Goregaon-Mulund Link Road: Real Estate Impact, Phases and Status
The Goregaon-Mulund Link Road is a 12.2 km BMC road whose twin tunnels under Sanjay Gandhi National Park are being bored, with the whole road targeted for February 2029. Its effect on property is still an expectation: Goregaon East launch prices rose sharply while Mulund prices stayed flat.
By Mridul Shakya · Edited by
Rakesh Mahajan · · 11 min read
Illustrative image What is the Goregaon-Mulund Link Road and where does it stand?
The Goregaon-Mulund Link Road is a 12.2 km east-west road being built by BMC (the Brihanmumbai Municipal Corporation) to join Goregaon on the Western Express Highway with Mulund on the Eastern Express Highway. As of 8 November 2026 both tunnel boring machines are digging under Sanjay Gandhi National Park and BMC targets February 2029 for the whole road, as reported by the Free Press Journal. Until then, the real estate impact is mostly an expectation that buyers is pricing in, not a commute anybody can use.
The road was estimated at about ₹14,000 crore, according to Swarajya citing The Indian Express (29 November 2025). An older figure of ₹12,013 crore including taxes also circulate, so treat the cost as approximate. BMC itself had set 2028 for full completion in November 2025, and that date has since slipped.
For a city-wide tracker, see our guide to upcoming infrastructure projects in Mumbai that could impact property prices.
GMLR phases: what each part covers and its status
The Free Press Journal (8 November 2026) describes GMLR as a road built in four phases. BMC hasn't published a phase-wise status sheet, so the table lists only the parts with a dated record.
| Part of the road | What it covers | Status (date) | Source |
|---|---|---|---|
| Dindoshi-Film City flyover | Six-lane flyover with an elevated rotary; 1.3 km per TOI, 1.2 km in other reports | Civil work done, due by 15 October 2026 after a load test; earlier targets of May and September 2026 missed | The Times of India, 24 September 2026 |
| GMLR connector | One of three road structures opened together with the Sion rail overbridge and Vidyavihar flyover | Opened 22 October 2026 (whether it is the Dindoshi-Film City flyover is not confirmed) | Property Nivesh news citing Mid-Day, 23 October 2026 |
| Phase 3(B) twin tunnels | Film City (Goregaon East) to Amar Nagar (Mulund West); 5.34 km bored length, each tunnel 6.675 km with box tunnels, ramps and shafts | Both TBMs boring from the Film City end | Free Press Journal, 8 November 2026 |
| Mulund retrieval shaft and ramps | Land at the Amar Nagar end where the machines come out | 612 of 743 structures cleared, 131 due by December 2026 or early January 2027 | Free Press Journal, 8 November 2026 |
| Nahur-Airoli flyover | 1.33 km, described as the final phase | Tender reported at ₹1,293 crore (tentative; tender date not confirmed) | Free Press Journal, date not confirmed |
So the GMLR project status in short: the western flyover end is largely built, the tunnels is just starting, and the eastern flyover towards Airoli is at tender stage on a tentative report. Cost for each phase is not on public record.
The GMLR twin tunnel under the national park
The heart of the project is the GMLR twin tunnel under Sanjay Gandhi National Park. Each tube carries three lanes and has a 13 m internal diameter, as per the Free Press Journal of 8 November 2026. The bored part is 5.34 km, and the rest of the 6.675 km per tunnel is box tunnels, ramps and shafts at the two portals.
The first machine, Tulsi, started on 17 August 2026 and had bored 270 m by 8 November 2026, at about 6 m a day. The second, Vihar, with a 14.49 m cutterhead, started on 7 November 2026. Both are digging from Film City towards Mulund. So 270 m is roughly 5% of the bored length.
The Film City box tunnel sits at the Goregaon portal. Its length and cost is not published separately, so ask BMC when the digging there will ends.
Free property updates
Never Miss a Property Opportunity!
Get the latest property news, investment opportunities, new launches and government plot scheme updates directly.
You're subscribed
One last tap so our WhatsApp updates reach you:
Say hello on WhatsAppIt opens a chat with +91 79824 13588, our main number. Save it in your contacts.
