Metro Line 3, the South Coastal Road and Atal Setu are already open, so the upcoming infrastructure projects in Mumbai start with Metro 4's first phase and Metro 9's last four stations, both targeted for December 2026, then tunnels and sea links aimed at 2028 to 2029. Price evidence is thinner than adverts suggest: the one rigorous Mumbai study found a 6 to 8% rise within 1 km of Metro Line 1.
By Preeti Pandey · Edited by
Rakesh Mahajan · · 12 min read
Illustrative image Upcoming infrastructure projects in Mumbai: where things stand
The upcoming infrastructure projects in Mumbai that matter most for home prices are Metro 4 to Thane, the unfinished ends of Metro 2B and Metro 9, the Thane-Borivali and Goregaon-Mulund tunnels, the northern coastal road and two sea links. As of 28 November 2026 none of these is finished, and most target dates fall between December 2026 and 2029. Metro Line 3, the South Coastal Road and Atal Setu are already open, so they forms the starting point, not the future.
This page is the index: each project gets its cost, a dated status, the next step and the areas it serve, with a link to our deeper post where one exists. Longer data sit in our Mumbai infrastructure impact reports.
Upcoming metro lines in Mumbai: status line by line
Metro Line 3, the Aqua Line, is open end to end from Aarey JVLR to Cuffe Parade since 8 October 2025, with 2,24,602 average weekday riders in September 2026 (ThePrint, citing MMRC, 3 November 2026). Our Metro Line 3 station-group guide covers it.
Lengths and costs are from Property Nivesh infrastructure records (October 2026) or the report in the status column. CMRS, the Commissioner of Metro Rail Safety, signs off before any line opens; GR means government resolution and DPR a detailed project report.
| Line | Length and cost | Status (source, date) | Next step |
|---|---|---|---|
| Metro 4 and 4A, Wadala to Gaimukh | 32.32 km plus 2.668 km; ₹14,549 crore plus ₹949 crore | Not open; April 2026 target missed. Gaimukh to Cadbury Junction RDSO certified 2 June 2026, CMRS inspection under way (FPJ, Sep 2026) | December 2026 opening announced (transport minister, Oct 2026) |
| Metro 2B, D N Nagar to Mandale | 23.643 km; ₹10,986 crore | Mandale to Chembur open (April and August 2026); 185 m gap at Juhu Circle (Nov 2026) | Full line March 2027 (state, April 2026) |
| Metro 9, Dahisar (E) to Mira-Bhayandar | 10.5 km; ₹6,607 crore | Dahisar (E) to Kashigaon open since 7 April 2026 | Four stations expected December 2026 (MMRDA, Oct 2026) |
| Metro 5, Thane-Bhiwandi-Kalyan | 24.9 km; ₹8,416.51 crore | First train at Kasheli depot (Mid-Day, Nov 2026) | Trials and CMRS; no official date |
| Metro 6, Swami Samarth Nagar to Vikhroli (EEH) | 15.31 km; ₹6,716 crore | Under construction; depot land cleared by the Supreme Court (Sep 2026) | No opening date on record |
| Metro 7A, Andheri (E) to CSMIA T2 | Airport spur of Line 7 | Work resumed (Oct 2026) | Airports Authority of India height nod |
| Metro 10, Gaimukh to Mira Road | 9.676 km; ₹8,535.49 crore with road widening | Approved by the state (FPJ, Aug 2026) | Contract and loans; period to March 2030 |
| Metro 12, Kalyan to Taloja | 23.57 km; ₹5,865 crore | Under construction (our records, Oct 2026) | No opening date on record |
| Metro 13, Mira-Bhayandar to Virar | 25.03 km; ₹17,724.99 crore | Approved by GR of 3 Sep 2026 (FPJ) | Tenders and loans; implementation 2026 to 2031 |
| Metro 11, Wadala (Anik) to Gateway of India | 17.4 km; ₹23,487 crore | State-approved Sep 2025; with the Centre (FPJ, Oct 2025) | Central approval, JICA funding |
| Metro 14, Kanjurmarg to Badlapur | About 43.7 km; cost not fixed | Feasibility re-tendered (Swarajya, June 2026) | Updated DPR, funding model |
Metro 4 matter most for Thane, as its first metro, and MMRDA hasn't published a dated target for the stretch beyond Cadbury Junction to Mulund, Ghatkopar and Wadala. See our Metro Line 4 stretch-by-stretch guide.
