L&T Aravista, Sector 86 Gurgaon
L&T Aravista expected launch date, Sector 86 Gurgaon: timeline and possession
L&T Aravista in Sector 86 Gurgaon has no announced launch date as of 23 November 2026. HRERA Gurugram approved its registration application on 16 November 2026 subject to corrections, but the certificate and number hadn't been issued a week later. Until they are, the project is pre-launch and cannot lawfully be sold.
On possession, the filings carry three dates. The promoter has declared an occupation certificate by 31 December 2032, the draft allotment letter proposes handing over flats by 31 March 2033, and the completion certificate is declared for 31 December 2037.
Below is the dated trail from the 2009 licence to the November hearing, followed by what has to happen next and what could shift the calendar.
- Launch date
- Not announced as of 23 November 2026
- HRERA status
- Approved 16 November 2026, certificate pending
- Likely construction start (Form REP-I)
- 1 January 2027
- Occupation certificate declared
- 31 December 2032
- Unit possession (draft allotment letter)
- 31 March 2033
- Completion certificate declared
- 31 December 2037
The short answer
- L&T Realty has announced no launch date, price list or project page for Aravista as of 23 November 2026.
- HRERA Gurugram approved the Phase 1 application on 16 November 2026, 28 days after it was filed, but will issue the certificate only after listed deficiencies are fixed.
- The promoter's Form REP-I gives 1 January 2027 as the likely start of construction and 31 December 2032 as likely completion, a six-year build.
- The draft allotment letter proposes possession of the unit by 31 March 2033, three months after the declared occupation certificate date.
- No official document contains an EOI, and the promoter has sworn that no marketing or booking has taken place.
- Environment clearance, fire scheme approval and the service plan were still pending at the hearing and are due within six months of the certificate.
When will L&T Aravista launch?
Nobody official has given a date. L&T Realty has made no launch announcement, there's no Aravista page on its website, and neither of its 2026 earnings calls mentions a Gurugram launch. The one firm marker is regulatory: HRERA cleared the application on 16 November 2026, with the certificate held back until listed deficiencies are fixed.
RERA is the real estate law that requires a project to be registered before it's advertised or sold. HRERA is the Haryana authority that applies it, and its Gurugram bench handles this file. In the legal sense, a launch can only follow the registration certificate.
On 23 November 2026 HRERA's project page read 'approved and ready for certificate issuing process'. The registration number field was still empty, and the project didn't appear on the public register of registered projects. Our RERA status page tracks that file in detail.
What the promoter has put on record
The promoter told HRERA in an affidavit that 'no advertisement, marketing, booking and third party rights have been created in the project'. At the hearing it added that no real estate agent has been appointed. Any talk of a launch already under way runs ahead of the record.
What has happened so far, in order?
The land was licensed long before L&T arrived. International Green Scapes Ltd (IGSL), the licence holder, got its first group housing licence in 2009. L&T Realty Properties bought the company in April 2026 for Rs 1,123 crore, and the phasing, building plans and RERA application all followed within about six months.
DTCP, mentioned in the table, is Haryana's Department of Town and Country Planning. It grants colony licences and approves building plans. HRERA's papers place the colony in Sectors 81 and 86, though the market usually calls it Sector 86 Gurgaon.
