of the other eight towers was not found on HRERA.
- Early phases got their OCs after the RERA dates, while Towers D2 and Z1 got theirs on 29 September 2026, more than two years inside the Phase-6 validity.
- Registration 95 of 2022 requires sale on carpet area with every charge inside the total price, and no separate EDC or IDC.
Is Sobha City Gurgaon RERA registered?
Yes, every tower sits under a registration. HRERA Gurugram's hearing brief for Phase-6 records that the 39.375-acre colony was not registered as a whole but in six phases. Phase-1 came in two parts, so there are seven registration numbers, issued between 23 August 2017 and 19 October 2022.
RERA is the real estate regulation law that makes a developer register a project with the state regulator before selling it. The developer must also file its plans, unit areas and completion date in public. In Haryana that regulator is HRERA, and Gurugram projects are handled by its Gurugram authority.
The Phase-6 certificate names Sobha Limited as the developer under a joint development agreement. The licence holders it lists include Chintels India Ltd, Vidu Properties Pvt Ltd, Madhyanchal Leasing Pvt Ltd and several individuals. The land itself is covered by DTCP Licence No. 107 of 2008, dated 27 May 2008. For Sobha's wider record in the city, see our Sobha developer page.
One number will not do
A seller or agent may quote any of the seven numbers for 'Sobha City'. Ask which tower the flat is in first, then match the tower to its phase in the table below. A number that belongs to another phase tells you nothing about your unit.
What is the RERA number of Sobha City Gurgaon?
There isn't a single number. The earliest is 86 of 2017 for Towers A1, B1 and C1, and the latest is 95 of 2022 for Vista Residences. The table sets out all seven with dates, towers and apartment counts, taken from HRERA's certificates, project pages and the promoter's REP-I filings.
| Phase | Towers | Registration number | Registered on | Validity or completion date on record | Apartments |
|---|---|---|---|---|---|
| Phase-1 Part-1 | A1, B1, C1 | 86 of 2017 | 23 August 2017 | Completion 30 October 2021 in REP-I; certificate validity not on record here | 240 |
| Phase-1 Part-2 | A2, B2, C2 | 115 of 2017 (Memo HRERA(Reg.)192/2017/792) | 28 August 2017 | Valid to 1 May 2022 | 240 |
| Phase-2 Part-1 | C3 | 12 of 2018 (RC/REP/HARERA/GGM/2018/12) | 27 July 2018 | Valid to 31 October 2022 | 96 |
| Phase-3 | C4 | 12 of 2019 (GGM/318/50/2019/12) | 25 February 2019 | Completion 31 October 2023 in REP-I; later listed as likely 30 April 2024 | 96 |
| Phase-4 | A3, A4, B3, B4 | 34 of 2019 (GGM/340/72/2019/34) | 27 May 2019 | Completion 31 December 2024 in REP-I; later listed as likely 30 June 2025 | 288 |
| Phase-5 | C5, C6 | 26 of 2020 (GGM/410/142/2020/26) | 21 September 2020 | Completion 31 December 2026 in REP-I | 192 |
| Phase-6 (Vista Residences) | D1, D2, D3, D4, Z1, Z2 | 95 of 2022 (RC/REP/HARERA/GGM/620/352/2022/95; RERA-GRG-PROJ-1152-2022) | 19 October 2022 | Valid to 31 December 2028 | 396 |
Add the last column and you get 1,548 apartments, which matches Sobha's own description of '1548 homes in 20 towers'. Certificate 115 of 2017 was issued by HRERA at Panchkula; the later certificates are from HRERA Gurugram. Two phases share the serial 12, one from 2018 and one from 2019, so always quote the year.
Phase-6 is wider than its six towers. The same registration covers 27 commercial units, a community centre, a primary school, a nursery school and EWS (economically weaker section) housing on 16.3995 acres. The layout is explained on our master plan page.
Illustrative image Sobha City Gurgaon RERA status: OCs set against the RERA dates
The project is largely delivered, with one registration still running. DTCP occupation certificates are on record for 12 of the 20 towers, covering 942 of the 1,548 homes. An occupation certificate (OC) is the permission that lets a tower be lived in. Phase-6 stays valid to 31 December 2028.