The Monorail has been suspended since 20 September 2025 (FPJ, September 2026). For homes near lines that already runs, see our guide to areas near Mumbai metro stations.
Mumbai road projects: tunnels, connectors and flyovers
The big Mumbai road projects are mostly tunnels dug by TBMs (tunnel boring machines), and a tunnel date is only as good as the land at both of it ends.
| Project | Size and cost | Status (source, date) | Next step |
|---|---|---|---|
| Thane-Borivali twin tunnel (MMRDA) | 11.84 km; cost not on record | TBM Nayak boring from Thane since April 2026, TBM Arjuna launched August 2026; Borivali end waits for land (FPJ, Aug 2026) | No tunnel-specific date |
| Goregaon-Mulund Link Road (BMC) | 12.2 km; about ₹14,000 crore (reported) | Both tunnel TBMs boring since 17 Aug and 7 Nov 2026 (FPJ) | BMC target February 2029 |
| Sewri-Worli elevated connector (MMRDA) | Sewri to Worli | Elphinstone Road bridge 63% built (Mid-Day, Nov 2026) | Early 2027, as reported |
| Orange Gate-Marine Drive tunnel (MMRDA) | 9.96 km; ₹8,056 crore | Boring since 3 Dec 2025 (ThePrint) | December 2028 |
| Elevated Eastern Freeway extension (MMRDA) | 13.9 km, Chheda Nagar to Anand Nagar | 51% of piers done (Times of India, Sep 2026) | No date on record |
| Patal Lok underground roads (MMRDA) | 31 km concept | Idea under review (Mumbai Live, Nov 2026) | DPR, funding, approvals |
MMRDA claims the Thane-Borivali tunnel will cut a 23 km trip of 1 to 1.5 hours by Ghodbunder Road to about 15 minutes, with about 80,000 vehicles a day by 2029 (FPJ, 6 August 2026). The December 2028 date often quoted is MMRDA's reported target for all its ongoing projects, not this tunnel's. Both end are compared in our Thane-Borivali tunnel post.
GMLR's finish moved from 2028 (BMC, November 2025) to February 2029 (FPJ, November 2026). At the Mulund end, Mid-Day reported in October 2026 all 604 Amarnagar structures cleared, while FPJ counted 131 of 743 still standing in November, possibly because they count different footprints. Our Goregaon-Mulund Link Road post sets out the phases.
Free property updates
Never Miss a Property Opportunity!
Get the latest property news, investment opportunities, new launches and government plot scheme updates directly.
You're subscribed
One last tap so our WhatsApp updates reach you:
Say hello on WhatsAppIt opens a chat with +91 79824 13588, our main number. Save it in your contacts.
Coastal roads and sea links on the western side
The South Coastal Road, 10.58 km from Marine Drive to the Bandra-Worli Sea Link, has been fully open since 27 January 2025 and carried about 63,000 vehicles a day by March 2026 (FPJ, 14 April 2026). The northern half is still to come; our Coastal Road post follows both.
Illustrative image- Versova-Bandra Sea Link (MSRDC). 9.89 km, cost revised from ₹11,332.82 crore to ₹18,120.96 crore, about 30% complete, target December 2028 (Hindustan Times via Swarajya, April 2026). MSRDC's earlier target was May 2028, so it has already slip once.
- Versova-Bhayandar coastal road (BMC). About 26 km, which BMC puts at about ₹18,000 crore (Mongabay-India, January 2026); another report says ₹18,263 crore. The Bombay High Court allowed mangrove removal on 12 December 2025 and the Supreme Court refused to interfere on 20 March 2026, but no construction progress figure is on record. The chief minister want it done by March 2029 (Times of India, September 2026).
- Uttan-Virar Sea Link (MMRDA). 55.12 km with connectors, approved at ₹58,754.71 crore on 25 November 2025 (PTI), though 2026 reports cite MMRDA cost variants as high as ₹87,427 crore. JICA funding wasn't confirmed as of June 2026, and no construction contract is on record.
MMR infrastructure beyond the city: corridors, airport and Navi Mumbai
Outside the city, MMR infrastructure is mostly long corridors and the new airport.
- Virar-Alibaug Multimodal Corridor (MSRDC). 126.06 km and 14 lanes; Phase 1 (96.41 km, Navghar to Balavali) costs ₹31,793.47 crore and got approval by GR on 7 May 2026. More than half the land is acquired, but it waits on the Centre's viability gap funding (VGF, a grant that make a toll road bankable); work is likely from March 2027 (FPJ, 24 September 2026).
