Goregaon-Mulund Link Road: Real Estate Impact, Phases and Status

The Goregaon-Mulund Link Road is a 12.2 km BMC road whose twin tunnels under Sanjay Gandhi National Park are being bored, with the whole road targeted for February 2029. Its effect on property is still an expectation: Goregaon East launch prices rose sharply while Mulund prices stayed flat.

By Mridul Shakya · Edited by Rakesh Mahajan · · 11 min read

A new elevated road and flyover under construction crossing a suburban area with forested hills behind Illustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show any project or building named in this post.

What is the Goregaon-Mulund Link Road and where does it stand?

The Goregaon-Mulund Link Road is a 12.2 km east-west road being built by BMC (the Brihanmumbai Municipal Corporation) to join Goregaon on the Western Express Highway with Mulund on the Eastern Express Highway. As of 8 November 2026 both tunnel boring machines are digging under Sanjay Gandhi National Park and BMC targets February 2029 for the whole road, as reported by the Free Press Journal. Until then, the real estate impact is mostly an expectation that buyers is pricing in, not a commute anybody can use.

The road was estimated at about ₹14,000 crore, according to Swarajya citing The Indian Express (29 November 2025). An older figure of ₹12,013 crore including taxes also circulate, so treat the cost as approximate. BMC itself had set 2028 for full completion in November 2025, and that date has since slipped.

For a city-wide tracker, see our guide to upcoming infrastructure projects in Mumbai that could impact property prices.

GMLR phases: what each part covers and its status

The Free Press Journal (8 November 2026) describes GMLR as a road built in four phases. BMC hasn't published a phase-wise status sheet, so the table lists only the parts with a dated record.

Part of the roadWhat it coversStatus (date)Source
Dindoshi-Film City flyoverSix-lane flyover with an elevated rotary; 1.3 km per TOI, 1.2 km in other reportsCivil work done, due by 15 October 2026 after a load test; earlier targets of May and September 2026 missedThe Times of India, 24 September 2026
GMLR connectorOne of three road structures opened together with the Sion rail overbridge and Vidyavihar flyoverOpened 22 October 2026 (whether it is the Dindoshi-Film City flyover is not confirmed)Property Nivesh news citing Mid-Day, 23 October 2026
Phase 3(B) twin tunnelsFilm City (Goregaon East) to Amar Nagar (Mulund West); 5.34 km bored length, each tunnel 6.675 km with box tunnels, ramps and shaftsBoth TBMs boring from the Film City endFree Press Journal, 8 November 2026
Mulund retrieval shaft and rampsLand at the Amar Nagar end where the machines come out612 of 743 structures cleared, 131 due by December 2026 or early January 2027Free Press Journal, 8 November 2026
Nahur-Airoli flyover1.33 km, described as the final phaseTender reported at ₹1,293 crore (tentative; tender date not confirmed)Free Press Journal, date not confirmed

So the GMLR project status in short: the western flyover end is largely built, the tunnels is just starting, and the eastern flyover towards Airoli is at tender stage on a tentative report. Cost for each phase is not on public record.

The GMLR twin tunnel under the national park

The heart of the project is the GMLR twin tunnel under Sanjay Gandhi National Park. Each tube carries three lanes and has a 13 m internal diameter, as per the Free Press Journal of 8 November 2026. The bored part is 5.34 km, and the rest of the 6.675 km per tunnel is box tunnels, ramps and shafts at the two portals.

The first machine, Tulsi, started on 17 August 2026 and had bored 270 m by 8 November 2026, at about 6 m a day. The second, Vihar, with a 14.49 m cutterhead, started on 7 November 2026. Both are digging from Film City towards Mulund. So 270 m is roughly 5% of the bored length.

The Film City box tunnel sits at the Goregaon portal. Its length and cost is not published separately, so ask BMC when the digging there will ends.

Free property updates

Never Miss a Property Opportunity!

Get the latest property news, investment opportunities, new launches and government plot scheme updates directly.

Where would you like to receive updates?
Send me

Free. Only updates worth your time, and you can stop any time. We never sell or share your number or email. By subscribing you agree to get Property Nivesh updates on the channel you chose. Stop updates

Goregaon to Mulund travel time: the claim as stated

BMC claims the Goregaon to Mulund travel time will drop from about 90 minutes to about 20 minutes once the road opens, as reported by the Free Press Journal on 8 November 2026. The Times of India (24 September 2026) gave a different version: travel between the western and eastern suburbs falling from around 75 minutes to 25. Both are official claims for a road that isn't open yet.

