DLF Hamilton Court 2, Sector 28, DLF Phase 4 Gurgaon
DLF Hamilton Court 2 booking in Sector 28, DLF Phase 4 Gurgaon: steps, amount and documents
Nobody can book DLF Hamilton Court 2 in Sector 28, DLF Phase 4 Gurgaon today. When we checked on 23 November 2026, DLF had put out no EOI (expression of interest, a deposit taken ahead of allotment), no booking figure and no application form. HRERA, Haryana's real estate regulator, hasn't registered the project, and until it does no one may lawfully accept a booking.
DLF is aiming for a launch in the January to March 2027 quarter. The name itself belongs to the market: on 17 October 2026 DLF said it had not named the project yet.
Below you'll find the order a lawful booking follows, which amounts are known and which aren't, the papers worth collecting, and how cancellation money gets treated under RERA.
- Booking status
- Closed; nothing opened as of 23 November 2026
- Booking or EOI amount
- No figure from DLF
- HRERA registration
- None found on the list read 23 November 2026
- Launch target
- January to March 2027 (DLF, 17 October 2026)
- Cap before agreement for sale
- 10% of the home's cost under RERA
- Promoter in the filings
- DLF Home Developers Ltd and co-licensee landowners
The short answer
- DLF had announced no EOI, deposit figure or booking window for its Sector 28 project when we checked on 23 November 2026.
- The project is missing from HRERA Gurugram's registered-projects list, so a lawful booking is not possible yet.
- DLF told analysts on 17 October 2026 that the launch is scheduled for Q4 of FY27, meaning January to March 2027.
- Under RERA, everything collected before the agreement for sale must stay within 10% of the home's cost.
- HRERA Gurugram's order of 14 August 2026 on DLF Skycourt allowed DLF to keep 10% as earnest money and return the rest with 10.80% interest.
- DLF said in October 2025 that The Dahlias is sold by invitation only, and has not said how this project will be sold.
Is DLF Hamilton Court 2 booking open right now?
Not yet. HRERA Gurugram's register of projects, as we read it on 23 November 2026, holds nothing for this site in Sector 28, DLF Phase 4 Gurgaon. The RERA Act stops a promoter from advertising, booking or selling until the project is registered. DLF hasn't opened a window or named a deposit either.
RERA is short for the Real Estate (Regulation and Development) Act. HRERA Gurugram is the body that enforces it in this district, and its register is where a buyer's checks begin. We follow that register for this site on the RERA page.
So what is actually on file? An environmental clearance of 27 September 2024, issued on a concept basis to DLF Home Developers Ltd and the landowners who share one of the licences. It describes 283 apartments across three main towers on 11.148 acres. A clearance of that kind lets planning go ahead. Selling needs registration.
On the earnings call of 17 October 2026, DLF's Aakash Ohri said a launch was being scheduled 'sometime in Q4', which is January to March 2027. Earlier targets slipped, so treat this one as an intention. The history is on our launch date page.
How do I book a home in DLF Hamilton Court 2? Steps from enquiry to registration
Booking isn't possible yet, though the sequence is well known. Lawfully it goes: enquiry, site visit, the promoter's HRERA registration, an application form with a deposit, an allotment letter, a registered agreement for sale, instalments, and finally possession with a conveyance deed. The table marks how far this project has got on each.
| Step | What it involves | Where it stands |
|---|---|---|
| 1. Enquiry | Asking for project papers; no payment | Open to anyone, but DLF has no project page, brochure or price list |
| 2. Site visit | Seeing the plot, approach roads and surroundings | Photos dated 3 October 2025 in DLF's compliance report show levelled, hoarded ground and a site office |
| 3. HRERA registration | Promoter registers the project; advertising and sales may begin only after this | Pending; no entry on the register |
| 4. EOI or application | Signed form plus a deposit | Nothing announced: no form, no EOI, no figure |
| 5. Allotment | Letter fixing the unit, price and payment plan | Not begun; method of sale not stated |
| 6. Agreement for sale | Signed and registered; the 10% cap applies up to this point | No draft released |
| 7. Instalments | Payments as per the plan filed with the regulator | No plan released |
| 8. Possession and conveyance deed | Handover; stamp duty and registration fee are paid on the deed | No possession date from DLF or the regulator |
How will units be sold? There's a hint, nothing firmer. Speaking about The Dahlias on 31 October 2025, DLF said it sells 'on an invitation basis only'. Whether the Sector 28 project goes the same way is something DLF hasn't addressed.