Goregaon to Mulund travel time: the claim as stated
BMC claims the Goregaon to Mulund travel time will drop from about 90 minutes to about 20 minutes once the road opens, as reported by the Free Press Journal on 8 November 2026. The Times of India (24 September 2026) gave a different version: travel between the western and eastern suburbs falling from around 75 minutes to 25. Both are official claims for a road that isn't open yet.
Illustrative image| Claim | Today | After GMLR opens | Reported by |
|---|---|---|---|
| Goregaon to Mulund (BMC) | About 90 minutes | About 20 minutes | Free Press Journal, 8 November 2026 |
| Western to eastern suburbs | Around 75 minutes | About 25 minutes | The Times of India, 24 September 2026 |
The BMC figure implies a saving of roughly 70 minutes each way. Treat it as a target, nobody has drive it end to end yet.
Property near GMLR: the areas along the road
Buying property near GMLR means buying into one of four quite different belts. The table gives the price evidence on record, one firm per row, with its basis and period. Carpet area is the usable floor inside your walls; it is smaller than built-up area, which adds walls and balconies.
| Area | Price evidence | Basis and period | Source |
|---|---|---|---|
| Goregaon East (incl. Film City Road) | ₹40,430 per sq ft on new launches, up from ₹26,831 in 2022 | Carpet, weighted average, 2026 to Q3 | The Times of India, 16 November 2026 (data provider not named) |
| Goregaon (east and west together) | ₹26,078 to ₹27,340 per sq ft | Basis not stated, H1 2026 | Knight Frank India, July 2026 |
| Mulund (east and west together) | ₹27,083 per sq ft | Carpet, average quoted base price, Q3 2026 | ANAROCK Research, October 2026 |
| Mulund | ₹23,062 to ₹23,182 per sq ft | Basis not stated, H1 2026 | Knight Frank India, July 2026 |
| Bhandup and Nahur side | No consultancy price published | Not on record | Ask for registered sale deeds in the building |
Don't compare the ANAROCK and Knight Frank rows, they use different bases. Our Mumbai property rates page keeps our own city tracker.
Goregaon East and Film City Road: the western end
Housing
This is the side where the road begins, at Film City and Dindoshi. The 80-acre Oberoi Garden City township sits here, with mid-segment towers, older societies and MHADA and cluster redevelopments around it. Redevelopment means an old building being pull down and rebuilt by a developer, with old members getting new flats.
Price evidence
The Times of India (16 November 2026) reported a 51% rise in the weighted average launch price, from ₹26,831 per sq ft carpet in 2022 to ₹40,430 in 2026 up to Q3. At the top end, Oberoi Realty reported an average of about ₹54,880 per sq ft carpet on bookings at Oberoi Elysian in July to September 2026, which is one luxury project, not the area.
What the road changes
Goregaon East already have Metro Line 7 at Aarey, Goregaon (East) and Dindoshi, and Line 3 ends at Aarey JVLR. GMLR would add a direct road east, which the area don't have now.
Watch-out
Sales are slow. The same TOI report counts 241 homes launched in 2026 up to Q3 and only 35 absorbed. Film City Road will also host portal works for years, with diversions likely, and you can read more in our news on the second GMLR tunnel machine.
The Aarey side: green land, strict rules
The road passes the edge of Aarey and the 521-acre Film City, so the green rules matter more here than elsewhere along the corridor. Aarey covers 3,162 acres and is an eco-sensitive zone under a 2016 notification, according to an Aarey CEO letter reported by the Free Press Journal (July 2025). Construction there needs approval from the SGNP Eco-Sensitive Zone Committee.
Illustrative imageThe state approved a Zonal Master Plan for the eco-sensitive zone by GR on 20 March 2026 (Free Press Journal, 24 March 2026). In July 2026 a citizens group asked the Union environment ministry to require wildlife and environmental studies before any Film City redevelopment approvals. So new supply on this side stay limited, and a buyer should ask in writing what the zone allow.
Mulund West and Amar Nagar: the eastern end
Housing
The tunnels come out at Amar Nagar in Mulund West. Large gated projects stand on old industrial land along LBS Marg and the GMLR, including Piramal Revanta, whose address is on the Goregaon-Mulund Link Road itself, and Oberoi's Eternia and Enigma.
