Sobha City Gurgaon launch date and possession timeline, Sector 108 Gurgaon

Sobha City Gurgaon in Sector 108 Gurgaon has no single launch date on record. The earliest dated markers are the building plan approval of 19 January 2016 and the first HRERA registration on 23 August 2017. Its last phase, Vista Residences, went on sale in the October to December 2022 quarter.

Possession isn't one date either. The colony was registered in six phases, each with its own deadline, and occupation certificates have arrived tower by tower since 8 April 2022. The final phase's registration runs to 31 December 2028.

Sobha says all 1,548 homes are sold, so this page is mostly for resale buyers who need to know where a particular tower stands. What follows is the dated record, phase by phase.

By Mridul Shakya, Property Nivesh Team Reviewed by Rakesh Mahajan Published Updated
First HRERA registration
86 of 2017, dated 23 August 2017
Final phase launch
October to December 2022 quarter (Sobha)
First occupation certificate
8 April 2022, Towers A1, B1, C1
Latest occupation certificate
29 September 2026, Towers D2 and Z1
Phase-6 RERA validity
31 December 2028
Sold out
By December 2023, per Sobha's Q4 FY24 deck

The short answer

  • The original launch date of Sobha City is not found in any filing; the first RERA registration is dated 23 August 2017.
  • DTCP occupation certificates on record cover 12 of the 20 towers, issued between 8 April 2022 and 29 September 2026.
  • Early phases got their OC five to six and a half months after the dates on the RERA record.
  • Towers D2 and Z1 in Phase-6 received OC on 29 September 2026, about 27 months before the registration ends on 31 December 2028.
  • Sobha's page still says 'Possession will begin from 2028', which is behind its own investor decks and the DTCP record.
  • No OC was found for Towers A3, A4, C5, C6, D1, D3, D4 and Z2, which together hold 606 homes.

When was Sobha City Gurgaon launched?

The original launch date isn't published in any developer filing or news report on record. What the record does show is a licence from 27 May 2008, building plans approved on 19 January 2016, and the first RERA registration on 23 August 2017. Sales were clearly open by April 2018.

That April 2018 marker comes from an HRERA Gurugram order in complaint 5207 of 2024. It records a builder buyer agreement, the sale contract between Sobha and an allottee, dated 12 April 2018 for a unit in Tower C2. HRERA is the Haryana Real Estate Regulatory Authority, which registers projects under the RERA law.

The final phase is better documented. On its call of 8 February 2023, Sobha said it had launched four new towers of close to 6 lakh sq ft, redesigned for larger homes, with 'record single day sales in Sobha history'. Two more towers of 350,000 sq ft were still to be launched then. Sobha's Q4 FY24 deck says the project was completely sold out by December 2023, so those two were released somewhere in between. The exact day isn't published.

A date that doesn't match

A launch date of June 2020 is quoted in the market for Sobha City. It doesn't fit the record: the first two phases were registered in August 2017, and only Phase-5 was registered in 2020, on 21 September. Treat that date as unverified.

What has happened so far, in order?

In order: the land was licensed in 2008, plans were approved in 2016, and six RERA registrations followed between August 2017 and October 2022. Occupation certificates started in April 2022 and the latest came on 29 September 2026. The table lists each dated step and where it's recorded.

Timeline of the project
DateWhat happenedWhere it's recorded
27 May 2008DTCP Licence 107 of 2008 for a 39.375-acre group housing colony in village Babupur, Sector 108HRERA RC 95 of 2022
25 November 2010Environment clearance issuedHRERA hearing brief, Phase-6
19 January 2016Building plan approvedHRERA hearing brief, Phase-6
23 August 2017Phase-1 Part-1 registered, 86 of 2017 (A1, B1, C1; 240 homes)HRERA Gurugram
28 August 2017Phase-1 Part-2 registered, 115 of 2017 (A2, B2, C2; 240 homes)HRERA certificate
12 April 2018Builder buyer agreement for a Tower C2 unitHRERA order, complaint 5207 of 2024
27 July 2018Phase-2 Part-1 registered, 12 of 2018 (C3; 96 homes)HRERA certificate
25 February 2019Phase-3 registered, 12 of 2019 (C4; 96 homes)HRERA Gurugram
27 May 2019Phase-4 registered, 34 of 2019 (A3, A4, B3, B4; 288 homes)HRERA Gurugram
Around 2020 (undated)2 and 3 BHK homes advertised with a 20:80 plan on near-complete towersSobha campaign page
21 September 2020Phase-5 registered, 26 of 2020 (C5, C6; 192 homes)HRERA Gurugram
8 April 2022First OC: Towers A1, B1, C1 and an EWS blockDTCP memo
19 October 2022Phase-6, Vista Residences, registered, 95 of 2022 (D1 to D4, Z1, Z2; 396 homes)HRERA certificate
October to December 2022Four Vista towers launchedSobha call, 8 February 2023
2 November 2022OC: Towers A2, B2, C2, shopping, community building and schoolsDTCP memo
16 May 2023OC: Tower C3Recited in DTCP OC of 30 January 2024
By December 2023Project reported completely sold outSobha Q4 FY24 deck
30 January 2024Part OC: Tower B3DTCP memo
15 May 2024Part OC: Tower C4DTCP memo
21 November 2024Part OC: Tower B4DTCP memo
Q4 FY26Tower D1 (72 homes) reported completedSobha investor presentation
29 September 2026OC: Towers D2 and Z1 (126 homes) plus 28 EWS unitsDTCP memo, on HRERA since 21 October 2026
DTCP is Haryana's Department of Town and Country Planning. OC means occupation certificate. EWS is housing reserved for economically weaker sections.