On that call, DLF's managing director also spoke of 'one round of what is usually called Hamilton 2'. The phrase could mean the homes are released in rounds. DLF hasn't said so. If it happens, find out which towers and units fall in each round before you apply.
Useful things to do now that cost nothing
- Go through DLF's environmental compliance report, the single project document it has released. We explain its contents on the brochure page.
- Look up HRERA Gurugram's register now and then for a DLF group housing row in Sector 28 or village Chakkarpur.
- Write down licence numbers 128 of 2014 and 26 of 2023. Both come from DTCP, Haryana's town and country planning department, and should show up on the registration.
- Walk the site and the roads leading to it. Our location page lists what the record says about access.
- Settle whose name goes on the home. In Haryana that choice changes the stamp duty rate.
Illustrative image DLF Hamilton Court 2 booking amount and EOI amount: what is known
There is no figure to report for either. DLF hasn't stated a booking amount or an EOI amount, and it has released no rate card or instalment schedule for the Sector 28 project. Its only money figure is a sales estimate for the big DLF City launch: Rs 8,000 to 9,000 crore, 'if not higher', given on 14 May 2026.
That estimate covers every home in the launch taken together, so it tells you nothing about a single apartment. Tying it to this project is our own reading, based on DLF naming just two Gurugram projects on that call.
| Item | Position on 23 November 2026 | Question for launch day |
|---|---|---|
| Booking amount | No figure released | What sum is printed on the application form? |
| EOI amount | No EOI announced | Is it fully refundable, and is that in writing? |
| Booking window | None; launch aimed at January to March 2027 | What is the HRERA registration number? |
| Method of sale | Not stated; The Dahlias went by invitation only | How are units allotted, and in what order? |
| Price list | Not released | Is the rate on carpet area, with each charge listed? |
| Payment plan | Not released | Does it match the plan filed with HRERA? |
| Cancellation and refund | Not released | What do the form and agreement for sale say? |
Whatever DLF asks for, one legal ceiling applies. Until the agreement for sale is signed, the promoter's total collection can't cross a tenth of the home's cost. The booking deposit counts towards that tenth, and so does any demand raised in between.
To get a feel for scale only: entry prices quoted in the market range from Rs 12 crore to roughly Rs 25 crore. A tenth of those would be Rs 1.2 crore and Rs 2.5 crore. The quotes disagree with one another and none is DLF's, as the price page sets out.
Stamp duty comes much later, at the conveyance deed, and Haryana charges men 7%, women 5% and joint owners 6%. Our stamp duty calculator will do the sum once a real price is out. Instalment details will sit on the payment plan page.
What documents are needed to book?
There's no official list, because DLF hasn't issued an application form for this project. When it does, the form will spell out the identity, tax and payment papers expected from resident and NRI applicants. For now the list that matters runs the other way: what you should get from the promoter.
What to get from the promoter
- The HRERA registration certificate, with its number, validity, registered area, towers and unit count.
- DTCP licence 128 of 2014 for 10.615 acres and licence 26 of 2023 for 0.533 acres, along with the collaboration papers between DLF Home Developers Ltd and the individuals who hold the smaller licence.
- The sanctioned building plan and the environmental clearance in force. The 2024 clearance itself says a change in planning calls for a new one.
- A rate card based on carpet area, meaning the usable floor inside the apartment's walls, which is RERA's measure. Super area adds a slice of common spaces and has no legal standing as a yardstick.
- A written list of extras: EDC and IDC (government development charges passed to buyers), PLC (a premium for a preferred position), club, parking and maintenance.
- The draft agreement for sale and a specimen allotment letter.
- The instalment schedule and the clause on cancellation and refund.
What you will have to hand over
We've chosen not to print a buyer-side checklist. DLF hasn't published one, and a guessed list is worse than none. Request it in writing along with the form, and check that the applicant names match the names you want on the registered deed.
Can the booking amount be refunded?
Nobody can say yet, since no booking terms have been issued. How much of a deposit returns on cancellation, and when, will be written into DLF's application form and agreement for sale at launch. Go through that clause line by line first. If an EOI is offered, get its refund terms in writing.
A recent ruling gives a sense of how the regulator thinks. Deciding a complaint about DLF Skycourt, Sector 86, on 14 August 2026, HRERA Gurugram accepted that DLF was entitled to cancel because the buyer hadn't paid. DLF still had to return what it had received, keeping 10% as earnest money and adding interest at 10.80%.
