DLF Hamilton Court 2, Sector 28, DLF Phase 4 Gurgaon
DLF Hamilton Court 2 expected launch date and possession timeline, Sector 28, DLF Phase 4 Gurgaon
DLF Hamilton Court 2 in Sector 28, DLF Phase 4 Gurgaon has no launch date yet, only a target. DLF said on 17 October 2026 that it is scheduling the launch 'sometime in Q4', which means January to March 2027. No possession date exists, either from DLF or from the regulator.
The project is still at the pre-launch stage. It isn't registered with HRERA Gurugram (the Haryana Real Estate Regulatory Authority, which administers RERA, the homebuyer protection law, in this district), so nothing can legally be sold. DLF also says the project has no official name. 'Hamilton Court 2' is the market's label.
This page sets out the dated trail from the first licence to today, the steps still ahead, and what could move them.
- Launch target
- Q4 FY27, January to March 2027 (DLF, 17 October 2026)
- HRERA registration
- None on the register as of 23 November 2026
- Possession date
- Not published by DLF or HRERA
- Environmental clearance
- 27 September 2024, on a concept basis
- Licence validity
- 24 August 2029 and 8 February 2028
- Official name
- Not yet named (DLF, 17 October 2026)
The short answer
- DLF's latest launch target for the project is Q4 FY27, which is January to March 2027, stated on its earnings call of 17 October 2026.
- The target has moved three times: 'slated for FY27' in August 2025, the second half of FY27 in August 2026, then the last quarter in October 2026.
- HRERA Gurugram's registered-projects list, read on 23 November 2026, has no entry for this project, so no RERA possession date exists.
- The environmental clearance of 27 September 2024 covers 3 main towers and 283 apartments on a concept basis and needs to be redone if the plan changes.
- DLF has announced no EOI, booking window or booking amount, and it called the product 'still on the drawing board' on 4 August 2026.
- DLF said on 31 October 2025 that launch timing depends on 'the approval cycle and the underlying demand'.
When will DLF Hamilton Court 2 launch?
DLF's latest stated target is the fourth quarter of FY27, which runs from January to March 2027. Aakash Ohri of DLF said on the Q2 FY27 earnings call of 17 October 2026: 'it is in DLF Phase 4 and we are scheduling a launch sometime in Q4'. No day or month has been given.
| Date of statement | What DLF said | Window it implies |
|---|---|---|
| 5 August 2025 | 'they are slated for FY '27' | April 2026 to March 2027 |
| 4 August 2026 | Launch confirmed for the second half of FY27 | October 2026 to March 2027 |
| 17 October 2026 | 'scheduling a launch sometime in Q4' | January to March 2027 |
Each update pushed the window later inside the same financial year. Counting from 23 November 2026, the end of that window is about 18 weeks away. A target given to analysts isn't a promise to buyers, and it can move again.
Some dates that circulated in the market earlier, such as a launch before September 2026, have already passed without one. Treat any date that doesn't come from DLF or HRERA as a guess. Our project overview carries the wider status picture.
What has happened so far, in order?
The paper trail starts with a DTCP licence from 2014. DTCP is Haryana's Directorate of Town and Country Planning, which licenses land for housing. A second, small licence came in 2023, the environmental clearance in 2024, and DLF's launch statements run from August 2025 to October 2026. Here is the sequence.
| Date | Event | Source |
|---|---|---|
| 2014 | DTCP licence 128 of 2014 for 10.615 acres in village Chakkarpur, Sector 28 | Environmental clearance papers |
| 2021 | Airports Authority of India height clearance signed | EC compliance report |
| 9 February 2023 | DTCP licence 26 of 2023 for 0.533 acres, held by landowners in collaboration with DLF Home Developers Ltd | Environmental clearance papers |
| 19 March 2024 | DHBVN power assurance memo issued | EC compliance report |
| 11 June 2024 | State expert committee (SEAC) recommends environmental clearance | Environmental clearance letter |
| 30 August 2024 | SEIAA Haryana grants the clearance in its 182nd meeting | Environmental clearance letter |
| 6 September 2024 | Renewal of licence 128 of 2014 endorsed, up to 24 August 2029 | Environmental clearance papers |
| 27 September 2024 | Environmental clearance letter issued: 3 main towers, 283 apartments, concept basis | SEIAA Haryana |
| 5 August 2025 | DLF says the launch is 'slated for FY '27' | Q1 FY26 call |
| 3 October 2025 | Site photos show levelled, hoarded ground and a site office | EC compliance report |
| 31 October 2025 | DLF: 'We have got the Hamilton 2 project lined up' | Q2 FY26 call |
| 28 November 2025 | Half-yearly compliance report for April to September 2025 submitted | DLF Home Developers Ltd |
| 23 January 2026 | DLF speaks of 2 to 2.5 million sq ft 'with all the TDRs' | Q3 FY26 call |
| 14 May 2026 | DLF puts its big DLF City launch at Rs 8,000 to 9,000 crore 'if not higher' | Q4 FY26 call |
| 4 August 2026 | Product 'still on the drawing board'; launch in second half of FY27 | Q1 FY27 call |
| 17 October 2026 | 'We are yet to name it'; launch 'sometime in Q4' | Q2 FY27 call |
| 23 November 2026 | No entry for the project on HRERA Gurugram's registered list | HRERA Gurugram register |
How to read this timeline
Twelve years separate the first licence from today, yet the sale side of the timeline hasn't started. Everything on record so far is land, environment and utility paperwork, plus management comments. The two licences together make up the 11.148-acre site. For how the site is laid out in those filings, see the master plan page.