A twin road tunnel construction site with segments stackedIllustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show any project or building named in this post.
ClaimTodayAfter GMLR opensReported by
Goregaon to Mulund (BMC)About 90 minutesAbout 20 minutesFree Press Journal, 8 November 2026
Western to eastern suburbsAround 75 minutesAbout 25 minutesThe Times of India, 24 September 2026

The BMC figure implies a saving of roughly 70 minutes each way. Treat it as a target, nobody has drive it end to end yet.

Property near GMLR: the areas along the road

Buying property near GMLR means buying into one of four quite different belts. The table gives the price evidence on record, one firm per row, with its basis and period. Carpet area is the usable floor inside your walls; it is smaller than built-up area, which adds walls and balconies.

AreaPrice evidenceBasis and periodSource
Goregaon East (incl. Film City Road)₹40,430 per sq ft on new launches, up from ₹26,831 in 2022Carpet, weighted average, 2026 to Q3The Times of India, 16 November 2026 (data provider not named)
Goregaon (east and west together)₹26,078 to ₹27,340 per sq ftBasis not stated, H1 2026Knight Frank India, July 2026
Mulund (east and west together)₹27,083 per sq ftCarpet, average quoted base price, Q3 2026ANAROCK Research, October 2026
Mulund₹23,062 to ₹23,182 per sq ftBasis not stated, H1 2026Knight Frank India, July 2026
Bhandup and Nahur sideNo consultancy price publishedNot on recordAsk for registered sale deeds in the building

Don't compare the ANAROCK and Knight Frank rows, they use different bases. Our Mumbai property rates page keeps our own city tracker.

Goregaon East and Film City Road: the western end

Housing

This is the side where the road begins, at Film City and Dindoshi. The 80-acre Oberoi Garden City township sits here, with mid-segment towers, older societies and MHADA and cluster redevelopments around it. Redevelopment means an old building being pull down and rebuilt by a developer, with old members getting new flats.

Price evidence

The Times of India (16 November 2026) reported a 51% rise in the weighted average launch price, from ₹26,831 per sq ft carpet in 2022 to ₹40,430 in 2026 up to Q3. At the top end, Oberoi Realty reported an average of about ₹54,880 per sq ft carpet on bookings at Oberoi Elysian in July to September 2026, which is one luxury project, not the area.

What the road changes

Goregaon East already have Metro Line 7 at Aarey, Goregaon (East) and Dindoshi, and Line 3 ends at Aarey JVLR. GMLR would add a direct road east, which the area don't have now.

Watch-out

Sales are slow. The same TOI report counts 241 homes launched in 2026 up to Q3 and only 35 absorbed. Film City Road will also host portal works for years, with diversions likely, and you can read more in our news on the second GMLR tunnel machine.

The Aarey side: green land, strict rules

The road passes the edge of Aarey and the 521-acre Film City, so the green rules matter more here than elsewhere along the corridor. Aarey covers 3,162 acres and is an eco-sensitive zone under a 2016 notification, according to an Aarey CEO letter reported by the Free Press Journal (July 2025). Construction there needs approval from the SGNP Eco-Sensitive Zone Committee.

A busy suburban road with diversion barricades and trafficIllustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show any project or building named in this post.

The state approved a Zonal Master Plan for the eco-sensitive zone by GR on 20 March 2026 (Free Press Journal, 24 March 2026). In July 2026 a citizens group asked the Union environment ministry to require wildlife and environmental studies before any Film City redevelopment approvals. So new supply on this side stay limited, and a buyer should ask in writing what the zone allow.

Mulund West and Amar Nagar: the eastern end

Housing

The tunnels come out at Amar Nagar in Mulund West. Large gated projects stand on old industrial land along LBS Marg and the GMLR, including Piramal Revanta, whose address is on the Goregaon-Mulund Link Road itself, and Oberoi's Eternia and Enigma.

Price evidence

ANAROCK put Mulund's average quoted base price at ₹27,083 per sq ft carpet in Q3 2026, against ₹26,900 in Q3 2024, so about 1% in two years. Its quoted rent for a 700 sq ft 2 BHK was ₹42,000 to ₹66,000 a month in Q3 2026. On those two figures a gross yield is roughly 2.7% to 4.2% before costs. Gross yield is a year's rent divided by price; net yield take out maintenance, tax and empty months.

What the road changes

For families who work in Goregaon or the western suburbs, GMLR could be the first fast road across the park. Our news on the GMLR land clearance covers the Amar Nagar end in more detail.