That ruling belongs to a different project with its own facts, so don't read it as a term of this one. What it shows is the same tenth appearing twice: as the ceiling on early collection and, in that dispute, as the amount the developer could retain.
Paying before registration
If you pay while the project is unregistered, you hold no registered agreement and there is no filed schedule behind your payment. HRERA Gurugram's advisory of 14 August 2026, as reported, asked buyers to stay away from bookings in unregistered projects.
For DLF's broader track record on complaints and delivery in Gurugram, see the reviews page.
Illustrative image RERA rules that protect the buyer at booking
Four safeguards matter most on booking day. A project must be registered before it is advertised or sold. Early collection is capped at 10% until the agreement for sale. Apartments are sold on carpet area. And the regulator has asked buyers to use only agents who are themselves RERA registered.
- Registration: on 23 November 2026 the HRERA Gurugram list had no row citing Chakkarpur, either licence, or DLF group housing in Sector 28 or Phase IV. Our sweep of public notices on 21 November 2026 found no application notice. Newer notices would not open, so a very recent filing can't be excluded.
- The cap: it counts every rupee collected before the agreement, under any label, be it EOI, token or booking.
- Carpet area: the 2024 clearance lists apartments per tower and gives no sizes. Sizes quoted in the market, about 4,000 to 5,500 sq ft, are unconfirmed and are not stated as carpet area. More on the floor plan page.
- Agents: Aaj Tak reported in January 2026 that HRERA had advised Gurugram buyers to transact only through RERA-registered agents.
Possession is the other blank. Neither DLF nor the regulator has a date on record. Once the project is registered, note the completion date filed with HRERA and see that the agreement for sale carries the same one.
What to do if someone offers a pre-launch booking
Don't pay, and ask for the HRERA registration number. The regulator's advisory of 14 August 2026, as reported, said buyers 'could be approached with pre-launch schemes, promotional offers or booking opportunities before projects receive the required approvals and RERA registration'. That is exactly the stage this project is at.
DLF's own website has no page, brochure or rate card for the project. It follows that any form, price sheet or 'priority' slot doing the rounds had not come from that website as of 23 November 2026.
- Someone wants a cheque or transfer to 'hold' a unit ahead of registration.
- A size, layout or price is shown as final. On 4 August 2026 DLF described the product as 'still on the drawing board'.
- A possession year is promised. No filing contains one.
- The project carries another name. 'DLF Magnolias 2' is used in the market for an upcoming Sector 28 launch, and nothing confirms it is this project.
- The land area or tower count doesn't match the filings: 11.148 acres, three main towers and one EWS block.
The concept on file could itself change. In January 2026 DLF mentioned about 2 to 2.5 million sq ft 'with all the TDRs' (transferable development rights), more than the cleared plan holds. Any booking should be tied to the plan that gets registered. The project overview pulls together the record so far.
Who should track this booking, and what to keep ready
This is one for buyers already weighing DLF's costliest homes in DLF City. DLF describes the project as a 'luxury-plus product' that will be 'at par with our recent luxury launches'. It fits people prepared to wait for documents. Anyone who needs a firm price or a handover date today won't find one here.
- Watch the HRERA register. Nothing else on this page moves until an entry appears.
- See registered alternatives on our new project launches page.
- Check DLF's handling of other Gurugram projects on the DLF developer page.
- Find quick answers on the FAQs page.
Not sure what to verify? Write to our advisors via the contact page. Property Nivesh accepts no deposits and forwards no bookings for projects without registration.
Questions people ask
How do I book a home in DLF Hamilton Court 2?
At present you can't. The Sector 28, DLF Phase 4 project had no HRERA registration on 23 November 2026, and DLF has released no form, EOI or booking window. Once registered, expect an application with a deposit, then an allotment letter, a registered agreement for sale and instalments. DLF's stated aim is to launch in the January to March 2027 quarter.
How much is the booking amount?
No amount has been stated by DLF, and there is no EOI figure, rate card or instalment schedule either. RERA limits total collection before the agreement for sale to 10% of the home's cost. Entry prices quoted in the market, Rs 12 crore to roughly Rs 25 crore, are unconfirmed, so a deposit worked out from them would only be a guess.
What documents are needed?
DLF hasn't issued an application form, so there is no official checklist yet. Request it in writing when the launch opens. On the promoter's side, ask for the HRERA registration certificate, DTCP licences 128 of 2014 and 26 of 2023, the sanctioned plan, a rate card on carpet area, the draft agreement for sale and the cancellation clause.