- Navi Mumbai International Airport (NMIA). Domestic flights since 25 December 2025, international since 15 July 2026. Phases I and II are for 20 million passengers a year, rising in stages to 90 million (CIDCO, April 2026), and Hindustan Times and Mumbai Live reported over 4.1 million passengers by late November 2026. See our airport impact post.
- Metro 8, CSMIA to NMIA (CIDCO). 34.89 km and 20 stations at ₹22,862 crore, approved by the state on 27 January 2026, with operations targeted from 2030 (CIDCO, April 2026).
- Navi Mumbai Metro Lines 1A and 2 (CIDCO). CBD Belapur to Sagar Sangam and Pendhar to NMIA Terminal 4, ₹5,575 crore, approved by the state's Cabinet Infrastructure Committee on 9 June 2026; construction from FY 2027-28 and full operation by FY 2031-32. Our Navi Mumbai metro post take them line by line.
- Atal Setu and its links. Open since 13 January 2024. Its 7.35 km connector to the Mumbai-Pune Expressway was 67% built in November 2026 for February 2027 (MMRDA), and CIDCO's Ulwe Coastal Road to the airport was about 80% done for a November 2026 opening that is not confirmed. See our Atal Setu area guide.
For the fringe towns from Virar to Karjat, read our test of emerging MMR locations.
Rail upgrades, the bullet train and Dharavi redevelopment
Illustrative image- Mumbai-Ahmedabad bullet train (NHSRCL). 508 km, with Maharashtra stations at BKC, Thane, Virar and Boisar. At BKC, 4.8 km of tunnel was bored by March 2026 (The Week). The cost is ₹1,08,000 crore in our records (July 2025); YourStory reported in July 2026 a revised cost near ₹1.98 lakh crore, not yet approved. The Railway Minister has said the first Gujarat section, Surat-Bilimora, opens on 15 August 2027, and said in September 2025 that the whole line opens by 2029; no separate BKC date have been notified.
- Suburban rail. Tentative reports in the Free Press Journal and Construction World put the Borivali-Virar 5th and 6th lines about 30% done for 2029 and the Goregaon-Borivali Harbour extension at March 2027. Virar-Dahanu quadrupling reached 64% in August 2026 (Construction World), and the Panvel-Karjat line was nearly 99% done in September 2026 (UNI), its opening not confirmed.
- Dharavi redevelopment. In this state-led rebuild, Adani-led work began in October 2026 on 10,432 rehab homes at the Matunga railway site, with the first five towers due by March 2029 (Mumbai Live, November 2026). Free-sale flats for the open market comes later; see our Dharavi handover timeline report.
Mumbai infrastructure projects 2027 to 2030: targeted dates
Dated targets in order, each with who set it and when. Treat all of them as tentative until a line or road actually open.
| Target | Milestone | Who said it (report date) |
|---|---|---|
| December 2026 | Metro 4 Phase 1 | Transport minister (Oct 2026) |
| December 2026 | Metro 9 Phase 2 | MMRDA (Oct 2026) |
| Early 2027 | Sewri-Worli connector | Mid-Day (Nov 2026) |
| February 2027 | Atal Setu-Mumbai-Pune Expressway connector | MMRDA (Nov 2026) |
| March 2027 | Metro 2B full line | State (April 2026) |
| March 2027 | Virar-Alibaug construction start, likely | FPJ (Sep 2026) |
| 15 August 2027 | Bullet train, Surat-Bilimora (Gujarat) | Railway Minister, as carried by NHSRCL (Nov 2026) |
| December 2028 | Versova-Bandra Sea Link | Hindustan Times via Swarajya (April 2026) |
| December 2028 | Orange Gate-Marine Drive tunnel | MMRDA (Dec 2025) |
| February 2029 | Goregaon-Mulund Link Road | BMC (Nov 2026) |
| March 2029 | Northern coastal road | Chief minister (Sep 2026) |
| March 2029 | First five Dharavi rehab towers | Mumbai Live (Nov 2026) |
| From 2030 | Metro 8 operations | CIDCO (April 2026) |
Which areas each project would serve
Areas are as the authority or the dated report above names them (November 2026). A name on the list means the project passes near it, not that every street gain equally.
