Signature Global City Gurgaon: All 7 Projects, RERA Dates and Status
Signature Global City is the name of seven plotted colonies in Gurugram, in Sectors 93, 79B, 63A, 37D (two projects), 81 and 92, each with plots and separately registered floor units. HRERA Gurugram's register, as read on 9 October 2026, lists their latest valid up to dates between 31 January 2027 and 30 November 2027, with one phase each marked lapsed in City 63A, City 37D II, City 81 and City 37D.
By Jaiprakash Mourya · Edited by
Rakesh Mahajan · · 14 min read
Illustrative image What is Signature Global City in Gurgaon?
Signature Global City is the name Signature Global gives to seven plotted colonies in Gurugram, in Sectors 93, 79B, 63A, 37D, 81 and 92. HRERA Gurugram's register, as read on 9 October 2026, lists 24 registrations across them, covering plots and separately registered floor units. As of 28 November 2026 some phases are still running, several dates has passed and four phases are marked lapsed.
A plotted colony is a gated layout where the developer sells plots and builds the roads, parks and services. Here the register also shows floor units, which are builder floors, also called independent floors, means a low-rise building split into separate homes on each level.
RERA is India's real estate law that requires developers to register projects before selling. HRERA is the Haryana Real Estate Regulatory Authority, and its Gurugram register is where nearly every date in this guide come from.
The order below is newest first, based on the date HRERA first registered each project. City 63A and City 37D II share 31 March 2022, and City 81 and City 92 share 27 July 2021, so for those ties we keeps our usual list order.
Our Signature Global developer profile, checked on 3 October 2026, says the company was founded in 2014 by Pradeep Kumar Aggarwal, is headquartered in Gurgaon and is listed on NSE and BSE, with 25 completed projects. Newer launches are in our guide to Signature Global new projects in Gurgaon, so this post stick to the City colonies.
Two other names get mixed up with these. Signature Global's City of Colours township on NH-8 is a separate project in village Sidhrawali; Property Nivesh's records show it registered on 7 October 2024 for 1,058 plots on 129.66 acres. HSIIDC's Global City in Sectors 36, 36B, 37 and 37B is a Haryana government township and is not a Signature Global project, our Global City Gurugram microsite covers that one.
All seven Signature Global City projects at a glance
Three register terms appear in every table. Valid up to is the completion date the promoter declared, and it can be extended by a corrigendum, a correction or extension notice whose content isn't shown here. Lapsed means the register marks the registration as lapsed.
None of these tell you if a building has an occupation certificate (OC), the permission that let people live in it. The register doesn't say whether any phase has one.
The table uses HRERA Gurugram's register, as read on 9 October 2026. Plot and unit counts are our sums of each project's rows, and land shows the plots registration only, since floors sit on that land.
| Project | Sector and village | Promoter company | Registrations | Plots | Units (floors) | Land in plots registration (acres) | Latest valid up to | Lapsed phases |
|---|---|---|---|---|---|---|---|---|
| City 93 | 93, Wazirpur | Signature Builders Private Limited | 2 | 251 | 997 | 17.3188 | 30 November 2027 | None |
| City 79B | 79B, Naungranpur | JMK Holdings Pvt. Ltd. | 2 | 194 | 922 | 12.4875 | 27 April 2027 | None |
| City 63A | 63A, Kadarpur | Signatureglobal (India) Limited (Private Limited on first row) | 3 | 72 | 239 | 5.0125 | 26 February 2027 | 1 |
| City 37D II | 37D, Gadoli Kalan | Rose Building Solutions Private Limited | 2 | 84 | 176 | 5.62 | 24 February 2027 | 1 |
| City 81 | 81, Nakhdola | Sternal Buildcon Private Limited | 3 | 209 | 1,248 | 11.9778 | 27 February 2027 | 1 |
| City 92 | 92, Mevka and Wazirpur | Signature Infrabuild Pvt. Ltd. | 5 | 388 | 1,316 | 10.3 and 8.3125 | 29 March 2027 | None |
| City 37D | 37D, Gaduli Kalan | Signatureglobal Developers Pvt. Ltd. | 7 | 359 | 1,368 | 20.589 and 1.673 | 31 January 2027 | 1 |
Two things stands out. City 37D has the most registrations and City 93 has the latest valid up to date. Each project also uses a different promoter company, which matters when you check who signs your agreement.