| Towers | Phase | RERA date on record | DTCP OC date | How they compare |
|---|---|---|---|---|
| A1, B1, C1 | Phase-1 Part-1 | 30 October 2021 (REP-I completion) | 8 April 2022 | OC about five months later |
| A2, B2, C2 | Phase-1 Part-2 | 1 May 2022 | 2 November 2022 | OC about six months later |
| C3 | Phase-2 Part-1 | 31 October 2022 | 16 May 2023 | OC about six and a half months later |
| C4 | Phase-3 | Listed as likely 30 April 2024 | 15 May 2024 | OC 15 days after registration expired, as HRERA noted |
| B3 | Phase-4 | 31 December 2024 (REP-I completion) | 30 January 2024 | OC about 11 months earlier |
| B4 | Phase-4 | 31 December 2024 (REP-I completion) | 21 November 2024 | OC about six weeks earlier |
| D2, Z1 | Phase-6 | 31 December 2028 | 29 September 2026 | OC more than two years earlier |
| A3, A4 | Phase-4 | 31 December 2024; later listed as likely 30 June 2025 | Not found on HRERA | Ask for the OC |
| C5, C6 | Phase-5 | 31 December 2026 (REP-I completion) | Not found on HRERA | Ask for the OC |
| D1, D3, D4, Z2 | Phase-6 | 31 December 2028 | Not found on HRERA | Sobha reports D1 completed in Q4 FY26; ask for the OC |
Sobha's investor presentations report Tower D1, with 72 homes, as completed in Q4 FY26. By Sobha's own definition, 'completed' means fit for living and available for interior fit outs. That is a company milestone, not an OC, and D1's certificate was not among the documents on the Phase-6 page.
Sobha's website FAQ still says six towers have an OC and that possession 'will begin from 2028'. The DTCP papers show more than that, including the 29 September 2026 certificate for D2 and Z1, which counts 126 main dwelling units and 28 EWS units. Where the two differ, we go by the government record. The fuller delivery history is on our reviews page and the dates are on the launch date page.
How do I check it on the HRERA site?
Search HRERA Gurugram's public project register for Sobha City and you'll find a separate entry for each phase, not one project page. Open the entry that matches your tower, then read four things: the registration certificate, Form REP-I, the uploaded documents and the hearing history.
- Get the tower and unit number from the seller's allotment letter or builder buyer agreement. Don't rely on a verbal answer.
- Match the tower to its phase using the table above. Tower C4 is Phase-3, for example, and Tower Z1 is Phase-6.
- Open the project search on HRERA Gurugram's website, look up Sobha City and pick the entry for your phase. Confirm the registration number shown matches the one in our table.
- Open the registration certificate. Note the date, the validity and the conditions printed on it, such as sale on carpet area.
- Read Form REP-I, the promoter's own filing. It lists the carpet area of each unit type, the number of apartments, the completion date, lifts and parking. The Phase-6 form shows nine carpet sizes from 102.51 to 177.60 sq m.
- Go to the documents list and look for the occupation certificate. On the Phase-6 page, the OC for D2 and Z1 was uploaded on 21 October 2026. Check that your tower is named in it.
- Read the hearing history for any proceedings against that phase, then compare everything with the seller's papers. The carpet area in the agreement should match a unit type in REP-I.
A filing quirk to know about
On the Phase-6 page, the file uploaded under 'PAYMENT PLAN' is actually the LC-IV licence agreement. So no Vista Residences payment plan sits on the register. What is known about earlier schedules is on our payment plan page.
What protections does RERA give a buyer?
The registration certificate carries the main ones. Certificate 95 of 2022 says homes must be sold on carpet area, the total price must include all charges, and no more than 10% may be taken before a written agreement for sale. HRERA's orders then show how refund and interest work in practice.
Carpet area and one all-in price
Carpet area is the usable floor inside the flat's walls, and it is the measure RERA recognises. Super area adds a share of lobbies, lifts and other common spaces. The gap can be wide: an HRERA order records a Tower C2 unit at 1,308.68 sq ft carpet against 2,072.90 sq ft super, so carpet was about 63% of super.
The Phase-6 certificate also states that 'No separate EDC/IDC are payable by the allottees except the total sale consideration'. EDC and IDC are the external and internal development charges a colony pays the state. Unit sizes are compared on our floor plan page, and what is quoted today is on the price page.
The 10% cap, paperwork and project money
Beyond the 10% cap, the certificate requires an allotment letter in the approved draft form. The sanction plan, layout and stage-wise completion schedule must be available at booking, and each buyer is enrolled in the allottees' association. Our booking page covers how these apply now that the project is sold out.
RERA also requires a promoter to keep 70% of buyers' money in a separate account for that project's land and construction. Account details for the Sobha City phases are not part of the record behind this page. When HRERA approved Phase-6 on 12 October 2022, it asked for two bank-backed securities of Rs 25 lakh each against a revised service plan and fire scheme.
Possession date, delay interest and refunds
The registration fixes a date the promoter is held to. On delay, the nearest example is not from Sobha City. In a case about Sobha's International City villas, the Haryana Real Estate Appellate Tribunal upheld delay interest at 9.30% on 18 September 2023, for a villa handed over on 16 October 2019.
On refunds, HRERA Gurugram caps the earnest money a promoter can forfeit at 10% of the basic sale consideration. In complaint 5207 of 2024 the basic price was Rs 1,79,47,194, so the cap worked out to about Rs 17.95 lakh. The balance was ordered back with 11.10% interest within 90 days.