Can the booking amount be refunded?
The terms aren't out. They'll appear in the application form and agreement for sale. For context, in a DLF Skycourt case decided on 14 August 2026, HRERA Gurugram had DLF return a cancelled buyer's payments after keeping 10% earnest money, and add 10.80% interest. Skycourt is a separate project, so check this project's own clause before you pay.
Is an EOI open for DLF Hamilton Court 2?
No expression of interest has been announced by DLF. In October 2025 the company said The Dahlias is sold on an invitation basis only, yet it has given no word on the route for this project. An EOI cheque collected today would be taken ahead of HRERA registration, the very situation the regulator cautioned buyers about in August 2026.
Is a pre-launch booking legal?
The RERA Act does not let a promoter advertise, book or sell a project that isn't registered. This Sector 28 site was absent from HRERA Gurugram's list on 23 November 2026. A regulator advisory dated 14 August 2026, as reported, asked buyers to avoid bookings in unregistered projects. So the registration number is the thing to ask for before any money changes hands.
Who is the promoter I would be dealing with?
DLF Home Developers Ltd 'and others' is the name on the environmental clearance. Those others are the individual holders of DTCP licence 26 of 2023, who are in collaboration with the DLF company. The promoter of record will be confirmed by the HRERA registration when it is granted. Match the licence numbers on that entry before paying.
More on DLF Hamilton Court 2
- DLF Hamilton Court 2: overview What DLF Hamilton Court 2 is, who builds it, where it stands today, and a guide to every page.
- DLF Hamilton Court 2: price No official price list yet: quoted figures, their basis and the stamp duty sums on sample prices.
- DLF Hamilton Court 2: payment plan No plan published yet: the 10% RERA cap, a sample schedule and loan disbursal explained.
- DLF Hamilton Court 2: location Where the Sector 28 site sits, the roads on record and the only measured airport distance.
- DLF Hamilton Court 2: launch date Launch target, dated timeline and why there is no possession date yet.
- DLF Hamilton Court 2: rera No HRERA number yet for the Sector 28 site: what the register shows and how to verify it yourself.
- DLF Hamilton Court 2: reviews Pros, cons and DLF's Gurugram delivery record, with no invented ratings or resident quotes.
- DLF Hamilton Court 2: brochure No official brochure exists yet; see what DLF's filings show and how to check one when it comes.
- DLF Hamilton Court 2: floor plan No floor plans yet: what the concept filing shows floor by floor, and how to read sizes.
- DLF Hamilton Court 2: master plan Land, towers, floors, density and open area as filed, plus how to read the site plan.
- DLF Hamilton Court 2: amenities What DLF's filings show on the clubhouse, green area and services, and what is still only a claim.
- DLF Hamilton Court 2: highlights Ten sourced highlights of DLF's unnamed Sector 28 project, split into on record and claimed.
- DLF Hamilton Court 2: investment Area price data, rent evidence, fixed costs and the real risks, with no appreciation forecast.
- DLF Hamilton Court 2: faqs 28 questions on DLF's unnamed Sector 28 project: name, price, RERA, launch, homes and checks.
Related on Property Nivesh
Talk to an advisor about DLF Hamilton Court 2
Tell us what you are looking for in DLF Hamilton Court 2. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.
✓
Request received
A senior property advisor will reach you within 4 working hours. No spam, no builder hand-offs — your details stay with our advisory desk only.
Sources
- HRERA Gurugram, Registered Projects (Gurugram) list, read 23 November 2026
- DLF Ltd, Q2 FY27 Earnings Conference Call transcript, 17 October 2026
- DLF Ltd, Earnings Conference Call transcripts for Q2 FY26 (31 October 2025), Q3 FY26 (23 January 2026), Q4 FY26 (14 May 2026) and Q1 FY27 (4 August 2026)
- DLF Home Developers Ltd, Half yearly EC compliance report, Group Housing Colony at Village Chakkarpur, Sector 28 (EC dated 27 September 2024), submitted 28 November 2025
- DLF Ltd, website homepage, read 23 November 2026
- HRERA Gurugram, Order in CR 4849/2024 (DLF Skycourt), 14 August 2026
- Aaj Tak, HRERA warning to Gurugram homebuyers: deal only with RERA-registered agents, 23 January 2026
Property Nivesh is an independent property research and advisory site. This guide is not the website of DLF and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.