Illustrative image What is the possession date of DLF Hamilton Court 2?
There is no possession date for DLF Hamilton Court 2. DLF hasn't stated one, and HRERA Gurugram holds no registration that would carry one. One figure quoted in the market, 'indicatively around 2031', appears under a different project name and isn't DLF's, so we don't treat it as a date.
RERA date versus developer date
Once a project is registered, the promoter declares a completion date to the regulator and the registration runs until then. That's the RERA date. The developer date is whatever the launch material or sales team says, and it can be earlier. The date written into your agreement for sale is the one you can enforce. Read all three side by side.
| Date | Where it comes from | Status for this project |
|---|---|---|
| RERA date | Completion date declared to HRERA at registration | None: not registered as of 23 November 2026 |
| Developer date | DLF's launch material or management statements | None stated by DLF |
| Agreement date | Possession clause in the agreement for sale | No agreement exists; nothing is on sale |
DLF's Gurugram record shows dates moving in both directions. HRERA records show completion certificates issued ahead of the registered dates on commercial-plot projects, including Alameda Central on 1 December 2025. Against that, the completion date of DLF Gardencity Enclave in Sector 93 moved to 30 October 2028. At The Primus in Sector 82A, possession was promised by February 2016, only a partial occupation certificate came on 7 October 2016, and the Supreme Court ordered a CBI probe on 25 February 2026. The reviews page covers that record in full.
Is there a DLF Hamilton Court 2 EOI or new launch booking window?
No. DLF has announced no EOI (expression of interest, a token of intent some developers take before a launch), no booking window and no booking amount. Because the project isn't RERA registered, a promoter may not advertise, book or sell it. A 'pre-launch slot' offered today is not something DLF has opened.
HRERA Gurugram's public advisory of 14 August 2026, as reported, warned that buyers could be approached with pre-launch schemes or booking opportunities before a project has its approvals and registration. Its message was plain: don't book in unregistered projects. An earlier advisory, reported in January 2026, asked buyers to deal only through RERA-registered agents.
How DLF will sell is also open. For The Dahlias, DLF said on 31 October 2025 that it sells 'on an invitation basis only'. It hasn't said whether the Sector 28 project will follow that route. Several websites copy DLF's branding and use the Hamilton Court 2 name; they aren't DLF's. The booking page explains what a lawful process looks like once registration is in place.
What could change the dates?
Four things on record could move the dates: approvals, a change of plan, demand, and how DLF chooses to sell. DLF itself said on 31 October 2025 that launch timing depends on 'the approval cycle and the underlying demand'. None of these has a published deadline.
- HRERA registration. The register read on 23 November 2026, whose newest certificate is dated 17 November 2026, has no row for this project. The most recent public notices couldn't be opened that day, so a very recent application can't be ruled out.
- A revised plan. The environmental clearance was given 'on concept basis' and says a fresh one is needed 'in case of any change in planning'. In January 2026 DLF spoke of 2 to 2.5 million sq ft 'with all the TDRs' (transferable development rights), and in August 2026 the product was 'still on the drawing board'.
- The name. As of 17 October 2026 DLF was 'yet to name' the project, so launch material can't exist in final form.
- Sale in rounds. DLF's managing director spoke of 'one round of what is usually called Hamilton 2'. That wording may mean the project is sold in rounds, though DLF has not said so.
- Demand. DLF's FY27 sales guidance is about Rs 20,000 crore, and it links launch timing to demand as well as approvals.