Illustrative image What HRERA orders and hearings are on record for Sobha City?
Three sets of papers inform this section: a 2024 suo motu review of Phase III, a 2025 order on a cancelled Phase-1 Part-2 unit, and the 2022 registration hearing for Phase-6. This is not a full list. A complete count of complaints filed against the project has not been compiled.
- Suo Motu Monitoring RERA-GRG-3335-2024, hearing of 7 August 2024, Phase III: HRERA noticed that the OC for Tower C4 was obtained 15 days after the registration certificate expired. The order reads 'The matter to put up on file.'
- Complaint 5207 of 2024, decided 2 May 2025, unit C2-022: the authority called the allottee a 'habitual defaulter' with at least 10 dishonoured cheques and upheld the cancellation of 6 October 2023. It still ordered a refund of the paid amount, less the capped earnest money and less the bank refund.
- Phase-6 registration hearing, 3 October 2022: the brief listed 21 pending documents, including a revised fire scheme, a revised service plan and a powerline-shifting NOC. Registration was 'Approved as proposed' on 12 October 2022.
The refund order is useful reading even for a buyer who never defaults. It shows that HRERA applies the forfeiture cap whichever side is at fault.
Does RERA still matter when the purchase is a resale?
Yes, mainly as a way to verify. Sobha's Q4 FY24 presentation says Sobha City was completely sold out by December 2023, so a buyer today usually deals with an existing owner. The certificate conditions bind the promoter at first sale. The register tells a resale buyer which phase, OC and orders apply.
- The seller's allotment letter and agreement, showing tower, unit number and carpet area.
- A copy of the DTCP occupation certificate that names the tower.
- For Towers A3, A4, C5, C6, D1, D3, D4 and Z2, written confirmation of OC status from Sobha, since these certificates were not found on HRERA.
- Sobha's latest statement of account for the unit, so you can see what has been paid and what is outstanding.
- The registration number on the seller's papers, checked against the phase table on this page.
Registration costs come on top of the price. Haryana stamp duty is 7% for men, 5% for women and 6% for joint owners, plus a 1% registration fee capped at Rs 50,000. Our stamp duty calculator does the sum, and the Gurgaon property rates page gives wider price context.
Buyers who book through Property Nivesh can get the brokerage back; brokerage is part of the discussion with our advisor. You can speak to the research desk with your tower number and we will help you read the phase record.
What the HRERA record leaves open
A few points stay unsettled even after going through every phase entry. The licence renewal, the OCs for eight towers and some mismatches between filings each need a document from Sobha or the seller. The table lists what the record shows and what to ask for.
| Item | What the record shows | What to ask for |
|---|---|---|
| DTCP Licence 107 of 2008 | Certificate 95 of 2022 records it as 'valid upto 26.05.2025'; renewal after that not verified | Licence renewal order or current status |
| Building plan approval | Dated 19 January 2016, revalidated to 18 January 2026 | Any later revalidation |
| OC for eight towers | A3, A4, C5, C6, D1, D3, D4 and Z2 not found on HRERA | OC copy naming the tower |
| Phase-2 Part-1 land area | 2.2753 acres on the certificate; 0.7906 acres in REP-I; 0.7901 acres in HRERA's phase table | Clarification of the correct figure |
| Phase-1 carpet areas | REP-I lists 6,555, 8,000 and 12,579 with no unit of measure | Carpet area as written in the agreement |
| Z-tower unit types | Carpet 177.60, 176.55, 125.25 and 102.51 sq m; bedroom count not published | Tower floor plan for the unit |
| Licence date in Phase-6 REP-I | Part B shows 26.05.2020; statutory tables show 27.05.2008 | Rely on the licence document itself |
| Phase-6 payment plan | Upload titled 'PAYMENT PLAN' is the LC-IV agreement | The schedule in the seller's own agreement |
For everything outside the regulator's file, start at the Sobha City overview or the FAQs.
Questions people ask
Is Sobha City Gurgaon RERA registered?
Yes. HRERA holds seven registrations for Sobha City in Sector 108, spread over six phases because Phase-1 was registered in two parts. The first, 86 of 2017, is dated 23 August 2017. The last, 95 of 2022 for Vista Residences, is dated 19 October 2022 and is valid to 31 December 2028. Together they cover 1,548 apartments.
What is the RERA number of Sobha City Gurgaon?
It depends on the tower. The numbers are 86 of 2017 (A1, B1, C1), 115 of 2017 (A2, B2, C2), 12 of 2018 (C3), 12 of 2019 (C4), 34 of 2019 (A3, A4, B3, B4), 26 of 2020 (C5, C6) and 95 of 2022 (D1 to D4, Z1, Z2). Always quote the year, because two phases share the serial 12.
What is the RERA number of Sobha Vista Residences?