| Date | What happened | Where it is recorded |
|---|---|---|
| 21 August 2009 | Licence 47 of 2009 granted for a group housing colony (now 11.35 acres) | Draft agreement; HRERA hearing brief |
| 6 October 2012 | Licence 104 of 2012 granted for 6.475 acres | Draft agreement; DTCP licence list |
| 19 August 2015 | Earlier building plans approved, valid to 18 August 2020, without RERA registration | HRERA hearing brief |
| 16 and 29 October 2025 | The two older licences renewed, to 20 August 2029 and 5 October 2029 | Draft agreement |
| 9 February 2026 | Licence 24 of 2026 granted for 2.15 acres, valid to 8 February 2031 | HRERA filings |
| 10 April 2026 | L&T Realty Properties signs to buy 100% of IGSL for Rs 1,123 crore; DTCP zoning plan carries the same date | L&T disclosure; DTCP drawing |
| 13 April 2026 | Acquisition completed; IGSL becomes a wholly owned subsidiary | L&T filing of 14 April 2026 |
| 27 April 2026 | L&T press release: 20 acres in Gurugram, about 3.6 million sq ft of potential | L&T press release |
| 30 June 2026 | Airport height clearance issued, valid to 29 June 2034 | HRERA filings |
| 14 August 2026 | Environment clearance applied for | HRERA hearing brief |
| 16 September 2026 | DTCP approves a nine-phase plan for the colony | DTCP memo filed with HRERA |
| 15 October 2026 | Revised building plans for DTCP Phases II, III and IV approved, valid to 14 October 2031 | DTCP memo cited by HRERA |
| 19 October 2026 | RERA application filed for Phase 1: 7.1969 acres, three towers, 444 flats | Form REP-I |
| 24 and 26 October 2026 | HRERA public notice, then newspaper notices; no objections received | HRERA notice and hearing brief |
| 7 November 2026 | Late fee of about Rs 1.69 crore paid to HRERA | HRERA hearing brief |
| 12 November 2026 | HRERA site visit; the 12 m service road is found not constructed | HRERA hearing brief |
| 16 November 2026 | First hearing: approved as proposed, subject to rectification of deficiencies | HRERA proceedings |
| 19 November 2026 | Promoter uploads documents including the draft application form, allotment letter and agreement | HRERA project page |
| 23 November 2026 | No certificate or number issued; project not on the register | HRERA project page and register |
Two things stand out. The first is pace: 28 days from application to hearing. The second is a legacy issue. HRERA charged the late fee because building plans on the two older licences were approved in 2015, before L&T owned the company, without registration.
Illustrative image What is the possession date of L&T Aravista?
There isn't one date. There are three, and they mean different things. The one HRERA will hold the promoter to is the occupation certificate (OC) by 31 December 2032. The draft allotment letter then proposes possession of the unit by 31 March 2033. A completion certificate is declared for 31 December 2037.
An OC is the authority's certificate that a building is fit to occupy. The completion certificate, or CC, comes later and closes out the project. A buyer's practical date is the possession date written into the allotment letter and the agreement for sale.
| Milestone | Date | Document | What it tells you |
|---|---|---|---|
| Likely start of construction | 1 January 2027 | Form REP-I | The promoter's own estimate to HRERA |
| Likely completion | 31 December 2032 | Form REP-I | Six years after the likely start |
| Occupation certificate | 31 December 2032 | REP-II declaration; draft agreement | The declared date on HRERA's file |
| Possession of the unit | 31 March 2033 | Draft allotment letter | The developer's proposed handover, three months after the OC |
| Completion certificate | 31 December 2037 | REP-II declaration | Five years after the OC date |
These dates cover RERA Phase 1 only: Towers 1, 2 and 3, each with 37 floors above the ground or stilt level. No dates are filed for Towers 4 to 7. The master plan page explains how the nine phases fit together.
L&T Aravista new launch: what stands between approval and the certificate
The order of 16 November 2026 approved the registration 'as proposed subject to rectification of deficiencies'. The certificate follows once the promoter fixes them. Pending items at the hearing included corrections to the online forms and revised drafts of the application form, allotment letter, agreement and brochure, plus quarterly estimates and a project report.
- Before the certificate: corrections to the online A-H form and DPI, the revised sales drafts and brochure, quarterly estimates and the project report.
- Within six months of the certificate: environment clearance (applied for on 14 August 2026), fire scheme approval, and the service plan and estimates (applied for on 10 November 2026).
- Security for those three: HRERA holds three demand drafts of Rs 25 lakh each.
- Before any excavation: mining permission.
HRERA hasn't said when the certificate will come, and we won't guess. What the record shows is that the promoter uploaded a set of documents on 19 November 2026, three days after the hearing. When a number is issued, it will show on the register. Only then does 'new launch' become an accurate label.
What are the next milestones after registration?
Once a registration number appears, the filings point to a clear sequence: sales documents in final form, construction from about 1 January 2027, slab-by-slab progress on three towers, the OC, then possession. The draft payment plan ties buyer instalments to several of these stages, so the build calendar is also the payment calendar.
| Milestone | Date or trigger | Basis |
|---|---|---|
| Registration certificate and number | Not issued on 23 November 2026 | HRERA project page |
| Developer price list and final brochure | Not published | No L&T document yet |
| Agreement for sale executed and registered | Within 90 days of application | Draft payment plan |
| First 30% of the price | 10% within 30 days, 10% within 120 days, 10% within 270 days of application | Draft payment plan |
| Construction start | 1 January 2027 (likely) | Form REP-I |
| Environment clearance, fire scheme, service plan | Within six months of the certificate | HRERA order of 16 November 2026 |
| 5th, 15th and 25th floor slabs, terrace slab, internal finishes | No dates filed; each triggers 10% | Draft payment plan |
| Occupation certificate | 31 December 2032 | REP-II declaration |
| Offer of possession | 31 March 2033 | Draft allotment letter |
| Completion certificate | 31 December 2037 | REP-II declaration |
The slab stages carry no calendar dates in the filings. That's normal for a construction-linked plan, but it means the only fixed points are the start and the OC. The payment plan page works through each draft instalment, and the price page covers what's quoted so far.