| Project | Areas served, as named in the source |
|---|---|
| Metro 4 and 4A | Wadala, Ghatkopar, Vikhroli, Bhandup, Mulund, Majiwada, Manpada, Kasarvadavali, Gaimukh |
| Metro 2B | Mandale, Chembur, Kurla, BKC, Bandra, Khar, Santacruz, Juhu, Andheri West |
| Metro 9 | Dahisar, Mira Road, Bhayandar |
| Metro 6 | Jogeshwari, JVLR, SEEPZ, Powai, Kanjurmarg, Vikhroli |
| Metro 11 | Wadala, Byculla, Crawford Market, CSMT, Gateway of India |
| Metro 13 | Mira-Bhayandar, Naigaon, Nalasopara, Virar |
| Thane-Borivali tunnel | Manpada, Ghodbunder Road, Thane West, Borivali East, Borivali West |
| Goregaon-Mulund Link Road | Goregaon East, Film City, Powai, Bhandup, Mulund West |
| Versova-Bhayandar coastal road | Versova, Malad West, Kandivali West, Borivali West, Dahisar |
| Versova-Bandra Sea Link | Bandra West, Khar, Juhu, Versova |
| Sewri-Worli connector | Sewri, Parel, Prabhadevi, Worli |
| Orange Gate-Marine Drive tunnel | Orange Gate, Girgaon, Marine Drive |
| Virar-Alibaug corridor | Vasai, Bhiwandi, Kalyan, Panvel, Uran, Pen, Alibaug |
| Bullet train | BKC, Thane, Virar, Boisar |
| Dharavi redevelopment | Dharavi, Matunga, Sion, Mahim |
Infrastructure impact on property prices: what the evidence shows
The firmest Mumbai number is from Suri and Cropper (NBER Working Paper 34650, 2026). Using assessed prices for 723 Mumbai subzones from 2011 to 2018, they found a 6 to 8% rise in residential and commercial prices within 1 km of Metro Line 1, against areas 1 to 3 km away, after the line opened.
Illustrative imageConsultancies mostly talks about rents, not prices. Savills India's H1 2026 premium residential report (The Realty Today, 16 July 2026) linked stronger leasing and rent growth to homes near Metro Line 3, the Coastal Road and Atal Setu, with no figure. The JLL-NAREDCO report, as Business Standard reported on 3 September 2026, expects Metro Lines 4, 6 and 11, the Coastal Road and the Borivali-Thane twin tunnel to support redevelopment and land values.
Near the airport, ANAROCK's index had Panvel at 176 by H1 2026 against 164 for Navi Mumbai (2021 = 100), as FPJ reported on 22 August 2026. ANAROCK calls the airport the most significant catalyst there, but 42,330 homes were also added in the Panvel catchment from 2021 to H1 2026.
The gaps matter as much. There is no consultancy figure for a station-level home price premium on Line 3 or Line 4; the bigger premiums quoted in adverts come from developer and portal blogs, not from studies. And forecasts runs ahead of reality: Atal Setu averaged about 22,689 vehicles a day in its first year against more than 56,000 projected (PTI, January 2025).
Prices also rose across the city with or without a new line. Our city tracker, an average across the projects and listings we follow, shows Mumbai at ₹32,000 per sq ft in 2026, up 62% in five years, so a rise near one station is not proof the station caused it. Past growth does not predict future growth; our Mumbai city page carry the wider market lines.
How to check an infrastructure claim in a property advert
Adverts often lead with a metro or a tunnel. Run these checks first.
- Name the project exactly as the authority does and find its latest dated release or news report.
- Pin down the stage: idea, DPR, approval, contract, construction, trial or open. Only an open line changes your commute today.
- Note who set the target and when. A minister's remark, an authority release and a newspaper estimate carry different weight.
- Count how often the date has moved. Metro 4 and the Sewri-Worli connector have both missed earlier targets.
- Measure the distance to the planned station on the authority's alignment, not on the advert's map.
- Ask for the source of any percentage premium. Without a named, dated study, set it aside.
- Check the building's own MahaRERA registration (MahaRERA is Maharashtra's real estate regulator), its possession date and its OC (occupancy certificate). A metro next door does not fix a delayed project.
- Price the flat on today's access. If the deal only works once the line opens, you are paying now for a date that can still slip.
Step 7 is covered in our RERA checks for buyers.