One claim needs correcting. A line doing the rounds in the market says a public interest litigation delayed this launch. DLF's own call of 14 May 2026 tied a PIL to its Goa project, not Gurugram, and no court record links one to the Sector 28 site.
Illustrative image What are the next milestones, and what does each one look like?
The next milestone is an HRERA registration, and it's the one to watch. After that come the official name and launch, the agreement for sale, construction with quarterly progress reports to the regulator, the occupation certificate, and then possession. None of these has happened yet for the Sector 28 site.
- Official name. DLF has said the market's label is not the project's name. Registration and launch papers may carry a name nobody is using today.
- Final plan. The clearance on file covers 3 main towers and 283 apartments on a concept basis. A changed plan needs a fresh environmental clearance.
- HRERA registration. A certificate number, a declared completion date, and the tower and unit count go on the regulator's public register. Sale becomes legal only from this point.
- Launch. DLF would publish a price list, payment plan and application form. None exists today.
- Agreement for sale. RERA allows no more than 10% to be collected before this agreement. The possession date written in it is the contractual one.
- Construction. A registered project files quarterly progress reports with HRERA, so work can be tracked against the declared date.
- Occupation certificate, then possession. The OC is the authority's permission to occupy a finished building. Handover follows it.
| Approval | Dated | Valid until |
|---|---|---|
| DTCP licence 128 of 2014 (10.615 acres) | Renewal endorsed 6 September 2024 | 24 August 2029 |
| DTCP licence 26 of 2023 (0.533 acres) | 9 February 2023 | 8 February 2028 |
| Environmental clearance | 27 September 2024 | 10 years from grant, if the plan is unchanged |
| Pollution board consent to establish | Not stated | 26 September 2034 |
Step three is where the RERA page of this microsite will change first. Price and instalment details follow at step four; until then our price page and payment plan page record only what is and isn't published.
Has construction started on the Sector 28 site?
Not in a way a buyer can verify. The compliance report for April to September 2025 says 'The project is in construction phase'. Yet its site photos of 3 October 2025 show levelled, hoarded ground with a site office and no building work in frame. In August 2026 DLF called the product 'still on the drawing board'.
That matters for possession. The plan on file has towers of up to stilt plus 25 floors over 3 basements, with a maximum height of 94.510 m. A build of that size hasn't visibly begun, and there's no RERA progress report to check because there's no registration. Any possession year quoted now has no construction schedule behind it.
What should you check when a launch is announced?
Check the regulator's register before anything else, then match every date you're told against it. A real launch of this project will show up as a new DLF group-housing entry for Sector 28 or village Chakkarpur on HRERA Gurugram's list. Until that entry exists, there's no launch, whatever a message or website says.
- The registration certificate: number, date, declared completion date, and the promoter's name. The environmental clearance names DLF Home Developers Ltd and others.
- Whether the registered towers and units match the 2024 clearance or a revised plan, and whether a fresh environmental clearance was taken.
- Whether the whole site is registered at once or only a first round.
- The possession clause in the draft agreement for sale, set against the RERA date.
- Licence validity, given the dates of 8 February 2028 and 24 August 2029 on record.
- The official brochure. None is published yet; the brochure page lists the documents that do exist.
We track upcoming projects across the city on our new project launches page, and DLF's other registered projects on the DLF developer page. If you'd like to be told when the HRERA entry appears, write to Property Nivesh. Site access and surroundings are covered on the location page.
Questions people ask
When will DLF Hamilton Court 2 launch?
DLF has given a target, not a date. On its earnings call of 17 October 2026 the company said it is 'scheduling a launch sometime in Q4', meaning January to March 2027. Earlier statements said FY27, then the second half of FY27. As of 23 November 2026 the project is not registered with HRERA Gurugram, which must happen before any launch.
What is the possession date of DLF Hamilton Court 2?
None has been published. DLF hasn't stated a possession date, and there's no HRERA registration that would carry a declared completion date. A figure of around 2031 is quoted in the market under a different project name, but it isn't from DLF. The first reliable date will be the one on the HRERA register once the project is registered.
Is DLF Hamilton Court 2 a new launch that is open now?
No. It's an upcoming project that hasn't been launched. DLF said in August 2026 the product was 'still on the drawing board' and in October 2026 that it wasn't yet named. Without RERA registration a promoter may not advertise, book or sell. Nothing is lawfully on sale in this project as of 23 November 2026.
Is there an EOI for DLF Hamilton Court 2?
DLF has announced no EOI, booking amount or booking window. HRERA Gurugram's advisory of 14 August 2026, as reported, warned buyers about pre-launch schemes and booking offers made before registration. If someone asks for an expression-of-interest cheque today, ask which HRERA registration it relates to. As of 23 November 2026 there isn't one.