Price evidence
ANAROCK put Mulund's average quoted base price at ₹27,083 per sq ft carpet in Q3 2026, against ₹26,900 in Q3 2024, so about 1% in two years. Its quoted rent for a 700 sq ft 2 BHK was ₹42,000 to ₹66,000 a month in Q3 2026. On those two figures a gross yield is roughly 2.7% to 4.2% before costs. Gross yield is a year's rent divided by price; net yield take out maintenance, tax and empty months.
What the road changes
For families who work in Goregaon or the western suburbs, GMLR could be the first fast road across the park. Our news on the GMLR land clearance covers the Amar Nagar end in more detail.
Watch-out
Two clearance counts disagree. Mid-Day (16 October 2026, via our news) said all 604 structures in Amarnagar were cleared, while the Free Press Journal (8 November 2026) said 612 of 743 at the retrieval shaft were done and 131 left. For pocket-by-pocket detail, read our guide to the best areas to buy property in Mulund.
Bhandup and the Nahur side
Bhandup has older societies and slum-rehab buildings, and new high-rises on LBS Marg. SRA means the Slum Rehabilitation Authority, which lets developers rebuild slums and sell extra flats. No consultancy publishes a Bhandup price, so a buyer have to rely on recent registered deals in the same building.
The Nahur side links to GMLR's last leg, the Nahur-Airoli flyover, reported by the Free Press Journal at a tender of ₹1,293 crore for 1.33 km. That is a tentative report with no confirmed date. Metro Line 4 stations in this belt, from Naval Housing to Mulund Naka, are also not open yet.
Also, about 255 to 256 acres of salt pan land along Bhandup, Kanjurmarg and Mulund has been allotted for Dharavi project rehabilitation (Free Press Journal), and local opposition continue.
GMLR completion date and the milestones so far
The GMLR completion date has already moved once. BMC said 2028 in November 2025; the Free Press Journal reported February 2029 on 8 November 2026.
Illustrative image| Date | Milestone | Source |
|---|---|---|
| 29 November 2025 | BMC sets 2028 for full completion; cost about ₹14,000 crore | Swarajya citing The Indian Express |
| 17 August 2026 | TBM Tulsi starts boring from Film City | Free Press Journal, 8 November 2026 |
| 24 September 2026 | Dindoshi-Film City flyover civil work done, due by 15 October | The Times of India |
| 16 October 2026 | 604 structures in Amarnagar reported cleared | Property Nivesh news citing Mid-Day |
| 22 October 2026 | A GMLR connector opens with the Sion and Vidyavihar structures | Property Nivesh news citing Mid-Day |
| 7 November 2026 | TBM Vihar starts the second tunnel | Free Press Journal, 8 November 2026 |
| 8 November 2026 | Tulsi at 270 m; target February 2029 | Free Press Journal |
Our report on the new Sion, Vidyavihar and GMLR bridges explains what the October opening changes on the ground. Past price moves near a road does not predict future ones, and no firm has published a GMLR price premium.
Checklist before you buy near the GMLR
- Check the MahaRERA page of the project. MahaRERA is the state regulator; note the registration number and the completion date it shows.
- Ask whether the building has an OC (occupancy certificate, the permission to live in it) or only a CC (commencement certificate, the permission to build).
- Ask the developer how far the plot is from the Film City portal, the Amar Nagar shaft or the Nahur flyover works.
- For Aarey or Film City side plots, get the eco-sensitive zone status in writing.
- Compare price on one basis only, carpet with carpet, and from one source.
- Budget for stamp duty: 6% in Mumbai including the 1% metro cess, plus 1% registration capped at ₹30,000, as listed in our state costs table. Confirm before paying.
- Plan your commute on today's roads, not on the February 2029 target.
Duty is charged on the higher of agreement value and ready reckoner value (the government's minimum value). See the cost of buying property in Mumbai has the full breakdown.
Where to go next
The GMLR is a slow, phased road with a 2029 target and no proven price effect yet. If Goregaon is on your list, read Goregaon vs Malad for property investment, where the two neighbours is compared on supply and prices. If you work in Powai, which the corridor reach only indirectly, see property investment opportunities in Powai.
Questions
Frequently Asked Questions
Is any part of the Goregaon-Mulund Link Road open now? +
A GMLR connector opened on 22 October 2026 along with the Sion rail overbridge and the Vidyavihar flyover, as reported by Mid-Day via our news. Whether that connector is the Dindoshi-Film City flyover is not confirmed. The twin tunnels, which carry the road under the national park, are still being bored.