Two stretches stand out. Nine years separate the licence from the first registration, and the filings on record don't say what happened on site in that time. Nearly 14 years passed between the licence and the first OC. Phase numbers and certificates are set out on our RERA page.

An illustrative picture of a construction site with foundation work and tower cranes on the Dwarka Expressway in Sector 108 Gurugram Illustrative image
Illustrative image, not a picture of Sobha City Gurgaon.

What is the possession date of Sobha City Gurgaon?

There is no single possession date. Each of the six phases carries its own RERA deadline, and DTCP has issued occupation certificates for 12 of the 20 towers between 8 April 2022 and 29 September 2026. For the final phase, the HRERA registration is valid to 31 December 2028.

The developer's own statements don't line up. Sobha's project page FAQ still says 'Possession will begin from 2028'. Its investor decks report Tower D1 completed in Q4 FY26 and Towers D2 and Z1 in Q2 FY27. The HRERA hearing brief of 3 October 2022 listed Phase-6 completion as 30 June 2026. That makes three different dates for one phase.

Mind the wording too. Sobha defines a tower as completed 'once it is fit for living and made available to customers for interior fit outs'. An OC is different: it's the DTCP's permission to occupy. A tower can be completed in a deck without an OC showing on the HRERA page, which is the position of D1 today.

Adding up the OCs on record gives 942 homes out of 1,548. For the other 606 the OC was not found, which is not the same as not granted. It means a buyer should ask for the memo.

RERA date versus actual OC date, phase by phase

The pattern changes over time. The first three phases got their OC five to six and a half months after the date on the RERA record. Phase-3 missed by 15 days. In Phase-4 the two B towers came in ahead, and in Phase-6 the first two towers were about 27 months early.

Date on the RERA record against the DTCP occupation certificate
Phase and towersRERA numberDate on RERA recordOC on recordGap
Phase-1 Part-1 (A1, B1, C1)86 of 2017Completion 30 October 2021 in REP-I8 April 2022About 5 months after
Phase-1 Part-2 (A2, B2, C2)115 of 2017Valid to 1 May 20222 November 2022About 6 months after
Phase-2 Part-1 (C3)12 of 2018Valid to 31 October 202216 May 2023About 6.5 months after
Phase-3 (C4)12 of 2019Completion 31 October 2023, later listed as likely 30 April 202415 May 202415 days after expiry, per HRERA
Phase-4 (A3, A4, B3, B4)34 of 2019Completion 31 December 2024, later listed as likely 30 June 2025B3: 30 January 2024. B4: 21 November 2024. A3, A4: not foundB towers ahead; A3 and A4 not known
Phase-5 (C5, C6)26 of 2020Completion 31 December 2026Not foundDate not yet reached
Phase-6 Vista (D1 to D4, Z1, Z2)95 of 2022Valid to 31 December 2028D2, Z1: 29 September 2026. Others: not foundD2 and Z1 about 27 months ahead
REP-I is the form in which the promoter declares project details and a completion date to HRERA. For Phase-1 Part-1 the validity printed on the certificate was not read; the REP-I date is used.

On Phase-3, HRERA Gurugram's suo motu hearing of 7 August 2024 recorded that 'the OC has been obtained after 15 days of expiry of registration certificate' and put the matter on file. Orders and complaints are covered on the reviews page.

Which towers have no occupation certificate on record yet?