Signature Global City 93 possession date and registrations
Signature Global City 93 is in village Wazirpur, Sector 93, with Signature Builders Private Limited as promoter. HRERA Gurugram's register, as read on 9 October 2026, shows two rows, both dated 30 January 2023.
| Registration no. | Phase name | Registered on | Plots or units | Land (acres) | Valid up to | Register status |
|---|---|---|---|---|---|---|
| GGM/682/414/2023/26 | City 93 (floors) | 30 January 2023 | 997 units | 9.304 | 30 November 2027 | Not lapsed, no corrigendum |
| GGM/681/413/2023/25 | City 93 (plots) | 30 January 2023 | 251 plots | 17.3188 | 28 April 2027 | Not lapsed, corrigendum shown |
The Signature Global City 93 possession date most buyers asks about is really the floors registration's valid up to date, 30 November 2027. A completion-date list shared with Property Nivesh on 28 November 2026 gives the same date for one phase, so the records agree. Neither date has passed yet.
The plots registration shows a corrigendum link, so its 28 April 2027 date may already been changed; check the notice on HRERA. The floors Form A-H also gives 9.304 acres in Part B but 17.31875 acres in Part C, we have used Part B, so ask the developer which figure applies.
Free property updates
Never Miss a Property Opportunity!
Get the latest property news, investment opportunities, new launches and government plot scheme updates directly.
You're subscribed
One last tap so our WhatsApp updates reach you:
Say hello on WhatsAppIt opens a chat with +91 79824 13588, our main number. Save it in your contacts.
Signature Global City 79B: plots and a floors phase due in December
Signature Global City 79B is in village Naungranpur, Sector 79B, with JMK Holdings Pvt. Ltd. as promoter. HRERA Gurugram's register, as read on 9 October 2026, lists a plots and a floors registration, both on 12.4875 acres.
Illustrative image| Registration no. | Phase name | Registered on | Plots or units | Land (acres) | Valid up to | Register status |
|---|---|---|---|---|---|---|
| GGM/656/388/2022/131 | City 79B (plots) | 23 December 2022 | 194 plots | 12.4875 | 27 April 2027 | Not lapsed, corrigendum shown |
| GGM/659/391/2023/03 | City 79B -1 (floors) | 12 January 2023 | 922 units | 12.4875 | 31 December 2026 | Not lapsed, no corrigendum |
The floors phase, City 79B -1, is valid up to 31 December 2026, that's barely a month away and no corrigendum link shows for it. The plots phase is valid up to 27 April 2027 and does show a corrigendum.
The completion-date list shared with us says phase-wise dates for City 79B need confirmation, so treat this dates as tentative until you check the live register.
No launch price, unit sizes or price list for City 79B are on record here; ask Signature Global for them. Carpet area is the usable floor inside the walls, while super area, also called saleable area, adds an share of common areas like stairs and lobbies.
Signature Global City 63A possession date by phase
Signature Global City 63A is in village Kadarpur, though the first row lists the locality as Sector 63. HRERA Gurugram's register, as read on 9 October 2026, names Signatureglobal (India) Private Limited on the first row and Signatureglobal (India) Limited on the later two.
| Registration no. | Phase name | Registered on | Plots or units | Land (acres) | Valid up to | Register status |
|---|---|---|---|---|---|---|
| GGM/546/278/2022/21 | City 63A (plots) | 31 March 2022 | 72 plots | 5.0125 | 24 February 2027 | Not lapsed, corrigendum shown |
| GGM/581/313/2022/56 | City 63A (1) (floors) | 27 June 2022 | 205 units | 5.0125 | 26 February 2027 | Not lapsed, corrigendum shown |
| GGM/619/351/2022/94 | City 63A(2) (floors) | 4 October 2022 | 34 units | 1.2395 | 28 February 2026 | Lapsed |
The Signature Global City 63A possession date depend on your phase. The plots phase is valid up to 24 February 2027 and City 63A (1) floors up to 26 February 2027, both with a corrigendum link.
The smaller City 63A(2) phase, 34 units on 1.2395 acres, was valid up to 28 February 2026 and the register marks it as lapsed. If someone offer you a floor there, ask in writing about its status and any fresh registration.
The completion-date list shared with us says phase-wise dates for City 63A need confirmation. No price list or unit sizes is on record here, ask for both before paying any token.