Watch-out

Two clearance counts disagree. Mid-Day (16 October 2026, via our news) said all 604 structures in Amarnagar were cleared, while the Free Press Journal (8 November 2026) said 612 of 743 at the retrieval shaft were done and 131 left. For pocket-by-pocket detail, read our guide to the best areas to buy property in Mulund.

Bhandup and the Nahur side

Bhandup has older societies and slum-rehab buildings, and new high-rises on LBS Marg. SRA means the Slum Rehabilitation Authority, which lets developers rebuild slums and sell extra flats. No consultancy publishes a Bhandup price, so a buyer have to rely on recent registered deals in the same building.

The Nahur side links to GMLR's last leg, the Nahur-Airoli flyover, reported by the Free Press Journal at a tender of ₹1,293 crore for 1.33 km. That is a tentative report with no confirmed date. Metro Line 4 stations in this belt, from Naval Housing to Mulund Naka, are also not open yet.

Also, about 255 to 256 acres of salt pan land along Bhandup, Kanjurmarg and Mulund has been allotted for Dharavi project rehabilitation (Free Press Journal), and local opposition continue.

GMLR completion date and the milestones so far

The GMLR completion date has already moved once. BMC said 2028 in November 2025; the Free Press Journal reported February 2029 on 8 November 2026.

Residential towers next to a new link road at duskIllustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show any project or building named in this post.
DateMilestoneSource
29 November 2025BMC sets 2028 for full completion; cost about ₹14,000 croreSwarajya citing The Indian Express
17 August 2026TBM Tulsi starts boring from Film CityFree Press Journal, 8 November 2026
24 September 2026Dindoshi-Film City flyover civil work done, due by 15 OctoberThe Times of India
16 October 2026604 structures in Amarnagar reported clearedProperty Nivesh news citing Mid-Day
22 October 2026A GMLR connector opens with the Sion and Vidyavihar structuresProperty Nivesh news citing Mid-Day
7 November 2026TBM Vihar starts the second tunnelFree Press Journal, 8 November 2026
8 November 2026Tulsi at 270 m; target February 2029Free Press Journal

Our report on the new Sion, Vidyavihar and GMLR bridges explains what the October opening changes on the ground. Past price moves near a road does not predict future ones, and no firm has published a GMLR price premium.

Checklist before you buy near the GMLR

  1. Check the MahaRERA page of the project. MahaRERA is the state regulator; note the registration number and the completion date it shows.
  2. Ask whether the building has an OC (occupancy certificate, the permission to live in it) or only a CC (commencement certificate, the permission to build).
  3. Ask the developer how far the plot is from the Film City portal, the Amar Nagar shaft or the Nahur flyover works.
  4. For Aarey or Film City side plots, get the eco-sensitive zone status in writing.
  5. Compare price on one basis only, carpet with carpet, and from one source.
  6. Budget for stamp duty: 6% in Mumbai including the 1% metro cess, plus 1% registration capped at ₹30,000, as listed in our state costs table. Confirm before paying.
  7. Plan your commute on today's roads, not on the February 2029 target.

Duty is charged on the higher of agreement value and ready reckoner value (the government's minimum value). See the cost of buying property in Mumbai has the full breakdown.

Where to go next

The GMLR is a slow, phased road with a 2029 target and no proven price effect yet. If Goregaon is on your list, read Goregaon vs Malad for property investment, where the two neighbours is compared on supply and prices. If you work in Powai, which the corridor reach only indirectly, see property investment opportunities in Powai.

Questions

Frequently Asked Questions

Is any part of the Goregaon-Mulund Link Road open now? +

A GMLR connector opened on 22 October 2026 along with the Sion rail overbridge and the Vidyavihar flyover, as reported by Mid-Day via our news. Whether that connector is the Dindoshi-Film City flyover is not confirmed. The twin tunnels, which carry the road under the national park, are still being bored.

What is the GMLR completion date? +

BMC targets February 2029 for the whole road, according to the Free Press Journal on 8 November 2026. In November 2025 BMC had said 2028, and an earlier report gave October 2028 for the tunnels. The date has slipped once already, so treat February 2029 as a target rather than a promise.

How long are the GMLR twin tunnels? +

The tunnel boring machines dig 5.34 km under Sanjay Gandhi National Park, from Film City in Goregaon East to Amar Nagar in Mulund West. Each tunnel is 6.675 km long once box tunnels, ramps and shafts are added, with three lanes and a 13 m internal diameter (Free Press Journal, 8 November 2026).