Eight towers: A3 and A4 in Phase-4, C5 and C6 in Phase-5, and D1, D3, D4 and Z2 in Phase-6. No OC for them was found on the HRERA pages read on 23 November 2026. Sobha reports D1 as completed, but the DTCP memo for it wasn't located.

Towers where the OC was not found, as read on 23 November 2026
TowersPhaseHomesWhat the record says
A3, A4Phase-4144REP-I completion 31 December 2024, later listed as likely 30 June 2025; OC not found
C5, C6Phase-5192REP-I completion 31 December 2026; OC not found
D1Phase-672Sobha reports completed in Q4 FY26; OC not found
D3, D4, Z2Phase-6198Registration valid to 31 December 2028; OC not found
Home counts are worked from the HRERA phase tables and the DTCP OC memos.

Sobha reported 336 Sobha City homes completed in FY26, including Tower D1. Its presentation doesn't name the other towers in that count. If you're looking at a flat in any of these eight, the tower's OC memo number and date is the first document to request. Tower positions are on the master plan page.

An illustrative picture of nearly finished mid-rise and high-rise residential towers with scaffolding on the Dwarka Expressway in Sector 108 Gurugram Illustrative image
Illustrative image, not a picture of Sobha City Gurgaon.

Is there a Sobha City Gurgaon new launch or EOI?

No. Sobha marks the project sold out and describes it as '1548 homes in 20 towers successfully sold out'. No EOI window, booking amount or fresh tower release is published. An EOI, or expression of interest, is a refundable token paid before a launch, and nothing of the kind is open here.

Buying in Sobha City today means buying from an existing owner. The RERA rule still frames any developer sale: no more than 10% can be taken before a written agreement for sale. How a resale transfer works is explained on the booking page, with asking prices on the price page. The old 20:80 offer from around 2020 is described under payment plan.

Buyers who book through Property Nivesh can get the brokerage back; brokerage is part of the discussion with our advisor. If it's a fresh launch you want, Sobha lists newer Gurugram projects: Altus and Strada in Sector 106, Aranya, and Crescent in Sector 63A, for which an HRERA application was made in February 2026. See our Sobha developer page and new project launches.

What are the next milestones?

The nearest one is 31 December 2026, the completion date Sobha declared for Phase-5, which is 38 days from today. After that, the items to watch are OCs for the eight remaining towers, two approvals whose renewal is not verified, and the Phase-6 registration end date of 31 December 2028.

  1. 31 December 2026: Phase-5 completion date in REP-I for Towers C5 and C6. Check the HRERA Phase-5 page for an OC upload.
  2. Towers A3 and A4: both Phase-4 dates on record have passed. An OC may exist without having been found; ask for it.
  3. Towers D1, D3, D4 and Z2: OC uploads on the HRERA Phase-6 page, where the D2 and Z1 certificate appeared on 21 October 2026.
  4. Licence 107 of 2008: recorded as valid up to 26 May 2025. Renewal after that date is not verified.
  5. Building plan: revalidated to 18 January 2026 by a memo of 4 March 2022. Ask whether it has been revalidated again.
  6. 31 December 2028: the Phase-6 registration expires.

Dates outside the gate matter as well. The Dwarka Expressway's Haryana section opened on 11 March 2024, and no metro station is announced in Sector 108. The location page has the rest.

What could change the dates?

Going by this project's own record, four things move dates: revised completion dates filed with HRERA, the time DTCP takes to issue each OC, approvals that were still open when a phase was registered, and the validity of the licence and building plan. This page forecasts none of them; it only shows what has happened.

  • Revised dates: Phase-3 moved from 31 October 2023 to a likely 30 April 2024, and Phase-4 from 31 December 2024 to a likely 30 June 2025.
  • OC processing: the D2 and Z1 application is dated 18 September 2026 and the OC 29 September 2026. Every OC on record also carries composition fees for site variations from approved plans.
  • Open approvals: the Phase-6 registration hearing of 3 October 2022 listed 21 pending documents, including a revised fire scheme, revised service plan and a powerline-shifting NOC. Registration was approved on 12 October 2022 against two bank-backed securities of Rs 25 lakh each.
  • Statutory validity: the licence and building plan dates noted above.

What should a resale buyer check on dates?

For a resale flat, the project timeline matters less than the paper trail of the one tower and unit you're buying. Ask the seller for the tower's OC memo, the offer of possession letter and the handover date, then match them to the HRERA and DTCP record above.