What is the GMLR completion date? +
BMC targets February 2029 for the whole road, according to the Free Press Journal on 8 November 2026. In November 2025 BMC had said 2028, and an earlier report gave October 2028 for the tunnels. The date has slipped once already, so treat February 2029 as a target rather than a promise.
How long are the GMLR twin tunnels? +
The tunnel boring machines dig 5.34 km under Sanjay Gandhi National Park, from Film City in Goregaon East to Amar Nagar in Mulund West. Each tunnel is 6.675 km long once box tunnels, ramps and shafts are added, with three lanes and a 13 m internal diameter (Free Press Journal, 8 November 2026).
How much will GMLR cut the Goregaon to Mulund travel time? +
BMC claims a drop from about 90 minutes to about 20 minutes, as reported by the Free Press Journal on 8 November 2026. The Times of India (September 2026) quoted around 75 minutes to 25 for travel between the western and eastern suburbs. Neither has been tested, because the road is not open.
Have prices near GMLR already gone up? +
It depends on the end. The Times of India reported Goregaon East launch prices up 51% from 2022 to 2026, but it linked that to redevelopment and metro lines too. ANAROCK shows Mulund at ₹27,083 per sq ft carpet in Q3 2026, close to its Q3 2024 level. No firm has published a price premium caused by GMLR.
What is the GMLR project cost? +
The road was estimated at about ₹14,000 crore, as reported by Swarajya citing The Indian Express in November 2025, and ANAROCK used the same figure in September 2026. An older figure of ₹12,013 crore including taxes also appears. A phase-wise cost has not been published, so treat the total as approximate.
Will construction affect homes near the tunnel portals? +
Expect years of works. Film City Road hosts the western portal and both machines start there, while the Mulund end needs a retrieval shaft and ramps at Amar Nagar. At that end, 131 of 743 structures were still to be cleared as of November 2026. Ask the developer how close the building is to each work site.
Can new projects come up on the Aarey side once GMLR opens? +
The road does not change the land rules. Aarey is an eco-sensitive zone under a 2016 notification and building there needs approval from the SGNP Eco-Sensitive Zone Committee. A Zonal Master Plan was approved on 20 March 2026. Supply on that side stays limited by these rules, whatever the road brings.
Sources
- Free Press Journal, Mumbai's GMLR Project Advances As 2nd TBM Joins Excavation Of Twin Tunnels, 8 November 2026
- The Times of India, Goregaon-Mulund Link Road project's flyover linking Dindoshi and Film City set to open by Oct 15, 24 September 2026
- The Times of India, Goregaon East property prices jump 51% and West rates rise 38%, 16 November 2026 (dataset provider not named)
- Swarajya (citing The Indian Express), Rs 14,000 crore Goregaon-Mulund Link Road first phase from Dindoshi to SGNP likely to open by May 2026, 29 November 2025
- Free Press Journal, BMC floats Rs 1,293 crore tender for Nahur-Airoli flyover under final phase of Goregaon-Mulund Link Road project (date not confirmed)
- Property Nivesh news (citing Mid-Day), Goregaon-Mulund Link Road Clearance, 16 October 2026
- Property Nivesh news (citing Mid-Day), Mumbai's New Sion, Vidyavihar and GMLR Bridges, 23 October 2026
- Property Nivesh news, GMLR Second Tunnel Machine Starts Digging, 8 November 2026
- ANAROCK Research, Residential Market Viewpoints: Mumbai Metropolitan Region Q3 2026, 21 October 2026
- ANAROCK Research, Residential Market Viewpoints MMR Q3 2024, 25 October 2024
- Knight Frank India, India Real Estate: Office and Residential Market H1 2026, 9 July 2026
- Oberoi Realty, investor presentation, Q2 FY27, 16 October 2026
- Free Press Journal, Aarey eco-sensitive zone report, 7 July 2025; Zonal Master Plan report, 24 March 2026; Film City redevelopment report, 23 July 2026
- Free Press Journal, Dharavi rehabilitation salt pan land reports (Bhandup, Kanjurmarg, Mulund)
- Property Nivesh state costs table (Maharashtra stamp duty and registration)