Vista Residences is the marketing name for Sobha City Phase-6. Its registration is 95 of 2022, also written RC/REP/HARERA/GGM/620/352/2022/95, with project ID RERA-GRG-PROJ-1152-2022. HRERA Gurugram issued it on 19 October 2022 with validity to 31 December 2028. It covers 396 residential units and 27 commercial units on 16.3995 acres.
How do I check Sobha City on the HRERA site?
Look up Sobha City in HRERA Gurugram's public project search and open the entry for your phase, since each phase has its own page. Read the registration certificate for date and validity, Form REP-I for carpet areas and completion date, the documents list for the occupation certificate, and the hearing history for any proceedings. Then compare these with the seller's agreement.
What protections does RERA give a Sobha City buyer?
The Phase-6 certificate requires sale on carpet area, a total price inclusive of all charges with no separate EDC or IDC, and no more than 10% taken before a written agreement. HRERA Gurugram also caps forfeitable earnest money at 10% of basic sale consideration. In one Sobha City order it directed a refund with 11.10% interest within 90 days.
Which Sobha City towers have an occupation certificate?
DTCP occupation certificates on record cover A1, B1 and C1 (8 April 2022), A2, B2 and C2 (2 November 2022), C3 (16 May 2023), B3 (30 January 2024), C4 (15 May 2024), B4 (21 November 2024) and D2 and Z1 (29 September 2026). No certificate was found on HRERA for A3, A4, C5, C6, D1, D3, D4 or Z2.
Has HRERA passed any order involving Sobha City?
Two are covered here. On 7 August 2024, in a suo motu review of Phase III, HRERA noted that the OC came 15 days after the registration expired and put the matter on file. On 2 May 2025, in complaint 5207 of 2024, it upheld Sobha's cancellation of a Tower C2 unit but ordered a refund beyond the 10% earnest cap. A full complaint list has not been compiled.
More on Sobha City
- Sobha City: overview Sobha City at a glance: developer, six RERA phases, OC status, sizes and prices on record.
- Sobha City: price No official price list: what Sobha, HRERA and market quotes show, plus the full cost with stamp duty.
- Sobha City: payment plan The old 20:80 plan, the 10% RERA advance cap and what a resale buyer pays, with worked sums.
- Sobha City: location Sector 108 address, Dwarka Expressway access, stated drive times, in-colony schools and metro status.
- Sobha City: launch date Dated timeline from the 2008 licence to the 2026 OCs, with RERA dates set against Sobha's own.
- Sobha City: reviews Pros, cons, OC dates against RERA dates, and the HRERA orders on Sobha City.
- Sobha City: brochure What Sobha's gated Vista Residences brochure covers and which documents actually bind.
- Sobha City: booking Booking steps for a resale in Sobha City, the amounts on record, documents and HRERA refund rules.
- Sobha City: floor plan Every Sobha City home size on record by tower, carpet versus super area, and how to read a plan.
- Sobha City: master plan 39.375 acres, six phases, 20 towers and 1,548 homes: how the Sobha City site is laid out.
- Sobha City: amenities Sobha City's clubhouses, pool, sport and green space by user, what's on record, and maintenance.
- Sobha City: highlights Ten defining facts about Sobha City, each tagged as on record, developer claim or market quote.
- Sobha City: investment Area price trend, rent estimates, buying costs and the risks on record for Sobha City.
- Sobha City: faqs 31 buyer questions on Sobha City, Sector 108: price, RERA numbers, OC status, sizes and resale checks.
Related on Property Nivesh
Talk to an advisor about Sobha City
Tell us what you are looking for in Sobha City. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.
✓
Request received
A senior property advisor will reach you within 4 working hours. No spam, no builder hand-offs — your details stay with our advisory desk only.
Sources
- HRERA Gurugram, Registration Certificate No. 95 of 2022, Sobha City Phase-6, 19 October 2022
- HRERA Gurugram, Sobha City Phase-6 Form REP-I, project detail and hearing history, read 23 November 2026
- HRERA Gurugram, project hearing brief for Sobha City Phase 6 with phase table, 3 October 2022
- HRERA, Registration Certificate No. 115 of 2017, Sobha City Phase 1 Part 2, 28 August 2017
- DTCP Haryana, occupation certificates for Sobha City towers uploaded on HRERA, 8 April 2022 to 29 September 2026
- HRERA Gurugram, order in Complaint No. 5207 of 2024, Sobha City Phase 1 Part 2, 2 May 2025
- HRERA Gurugram, Suo Motu Monitoring RERA-GRG-3335-2024, Sobha City Phase III, 7 August 2024
- Sobha Limited, investor presentations Q4 FY2024 and Q4 FY2026 and SOBHA City project page, read 23 November 2026
Property Nivesh is an independent property research and advisory site. This guide is not the website of SOBHA and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.