  1. Identify the tower and its phase, then find its RERA number in the table above.
  2. Ask for the DTCP OC memo number and date. For A3, A4, C5, C6, D1, D3, D4 and Z2 no memo was found on the HRERA pages.
  3. Ask for the builder buyer agreement and the possession date written in it.
  4. Ask for the offer of possession and proof of handover, plus a statement showing no dues to Sobha.
  5. Budget for Haryana stamp duty of 7% for men, 5% for women or 6% for joint buyers, plus a registration fee of 1% capped at Rs 50,000. Our stamp duty calculator does the sum.

For the full picture of the project, start at the Sobha City overview. If you'd like a specific tower's papers checked, contact our advisor.

Questions people ask

When was Sobha City Gurgaon launched?

The original launch date is not published in any filing or report on record. The dated markers are building plan approval on 19 January 2016 and the first HRERA registration, 86 of 2017, on 23 August 2017. An HRERA order shows a sale agreement signed on 12 April 2018. The final phase, Vista Residences, launched in the October to December 2022 quarter, according to Sobha.

What is the possession date of Sobha City Gurgaon?

It varies by tower. DTCP occupation certificates on record cover 12 towers, from A1, B1 and C1 on 8 April 2022 to D2 and Z1 on 29 September 2026. The Phase-5 completion date in the HRERA filing is 31 December 2026, and the Phase-6 registration is valid to 31 December 2028. Ask for the OC of the specific tower you're considering.

Is Sobha City Gurgaon a new launch?

No. The project was registered in six phases between August 2017 and October 2022, and Sobha's Q4 FY24 deck says it was completely sold out by December 2023. Sobha's Gurugram page marks it Sold Out. Anyone buying now is buying a resale flat from an existing owner, not a fresh allotment from the developer.

Is there an EOI open for Sobha City Gurgaon?

No EOI, booking amount or new tower release is published for Sobha City, and the developer describes all 1,548 homes as sold. An EOI is a token paid ahead of a launch, so it doesn't apply to a sold-out project. For any developer sale, RERA allows no more than 10% to be collected before a written agreement for sale.

Which Sobha City towers have an occupation certificate?

DTCP memos found on the HRERA pages cover Towers A1, B1, C1 (8 April 2022), A2, B2, C2 (2 November 2022), C3 (16 May 2023), B3 (30 January 2024), C4 (15 May 2024), B4 (21 November 2024), and D2 and Z1 (29 September 2026). That is 942 of 1,548 homes. No OC was found for the other eight towers.

Did Sobha City meet its RERA dates?

Not in the early phases. Phase-1 Part-2 was due on 1 May 2022 and its OC came on 2 November 2022. Tower C3's OC came on 16 May 2023 against a registration valid to 31 October 2022. HRERA noted that Phase-3's OC arrived 15 days after expiry. Phase-6 went the other way: D2 and Z1 got OC about 27 months early.

When will Vista Residences be handed over?

Sobha's page says 'Possession will begin from 2028', and the Phase-6 HRERA registration is valid to 31 December 2028. The record is ahead of that: Sobha reports Tower D1 completed in Q4 FY26, and DTCP granted OC for Towers D2 and Z1 on 29 September 2026. OC status for D1, D3, D4 and Z2 was not found, so ask for it.

More on Sobha City

Related on Property Nivesh

Talk to an advisor about Sobha City

Tell us what you are looking for in Sobha City. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.

Unbiased advice. Your data is never sold to builders or brokers.

Sources

  • HRERA Gurugram, Registration Certificate No. 95 of 2022, Sobha City Phase-6, 19 October 2022
  • HRERA Gurugram, Sobha City Phase-1 to Phase-6 project details and Form REP-I filings, read 23 November 2026
  • HRERA Gurugram, Project hearing brief, Sobha City Phase 6, 3 October 2022
  • DTCP Haryana (via HRERA), Occupation certificates for Sobha City towers, 8 April 2022 to 29 September 2026
  • HRERA Gurugram, Suo Motu Monitoring RERA-GRG-3335-2024, Sobha City Phase III, 7 August 2024
  • HRERA Gurugram, Complaint No. 5207 of 2024 order, 2 May 2025
  • Sobha Limited, Q3 FY2023 earnings call transcript, 8 February 2023
  • Sobha Limited, investor presentations Q4 FY2024, Q4 FY2026 and Q2 FY2026-27, and SOBHA City project page modified 30 June 2026

Property Nivesh is an independent property research and advisory site. This guide is not the website of SOBHA and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.

Chat with Us +91 79824 13588
A couple going through a price list with a property advisor

Latest price list

Get the latest price list for Sobha City

Prices and payment plans change often. Our advisor shares the current Sobha City price list and books a site visit if you want one.

Unbiased advice. Your data is never sold to builders or brokers.

Prefer WhatsApp? Chat with Us: +91 79824 13588