Signature Global City 37D II: one live phase, one lapsed
Signature Global City 37D II is in village Gadoli Kalan, Sector 37D, with Rose Building Solutions Private Limited as promoter. It shares the sector with City 37D but has it's own registrations, as HRERA Gurugram's register, as read on 9 October 2026, shows.
| Registration no. | Phase name | Registered on | Plots or units | Land (acres) | Valid up to | Register status |
|---|---|---|---|---|---|---|
| GGM/545/277/2022/20 | City 37D II (plots) | 31 March 2022 | 84 plots | 5.62 | 24 February 2027 | Not lapsed, corrigendum shown |
| GGM/618/350/2022/93 | City 37D II(2) (floors) | 4 October 2022 | 176 units | 1.42 | 28 February 2026 | Lapsed |
The plots phase is valid up to 24 February 2027 with a corrigendum shown. The completion-date list shared with us calls the same date an extended deadline for one phase, so both records line up.
The floors phase, City 37D II(2), was valid up to 28 February 2026 and the register mark it as lapsed. Prices and unit sizes are not on record here. Our Signature Global Sector 37D guide go deeper on the sector.
Signature Global City 81 possession date and a lapsed floors phase
Signature Global City 81 is in village Nakhdola, Sector 81, with Sternal Buildcon Private Limited as promoter. HRERA Gurugram's register, as read on 9 October 2026, shows three rows.
Illustrative image| Registration no. | Phase name | Registered on | Plots or units | Land (acres) | Valid up to | Register status |
|---|---|---|---|---|---|---|
| GGM/477/209/2021/45 | City 81 (plots) | 27 July 2021 | 209 plots | 11.9778 | 27 June 2026 | Not lapsed, corrigendum shown |
| GGM/478/210/2021/46 | City 81-(1) (floors) | 27 July 2021 | 840 units | 9.12 | 26 February 2026 | Lapsed, corrigendum shown |
| GGM/623/355/2022/98 | City 81(2) (floors) | 27 October 2022 | 408 units | 2.7899 | 27 February 2027 | Not lapsed, corrigendum shown |
The Signature Global City 81 possession date people quote most is 27 June 2026, the plots registration's valid up to date and the original listed deadline in the list shared with us. It has passed as of 28 November 2026.
The plots phase isn't marked lapsed and shows a corrigendum link, which hint at an extension, but the notice's content isn't shown here. Check HRERA before relying on any date.
City 81-(1), with 840 units, was valid up to 26 February 2026 and is marked lapsed, even with a corrigendum link showing. The later City 81(2) phase, 408 units on a 2.7899-acre parcel, valid up to 27 February 2027. No launch price or unit sizes are on record here.
Signature Global City 92 RERA number, dates and page notes
Signature Global City 92 is in villages Mevka and Wazirpur, Sector 92, with Signature Infrabuild Pvt. Ltd. as promoter, spelled Infrbuild on two rows. The RERA number depends on the phase, because HRERA Gurugram's register, as read on 9 October 2026, list five rows.
| Registration no. | Phase name | Registered on | Plots or units | Land (acres) | Valid up to | Register status |
|---|---|---|---|---|---|---|
| GGM/470/202/2021/38 | City 92 (plots) | 27 July 2021 | 191 plots | 10.3 | 27 April 2026 | Not lapsed, corrigendum shown |
| GGM/471/203/2021/39 | City 92-(1) (floors) | 27 July 2021 | 364 units | 7.806 | 28 December 2026 | Not lapsed, corrigendum shown |
| GGM/664/396/2023/08 | City 92-2 (plots) | 13 January 2023 | 197 plots | 8.3125 | 28 March 2026 | Not lapsed, corrigendum shown |
| GGM/665/397/2023/09 | City 92-2 (floors) | 13 January 2023 | 688 units | 8.3125 | 31 December 2026 | Not lapsed, no corrigendum |
| GGM/666/398/2023/10 | City 92-(II) (floors) | 13 January 2023 | 264 units | 2.494 | 29 March 2027 | Not lapsed, corrigendum shown |
Our City 92 project page, checked on 3 October 2026, lists three of these: /38 for plots, /39 for floors and /10 for City 92-(II). It treats City 92-2, the /08 and /09 rows, as a separate colony on a different licence, so don't mix them up when you reading an agreement.
The page describes stilt-plus-four builder floors in 2 BHK and 3 BHK layouts with two toilets each. It gives launch as 2022, status as under construction and possession as Dec 2026.
Dates is where the records disagree. The plots registration gave 30 April 2023 as likely completion and now shows 27 April 2026, which has passed. The floors continuation certificate of 11 November 2025 records an original validity to 31 December 2023, extended to 30 December 2024, continued to 29 December 2025 and now ending on 28 December 2026.