Illustrative image L&T Aravista EOI: is there one?
No. An EOI, or expression of interest, is a token some developers collect before launch to gauge demand, and no official Aravista document contains one. A single report quoted in the market spoke of a Rs 10 lakh EOI from October 2026. That sits against the promoter's sworn statement that nothing was marketed or booked.
The matching figure may explain the confusion. The draft application form filed with HRERA sets application money at Rs 10 lakh, counted toward a 10% booking amount. That form is for use after registration, and it's still a draft. Under RERA a promoter can't take more than 10% before the agreement for sale.
The safe reading is plain: pay nothing until a registration number is issued and visible on HRERA's register. The booking process page sets out what the draft form says about applications, refunds and cancellation.
What could change the dates?
Several things on record could move them. The sales documents are drafts that HRERA wants revised. Environment clearance, fire scheme approval and the service plan are still pending. A service road at the site wasn't built when HRERA visited. And some approvals expire before the declared OC date, so they'll need renewing.
- Draft documents: the possession date of 31 March 2033 sits in a draft allotment letter. The revised version could carry the same date or a different one.
- Pending clearances: environment clearance was applied for on 14 August 2026 and not yet obtained at the hearing. Excavation also needs mining permission.
- Site access: HRERA's visit on 12 November 2026 found access by the 60 m and 24 m sector roads, with the 12 m service road not constructed. The promoter submitted road access permission from GMDA.
- Validity of approvals: the building plans are valid to 14 October 2031, and the three licences run to August 2029, October 2029 and February 2031. All end before 31 December 2032.
- Form corrections: Form REP-I puts project cost at Rs 1,731.30 crore while the hearing brief records Rs 1,729.79 crore. Corrections to the form were still pending.
- Later phases: the club sits in the community buildings of DTCP Phase III, outside this registration, so its timing isn't filed.
Track record matters too. This is L&T Realty's first Gurugram project, so there's no local delivery history to judge by. Its record elsewhere, including a reported delay-interest order at a Mumbai project, is covered on the reviews page and the L&T Realty developer page. Road and access detail is on the location page, and the club's place in the plan is on the amenities page.
How to check the launch and possession dates yourself
You don't need to rely on anyone's word, including ours. Every date on this page comes from HRERA's public file or L&T's own disclosures, and the same sources will show the launch when it happens. Six checks take a few minutes and settle most questions about whether sales have lawfully opened.
- Search HRERA Gurugram's register of registered projects for 'L & T Realty Aravista Phase 1' and confirm a registration number is shown.
- Match the promoter name: International Green Scapes Ltd, the L&T subsidiary that holds the licences.
- Read the validity date on the certificate and compare it with the declared OC date of 31 December 2032.
- Compare the possession date in the final allotment letter with the draft's 31 March 2033.
- Check that any payment request names the RERA master account, 'IGSL L&T Realty Aravista Phase-1 Master A/C' at Axis Bank.
- Ask for the price list and payment plan on the developer's own paper, not a summary.
We re-read the HRERA file regularly and update the project overview when something changes. You can compare this with other new project launches in Gurugram, or talk to a Property Nivesh advisor who can walk you through the filings.
Questions people ask
When will L&T Aravista launch?
No launch date has been announced. L&T Realty has issued no price list, brochure or project page, and its July and October 2026 earnings calls don't mention a Gurugram launch. HRERA Gurugram approved the registration on 16 November 2026 subject to corrections, and the certificate hadn't been issued by 23 November 2026. A lawful launch can only follow that certificate.
What is the possession date of L&T Aravista?
The filings give three dates. The promoter has declared an occupation certificate by 31 December 2032. The draft allotment letter proposes possession of the unit by 31 March 2033, three months later. The completion certificate is declared for 31 December 2037. The allotment letter is a draft that HRERA asked to be revised, so confirm the date in the final version.
Is L&T Aravista RERA registered yet?