Where to read next
For where a finished project lands soonest, our shortlist of areas to invest in Mumbai in 2027 pick up from here.
Questions
Frequently Asked Questions
Which Mumbai metro line is expected to open next? +
Two openings are targeted for December 2026. Transport Minister Pratap Sarnaik said on 27 October 2026 that Metro 4's first phase, Gaimukh to Cadbury Junction, would open then, and MMRDA expects Metro 9's four Phase 2 stations the same month (Times of India, October 2026). Neither was open by 28 November 2026, and Metro 4 has already missed an April 2026 target.
Which big Mumbai projects are already open? +
Metro Line 3 has run from Aarey JVLR to Cuffe Parade since 8 October 2025. The South Coastal Road has been fully open since 27 January 2025 and Atal Setu since 13 January 2024. Metro Lines 2A and 7 have been fully open since 19 January 2023, and Navi Mumbai International Airport has handled domestic flights since 25 December 2025.
What does it mean when a project is approved but not under construction? +
Approval means the state has cleared the plan and the cost, often through a government resolution, but contractors and money may still be missing. Metro 13 was approved by a GR on 3 September 2026 and still needs tenders and loans. Under construction means physical work, like the GMLR tunnels, where both boring machines were digging by 7 November 2026.
Which Mumbai projects target 2028 and 2029? +
December 2028 is the target for the Versova-Bandra Sea Link and the Orange Gate-Marine Drive tunnel. BMC says February 2029 for the Goregaon-Mulund Link Road, the chief minister wants the northern coastal road done by March 2029, and the first five Dharavi rehab towers are due by March 2029. The Thane-Borivali tunnel has no date of its own.
Do new metro lines raise flat prices in Mumbai? +
They can, but the measured effect is modest. Suri and Cropper (NBER, 2026) found assessed prices within 1 km of Metro Line 1 rose 6 to 8% compared with areas 1 to 3 km away. There is no consultancy figure for a station-level premium on Line 3 or Line 4, so treat the bigger premiums quoted in adverts with caution.
How much do the biggest projects cost? +
The bullet train is the largest, recorded at ₹1,08,000 crore for the whole 508 km line in July 2025, with a revised cost near ₹1.98 lakh crore reported but not approved. Inside the MMR, the Uttan-Virar Sea Link was approved at ₹58,754.71 crore and Virar-Alibaug Phase 1 at ₹31,793.47 crore. Metro 11 is put at ₹23,487 crore.
Which projects are still only plans? +
Metro 14 to Badlapur is back at feasibility stage, and Metro 11 was waiting on central approval when last reported in October 2025. The Uttan-Virar Sea Link is waiting on JICA funding with no construction contract on record. MMRDA's 31 km Patal Lok underground road network is an idea under review, and Third Mumbai is still at planning and land acquisition.
Why do Mumbai infrastructure dates keep moving? +
Most slips on record trace to land, courts and safety checks. The Borivali end of the Thane-Borivali tunnel still waits for land, the northern coastal road needed Bombay High Court and Supreme Court rulings on mangroves, and Metro 4's RDSO certification took about 209 days. Metro 2B's western end is held up by a 185 m gap over one plot.