The completion-date list shared with us gives 30 April 2024 and 31 March 2025 for different phases. Those don't match the register, so treat them as tentative earlier deadlines and go by the register's later dates.
Our page also records a July 2026 completion certificate uploaded against the plotted registration. It cover colony services like roads and parks only, and isn't an OC for individual floors.
The licence is held with S.A. Township Private Limited and Ramprastha Estates Private Limited under a registered collaboration agreement, a deal where landowners lets a developer build on their land. The 2023 prospectus recorded Kotak Mahindra Bank term loans secured on the land. The brochure's starred Phase 2 amenities, like the pool and clubhouse, has no date attached.
Signature Global City 37D: the oldest colony and its seven registrations
Signature Global City 37D is the oldest of the seven, first registered on 13 July 2021. The promoter is Signatureglobal Developers Pvt. Ltd., in village Gaduli Kalan, spelled Gadauli Kalan on later rows. HRERA Gurugram's register, as read on 9 October 2026, shows seven rows.
| Registration no. | Phase name | Registered on | Plots or units | Land (acres) | Valid up to | Register status |
|---|---|---|---|---|---|---|
| GGM/462/194/2021/30 | City 37D (plots) | 13 July 2021 | 324 plots | 20.589 | 28 April 2025 | Lapsed, corrigendum shown |
| GGM/463/195/2021/31 | City 37D - 1 (floors) | 13 July 2021 | 632 units | 15.502 | 28 September 2025 | Not lapsed, corrigendum shown |
| GGM/622/354/2022/97 | City 37D-(2) (floors) | 27 October 2022 | 536 units | 4.16 | 28 February 2026 | Not lapsed, no corrigendum |
| GGM/754/486/2023/98 | City 37D-2 (floors) | 30 October 2023 | 60 units | 0.3675 | 28 February 2026 | Not lapsed, no corrigendum |
| GGM/932/664/2025/35 | City 37D-1A (floors) | 28 March 2025 | 68 units | 0.543 | 31 January 2027 | Not lapsed, no corrigendum |
| GGM/930/662/2025/33 | City 37D EXTN. (plots) | 28 March 2025 | 35 plots | 1.673 | 31 January 2027 | Not lapsed, no corrigendum |
| GGM/931/663/2025/34 | City 37D EXTN. (floors) | 28 March 2025 | 72 units | 0.5877 | 31 January 2027 | Not lapsed, no corrigendum |
The plots registration was valid up to 28 April 2025 and are marked lapsed. The completion-date list shared with us says the same.
Three floors phases, City 37D - 1, City 37D-(2) and City 37D-2, have dates that passed before 28 November 2026, yet the register don't mark them lapsed. The three 2025 rows are valid up to 31 January 2027.
Sector detail belong in the Sector 37D guide above. For the wider corridor see our Dwarka Expressway locality page and the Dwarka Expressway investment guide 2026.
What resale asking prices are on record for City 92 and City 93?
Resale asking prices are on record here for only two of the seven colonies. Property Nivesh data shows resale asking prices of roughly ₹10,700 to ₹10,950 per sq ft for City 92 and roughly ₹11,350 to ₹11,900 per sq ft for City 93, for June to September 2026. They're approximate and indicative, and the area basis isn't clear.
Illustrative image| Project | Sector | Resale asking price per sq ft (approx.) | Period | Example in the data |
|---|---|---|---|---|
| City 92 | 92 | ₹10,700 to ₹10,950 | June to September 2026 | 3 BHK, 1,385 to 1,432 sq ft (saleable), about ₹1.59 crore to ₹1.65 crore |
| City 93 | 93 | ₹11,350 to ₹11,900 | June to September 2026 | 3 BHK, 951 sq ft carpet, about ₹2.23 crore |
Asking prices are not deal prices, and past growth does not predict future growth. For sector-wide rates, our Gurgaon property rates page is the better place to compare, and the stamp duty calculator help with registration costs on top.
At company level, our developer profile records FY25 pre-sales of a record ₹10,290 crore and FY26 pre-sales of about ₹8,220 crore, down about 20% amid a Gurugram slowdown (verified August 2026). Those are whole-company numbers, not a figures for any one colony.
How to check a Signature Global City phase on HRERA
Because each colony is split in several registrations, the date that matters is your phase's one. Use these steps before you pay or sign.
- Find the registration number on your allotment letter or agreement and match it to the phase name, such as City 92-(1) or City 37D-1A.