Why has the launch target kept moving?
DLF hasn't given a specific reason. It said on 31 October 2025 that launch timing depends on 'the approval cycle and the underlying demand'. The record also shows an unfinished product: DLF called it 'still on the drawing board' on 4 August 2026, and the environmental clearance must be redone if the plan changes from the 2024 concept.
What is the difference between the RERA date and the developer's possession date?
The RERA date is the completion date a promoter declares to the regulator at registration, and it appears on the public register. The developer date is what launch material or the sales team states, which can be earlier. The possession clause in your agreement for sale is the contractual date. For this project none of the three exists yet.
Has construction started at the Sector 28 site?
The compliance report for April to September 2025 says the project is in 'construction phase'. Its photos from 3 October 2025, though, show levelled, hoarded ground and a site office, with no building work in frame. DLF said in August 2026 the product was 'still on the drawing board'. There is no RERA progress report because there's no registration.
How will I know the launch is real?
Look for a new DLF group-housing entry for Sector 28 or village Chakkarpur on HRERA Gurugram's registered-projects list. On 23 November 2026 that list had no such row. A real launch will come with a registration certificate, a declared completion date and DLF's own price list. Websites using the Hamilton Court 2 name with DLF-style branding are not DLF's.
More on DLF Hamilton Court 2
- DLF Hamilton Court 2: overview What DLF Hamilton Court 2 is, who builds it, where it stands today, and a guide to every page.
- DLF Hamilton Court 2: price No official price list yet: quoted figures, their basis and the stamp duty sums on sample prices.
- DLF Hamilton Court 2: payment plan No plan published yet: the 10% RERA cap, a sample schedule and loan disbursal explained.
- DLF Hamilton Court 2: location Where the Sector 28 site sits, the roads on record and the only measured airport distance.
- DLF Hamilton Court 2: rera No HRERA number yet for the Sector 28 site: what the register shows and how to verify it yourself.
- DLF Hamilton Court 2: reviews Pros, cons and DLF's Gurugram delivery record, with no invented ratings or resident quotes.
- DLF Hamilton Court 2: brochure No official brochure exists yet; see what DLF's filings show and how to check one when it comes.
- DLF Hamilton Court 2: booking Booking is not open: no EOI, no amount, no HRERA registration. Steps and checks for launch.
- DLF Hamilton Court 2: floor plan No floor plans yet: what the concept filing shows floor by floor, and how to read sizes.
- DLF Hamilton Court 2: master plan Land, towers, floors, density and open area as filed, plus how to read the site plan.
- DLF Hamilton Court 2: amenities What DLF's filings show on the clubhouse, green area and services, and what is still only a claim.
- DLF Hamilton Court 2: highlights Ten sourced highlights of DLF's unnamed Sector 28 project, split into on record and claimed.
- DLF Hamilton Court 2: investment Area price data, rent evidence, fixed costs and the real risks, with no appreciation forecast.
- DLF Hamilton Court 2: faqs 28 questions on DLF's unnamed Sector 28 project: name, price, RERA, launch, homes and checks.
Related on Property Nivesh
Talk to an advisor about DLF Hamilton Court 2
Tell us what you are looking for in DLF Hamilton Court 2. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.
✓
Request received
A senior property advisor will reach you within 4 working hours. No spam, no builder hand-offs — your details stay with our advisory desk only.
Sources
- DLF Ltd, Q2 FY27 Earnings Conference Call transcript, 17 October 2026
- DLF Ltd, Q1 FY27 Earnings Conference Call transcript, 4 August 2026
- DLF Ltd, Q1 FY26, Q2 FY26, Q3 FY26 and Q4 FY26 Earnings Conference Call transcripts, 5 August 2025 to 14 May 2026
- DLF Home Developers Ltd, half-yearly EC compliance report for the Group Housing Colony at village Chakkarpur, Sector 28 (including EC letter of 27 September 2024, licences, site photos), submitted 28 November 2025
- HRERA Gurugram, Registered Projects list, read 23 November 2026
- HRERA Gurugram, public advisory on unregistered projects, 14 August 2026, as reported in news coverage of 17 August 2026
- The Tribune, SC orders CBI probe into DLF's The Primus Garden City project, 3 March 2026
- Aaj Tak, HRERA warning to Gurugram homebuyers on RERA-registered agents, 23 January 2026
Property Nivesh is an independent property research and advisory site. This guide is not the website of DLF and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.