Sources
- ThePrint (PTI), citing an MMRC release: 46 trips added to Mumbai's Metro Line 3, daily services now reach 337, 3 November 2026
- Free Press Journal: Thane Metro 4, 4A trial runs resume as Gaimukh-Cadbury stretch moves closer to launch, 10 September 2026
- Swarajya: Thane Metro Line 4 first phase from Gaimukh to Cadbury Junction set to open in December 2026, 27 October 2026
- MMRDA: release on the start of trial runs and technical inspection of Metro Lines 4 and 4A, 22 September 2025
- MMRDA: SCLR Phase-II and Chembur Metro Station inauguration release, 13 August 2026
- Property Nivesh news, citing The Indian Express: Metro 2B delay at Juhu Circle, 15 November 2026
- Swarajya, citing Times of India: Four new stations on Mumbai Metro Line 9 Phase 2 expected to open by December, 21 October 2026
- MMRDA: Extended Metro Line 5 to Strengthen Connectivity Across Thane, Bhiwandi, Kalyan and Ulhasnagar (PRC/PR/31/2026), 28 May 2026
- Property Nivesh news, citing Mid-Day: Metro-5 first train at Kasheli depot, 17 November 2026
- Times of India: Supreme Court clears Mumbai Metro 6 depot hurdle, 30 September 2026
- Property Nivesh news: Metro 7A work resumes, AAI nod pending, 14 October 2026
- Free Press Journal: Maharashtra approves Rs 8,535 crore Mumbai Metro Line 10 project with Ghodbunder Road widening, 20 August 2026
- Free Press Journal: Maharashtra Govt approves Rs 17,725-crore Metro Line 13, 3 September 2026
- Free Press Journal: Mumbai Metro Line 11 proposal sent to Centre, 26 October 2025
- Swarajya: MMRDA revives 43.7-km Metro Line 14 project, floats fresh tender for feasibility study, 24 June 2026
- Free Press Journal: Mumbai Monorail, MMRDA awaits IIT Bombay recommendation, 1 September 2026
- Free Press Journal: MMRDA set to launch second TBM Arjuna for Mumbai's Thane-Borivali twin tunnel, 6 August 2026
- Free Press Journal: Mumbai's GMLR project advances as 2nd TBM joins excavation of twin tunnels, 8 November 2026
- Property Nivesh news, citing Mid-Day: Goregaon-Mulund Link Road clearance at Amarnagar, October 2026
- Mongabay-India: The environmental costs of replacing mangroves with a road, 21 January 2026
- Property Nivesh news, citing Mid-Day: Elphinstone Road double-decker bridge, 24 November 2026
- ThePrint: With Dec 2028 deadline, MMRDA begins tunnelling for Orange Gate-Marine Drive link, 3 December 2025
- Times of India: Mumbai's 13.9-km Elevated Eastern Freeway takes off, September 2026
- CIDCO: Budget 2026-27, statement of the Vice Chairman and Managing Director, 18 April 2026
- Property Nivesh news, citing Mumbai Live: Patal Lok tunnel plan, 20 November 2026
- Free Press Journal: Mumbai Coastal Road sees 3.16 crore vehicles since launch, 14 April 2026
- Swarajya, citing Hindustan Times: Bandra-Versova Sea Link redesign gets green nod, 7 April 2026
- Free Press Journal: Supreme Court allows mangrove removal for Versova-Bhayandar coastal road, 21 March 2026
- Times of India: Signal-free Coastal Road from SoBo to Bhayander by 2029, CM, September 2026
- ThePrint (PTI): Maharashtra govt approves Rs 58,754 crore Uttan-Virar sea link plan, 25 November 2025
- Free Press Journal: Virar-Alibaug Multi-Modal Corridor work likely by March 2027, awaits Centre's VGF approval, 24 September 2026
- Directorate General of Information and Public Relations, Maharashtra: Cabinet Infrastructure Committee approves Navi Mumbai Metro Line 1A and Line 2, 9 June 2026
- Property Nivesh news, reporting MMRDA: Atal Setu-Pune connector 67% done, 9 November 2026
- Property Nivesh news, reporting Hindustan Times and Mumbai Live: NMIA passes 4 million passengers, 26 November 2026
- Press Information Bureau: PM inaugurates Atal Setu, 12 January 2024; ThePrint (PTI) on Atal Setu first-year traffic, 29 January 2025
- The Week, quoting the Ministry of Railways: Is the BKC underground train station ready?, 26 March 2026
- Deccan Chronicle (PTI): Railway Minister on the bullet train timeline, 27 September 2025
- YourStory: Inside India's bullet train, July 2026 (revised cost, as reported)
- Free Press Journal and Construction World: Western Railway 5th and 6th line reports, 2026 (tentative)
- Construction World: Virar-Dahanu rail quadrupling reaches 64 per cent, 17 August 2026
- UNI: Panvel-Karjat corridor update, 22 September 2026
- Property Nivesh news, citing Mumbai Live: Dharavi handover timeline, 12 November 2026
- Palak Suri and Maureen L. Cropper: What Are the Benefits of Metro Rail in Mumbai, India?, NBER Working Paper 34650, 2026
- The Realty Today, reporting Savills India's H1 2026 premium residential report, 16 July 2026
- Business Standard, reporting the JLL-NAREDCO Mumbai redevelopment report, 3 September 2026
- Free Press Journal, reporting ANAROCK: Panvel price index and supply, 22 August 2026
- Property Nivesh city tracker: Mumbai market line, updated 2 October 2026
- Property Nivesh infrastructure records: lengths and costs, status as of 9 October 2026