- Search that number on HRERA Gurugram's register and read the valid up to date shown today, not the date in an old brochure.
- Check whether the row says Lapsed Project. If it does, ask the developer in writing which extension or fresh registration applies.
- Open any corrigendum link and note what it changes, such as dates, land area or unit counts.
- Compare the plots or units and land acres on the register with the figures in your agreement.
- Ask for the occupation certificate (OC) for your own building; a colony completion certificate is not the same thing.
- Confirm the promoter company named on the register, since each City project uses a different company, and have a lawyer read any collaboration agreement.
- Ask whether any lender's mortgage on the project land has been released or a no-objection issued for your unit.
For more register checks, read what buyers must check on RERA in 2026 and how to check a builder's track record on RERA. NRIs can also use our NRI buying guide for India 2026.
Where to read next on Signature Global
This guide is a register snapshot, not a verdict on any colony. For the developer's plans south of the city, read our Signature Global new project in Sohna post. If you're weighing a finished floor against one still being built, our ready to move vs under construction guide lay out the trade-offs.
Questions
Frequently Asked Questions
What is the Signature Global City 93 possession date? +
HRERA Gurugram's register, as read on 9 October 2026, lists the City 93 floors registration GGM/682/414/2023/26 as valid up to 30 November 2027 and the plots registration as valid up to 28 April 2027. These are declared completion dates, not promised handover dates, and a corrigendum can change them, so check the live register.
What is the Signature Global City 92 RERA number? +
City 92 has more than one. The plots registration is GGM/470/202/2021/38 and the floors registration is GGM/471/203/2021/39, both dated 27 July 2021. City 92-(II) is GGM/666/398/2023/10. HRERA Gurugram's register also lists two City 92-2 rows from 13 January 2023, which our project page treats as a separate colony.
What is the Signature Global City 81 possession date? +
The plots registration, GGM/477/209/2021/45, was valid up to 27 June 2026 per HRERA Gurugram's register as read on 9 October 2026. That date has passed and a corrigendum link is shown. City 81(2) floors are valid up to 27 February 2027, while City 81-(1) floors are marked lapsed after 26 February 2026.
What is the Signature Global City 63A possession date? +
It depends on the phase. HRERA Gurugram's register, as read on 9 October 2026, shows the plots phase valid up to 24 February 2027 and City 63A (1) floors valid up to 26 February 2027. City 63A(2), with 34 units, was valid up to 28 February 2026 and is marked lapsed. Phase-wise dates still need confirmation.
Is Signature Global City the same as Global City Gurugram? +
No. Global City in Sectors 36, 36B, 37 and 37B is an HSIIDC township, a Haryana government project, and it is not a Signature Global project. Signature Global's City of Colours on NH-8 is also a separate township, distinct from the seven City colonies covered in this guide.
What does lapsed mean on the HRERA register? +
It means HRERA Gurugram's register marks the registration as a Lapsed Project. In this group, City 63A(2), City 37D II(2), City 81-(1) and the City 37D plots registration carry that mark. The mark alone doesn't explain what happens next for buyers, so ask the developer in writing and check the live register.
Do any Signature Global City phases have an occupation certificate? +
The register doesn't say whether an OC was issued for any phase. Our City 92 page records a July 2026 completion certificate covering colony services only, which isn't an occupation certificate for individual floors. Ask Signature Global for the OC of your specific building before taking possession of a floor.
What are resale prices in Signature Global City 92 and City 93? +
Property Nivesh data shows resale asking prices of roughly ₹10,700 to ₹10,950 per sq ft for City 92 and roughly ₹11,350 to ₹11,900 per sq ft for City 93, for June to September 2026. These are approximate asking figures with an unclear area basis, not deal prices, and past growth does not predict future growth.
Sources
- HRERA Gurugram, register of registered projects, as read on 9 October 2026
- HRERA Gurugram, City 92-(1) continuation certificate dated 11 November 2025 (as recorded on our City 92 project page)
- Property Nivesh, Signature Global City 92 project page, facts checked on 3 October 2026
- Property Nivesh, Signature Global developer profile, checked on 3 October 2026 (financials verified August 2026)
- Property Nivesh project-prices dataset, resale asking prices, June to September 2026
- Signatureglobal (India) Ltd, Prospectus, September 2023
- Signature Global, City 92 brochure (as recorded on our City 92 project page)
- Completion-date list shared with Property Nivesh by the site owner, 28 November 2026