How much will GMLR cut the Goregaon to Mulund travel time? +

BMC claims a drop from about 90 minutes to about 20 minutes, as reported by the Free Press Journal on 8 November 2026. The Times of India (September 2026) quoted around 75 minutes to 25 for travel between the western and eastern suburbs. Neither has been tested, because the road is not open.

Have prices near GMLR already gone up? +

It depends on the end. The Times of India reported Goregaon East launch prices up 51% from 2022 to 2026, but it linked that to redevelopment and metro lines too. ANAROCK shows Mulund at ₹27,083 per sq ft carpet in Q3 2026, close to its Q3 2024 level. No firm has published a price premium caused by GMLR.

What is the GMLR project cost? +

The road was estimated at about ₹14,000 crore, as reported by Swarajya citing The Indian Express in November 2025, and ANAROCK used the same figure in September 2026. An older figure of ₹12,013 crore including taxes also appears. A phase-wise cost has not been published, so treat the total as approximate.

Will construction affect homes near the tunnel portals? +

Expect years of works. Film City Road hosts the western portal and both machines start there, while the Mulund end needs a retrieval shaft and ramps at Amar Nagar. At that end, 131 of 743 structures were still to be cleared as of November 2026. Ask the developer how close the building is to each work site.

Can new projects come up on the Aarey side once GMLR opens? +

The road does not change the land rules. Aarey is an eco-sensitive zone under a 2016 notification and building there needs approval from the SGNP Eco-Sensitive Zone Committee. A Zonal Master Plan was approved on 20 March 2026. Supply on that side stays limited by these rules, whatever the road brings.

Sources

  1. Free Press Journal, Mumbai's GMLR Project Advances As 2nd TBM Joins Excavation Of Twin Tunnels, 8 November 2026
  2. The Times of India, Goregaon-Mulund Link Road project's flyover linking Dindoshi and Film City set to open by Oct 15, 24 September 2026
  3. The Times of India, Goregaon East property prices jump 51% and West rates rise 38%, 16 November 2026 (dataset provider not named)
  4. Swarajya (citing The Indian Express), Rs 14,000 crore Goregaon-Mulund Link Road first phase from Dindoshi to SGNP likely to open by May 2026, 29 November 2025
  5. Free Press Journal, BMC floats Rs 1,293 crore tender for Nahur-Airoli flyover under final phase of Goregaon-Mulund Link Road project (date not confirmed)
  6. Property Nivesh news (citing Mid-Day), Goregaon-Mulund Link Road Clearance, 16 October 2026
  7. Property Nivesh news (citing Mid-Day), Mumbai's New Sion, Vidyavihar and GMLR Bridges, 23 October 2026
  8. Property Nivesh news, GMLR Second Tunnel Machine Starts Digging, 8 November 2026
  9. ANAROCK Research, Residential Market Viewpoints: Mumbai Metropolitan Region Q3 2026, 21 October 2026
  10. ANAROCK Research, Residential Market Viewpoints MMR Q3 2024, 25 October 2024
  11. Knight Frank India, India Real Estate: Office and Residential Market H1 2026, 9 July 2026
  12. Oberoi Realty, investor presentation, Q2 FY27, 16 October 2026
  13. Free Press Journal, Aarey eco-sensitive zone report, 7 July 2025; Zonal Master Plan report, 24 March 2026; Film City redevelopment report, 23 July 2026
  14. Free Press Journal, Dharavi rehabilitation salt pan land reports (Bhandup, Kanjurmarg, Mulund)
  15. Property Nivesh state costs table (Maharashtra stamp duty and registration)

Mentioned here

Projects in this analysis

Chat with Us +91 79824 13588
A man reading about property on his phone at home

Free advice

Have a question before you buy?

Get straight answers from our advisor on projects, prices, home loans and paperwork. Free, with no obligation.

Unbiased advice. Your data is never sold to builders or brokers.

Prefer WhatsApp? Chat with Us: +91 79824 13588

Free property updates

Never Miss a Property Opportunity!

Get the latest property news, investment opportunities, new launches and government plot scheme updates directly.

Where would you like to receive updates?
Send me

Free. Only updates worth your time, and you can stop any time. We never sell or share your number or email. By subscribing you agree to get Property Nivesh updates on the channel you chose. Stop updates

Rent, sell or advertise

Tell us what you need

Pick one, answer a few questions, and our team calls you back. It is free.

What would you like to do?