Not yet. HRERA Gurugram approved the application at its 16 November 2026 hearing, subject to the promoter fixing listed deficiencies. On 23 November 2026 the project page showed the registration number as not yet approved or uploaded, and the project was absent from the public register. Until a number appears there, it remains a pre-launch project.
Is there an EOI for L&T Aravista?
No official document mentions an EOI. A single report quoted in the market described a Rs 10 lakh EOI from October 2026, but the promoter swore to HRERA that no marketing or booking had taken place and said no real estate agent was appointed. The draft application form does set Rs 10 lakh as application money, payable only once sales lawfully open.
When does construction of L&T Aravista start?
Form REP-I, the promoter's application to HRERA, gives 1 January 2027 as the likely start of construction and 31 December 2032 as likely completion, a span of six years. Excavation needs mining permission first, and environment clearance was still awaited at the hearing. HRERA recorded Rs 241 crore as already spent on a project costed at Rs 1,729.79 crore.
Why is the completion certificate date 2037 when the OC is 2032?
The filings state the dates without explaining the gap. The promoter declared the OC for 31 December 2032 and the CC for 31 December 2037, five years apart. The licensed colony has nine DTCP phases, and only two are in this application. Towers 4 to 7, the community building, the EWS block and the school site are still to be applied for.
Which part of the project do these dates cover?
Only RERA Phase 1: 7.1969 acres holding Towers 1, 2 and 3 with 444 flats, plus the sector roads. The full colony is 19.975 acres under three licences in Sectors 81 and 86. Towers 4 to 7 and the community buildings that house the club sit in later DTCP phases, with no registration application and no declared dates yet.
More on L&T Aravista
- L&T Aravista: overview What L&T Aravista is, who builds it, its HRERA status and the headline numbers on record.
- L&T Aravista: price No official price list yet: quoted figures, per sq ft sums and full cost for L&T Aravista.
- L&T Aravista: payment plan Draft stages filed with HRERA, a worked schedule on sample prices and the 10% advance rule.
- L&T Aravista: location Address, access roads, quoted distances and the unbuilt service road around L&T Aravista.
- L&T Aravista: rera RERA status, the pending certificate and how to verify L&T Aravista on the HRERA site yourself.
- L&T Aravista: reviews Pros, cons, L&T Realty's delivery record and who the project suits, from the filings.
- L&T Aravista: brochure No official brochure yet: what the HRERA filings show and how to read one when it arrives.
- L&T Aravista: booking Booking steps, the draft Rs 10 lakh application money, documents and refund terms.
- L&T Aravista: floor plan Carpet areas for all six home types, 1,114 to 2,336 sq ft, and how to read the plans.
- L&T Aravista: master plan Land, nine DTCP phases, seven towers, density and open area from the approved site plan.
- L&T Aravista: amenities 29 listed amenities by user group, the clubhouse's filed size and timing, and what upkeep will involve.
- L&T Aravista: highlights Ten sourced facts on L&T Aravista, with what is on record split from what is only quoted.
- L&T Aravista: investment Corridor prices, rent benchmarks, holding costs and risks for L&T Aravista, with no forecasts.
- L&T Aravista: faqs 27 buyer questions on L&T Aravista answered from HRERA filings: price, RERA, possession, sizes.
Related on Property Nivesh
Talk to an advisor about L&T Aravista
Tell us what you are looking for in L&T Aravista. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.
✓
Request received
A senior property advisor will reach you within 4 working hours. No spam, no builder hand-offs — your details stay with our advisory desk only.
Sources
- HRERA Gurugram, project detail page for L & T Realty Aravista Phase 1 including proceedings of 16 November 2026, read 23 November 2026
- HRERA Gurugram, hearing brief and proceedings, 16 November 2026
- HRERA Gurugram, Form REP-I Parts A to H submitted 19 October 2026, read 23 November 2026
- International Green Scapes Ltd via HRERA, draft allotment letter and draft builder buyer agreement, uploaded 19 November 2026
- HRERA Gurugram, public notice on the registration application, 24 October 2026
- DTCP Haryana via HRERA, approval of phasing plan, 16 September 2026
- Larsen & Toubro, stock exchange disclosures and press release on the IGSL acquisition, 10, 14 and 27 April 2026
- Larsen & Toubro, Q1 and Q2 FY27 earnings call transcripts, 28 July 2026 and 27 October 2026
Property Nivesh is an independent property research and advisory site. This guide is not the website of L&T Realty and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.