How to Check Any Builder's Delivery Track Record on RERA (Step-by-Step)

Search the promoter's name on the state RERA portal and compare each project's completion date at registration with its current date, then read the complaints and OC records. K-RERA is the easiest: one Project Status search lists the original, COVID-19, Section 6 and further extension dates side by side. TNRERA needs a year-by-year search, and MahaRERA's detailed view sits behind a CAPTCHA.

By Preeti Pandey · Edited by Rakesh Mahajan · · 15 min read

Illustration of someone checking records on a laptop at home Illustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show a real RERA portal.

Quick answer: why a builder's track record matters and where to check it

To check builder track record on RERA, compare what the builder promised the regulator with what it delivered, project by project. Three dates do most of the work: the completion date at registration, each extension after it, and the occupancy certificate (OC) date.

Section 4(2)(b) of the RERA Act makes every promoter disclose its last five years of projects, including delays and pending cases. The stakes are real. ICRA Research counted about 1.56 lakh stalled units in the top seven cities in December 2025, nearly 90% from pre-RERA projects. ANAROCK says a record 5,40,400 homes are due there in 2026, and flags execution risk if the West Asia conflict drags on.

What you needTNRERAK-RERAMahaRERA
Promoter searchNone; search each year list'Promoter / Company / Firm Name''Search Promoters' page
Date at registrationOnly where extension text keeps itOwn column'Proposed Completion Date (Original)'
ExtensionsText: 'Extension given upto'COVID-19, Section 6 and further columns'Proposed Completion Date (Revised)'
Past projectsNot shown'Previous Project Details (Last 5 years only)''Promoter Past Experience Details'
OC on the portalNo field foundOC date and PDFNo field found
Login or CAPTCHANoneNoneCAPTCHA on project view

This guide goes deeper than our posts on what buyers must check on RERA and how to check a builder before buying.

Step-by-step: how to check RERA project status on TNRERA

On TNRERA you can see each project's completion date and any extension without a login. But there is no promoter-name or PAN search, so you build the builder's list yourself, one year list at a time.

  1. Open the TNRERA website and go to 'Registration' > 'Projects' > 'Registered Projects - Tamil Nadu' > 'Building'.
  2. Pick a year in the 'Online Registered Projects' card (2026, 2025 or 2024), or one of the 'Offline Registered Projects' cards from 2017 to 2025.
  3. Type the promoter's name into the 'Search projects...' box. It filters only the loaded year, so repeat it for all twelve lists. The Excel and CSV export buttons are very much helpful for this.
  4. Read 'Project Completion Date' and 'Current Status of the Project'. For TN/29/Building/0364/2024 the date reads 31.12.2025 and the status says 'Extension given upto 31.12.2026'.
  5. Offline rows write the extension inside the date cell. In the 2023 offline building list, 54 of 504 rows carry 'Extension' text.
  6. For bookings, open the 'Progress of Work' report and find 'VIII. Sales', since the project page does not show them. The Appaswamy WINGFIELD report for the quarter ending September 2025 shows 133 of 149 flats booked.

The 'Promoter Details' page gives a masked PAN and 'Financial Indicators' but no past projects. Many buyers stops at the first year list and miss the older projects. Do the full search once and save the sheet, it will help when you compare second builder later.

Step-by-step: K-RERA, the fastest builder delay check

K-RERA is the best of the three portals for a builder delay check. One promoter search returns every Karnataka project, with the date at registration and each extension in the same row.

Illustration of someone reading a table of records onlineIllustrative image
Illustrative image: an AI-generated picture of someone reading records online. It does not show a real RERA portal.
  1. The site opens in Kannada; click 'English' at the top.
  2. Go to 'Services' > 'Project Status'. There is no login or CAPTCHA.
  3. Type in 'Promoter / Company / Firm Name' and pick the name from the suggestions. Type the full registered name: a partial name can return nothing, while 'SOBHA LIMITED' returned 122 rows on 22 November 2026.
  4. Read the columns 'PROPOSED COMPLETION DATE AT THE TIME OF REGISTRATION', 'COVID-19 EXTENSION DATE', 'SECTION 6 EXTENSION DATE' and 'FURTHER EXTENSION DATE'.
  5. Click 'View Project Details' and open 'Promoter Details' for 'Previous Project Details (Last 5 years only)'. Keep a notepad open here, it is easy to lose track of which date belong to which phase.
  6. In 'Project Extension Details', read the delay reason and 'Whether any compensation is provided for the Buyer?'. This tab gets skipped often, but the reasons are written here only.
  7. In 'Quarterly Updates', check the completion percentage, the submission date and 'Total No of Units Booked'.

Then check the portal-wide lists. 'Services' > 'Project Extension Status' shows the old and new completion date of each approved extension. The home-page 'DEFAULT PROJECT LIST' carries projects whose completion date has expired. Searching your builder's name in these lists take only a few minutes more.

Step-by-step: MahaRERA project and promoter search

MahaRERA's search pages are open, but the detailed project view sits on the MahaCRITI portal behind a CAPTCHA. You solve it yourself; the field names below are the ones that view uses, so match them on the live page.

  1. Go to 'Home Buyers' > 'Projects' > 'Registered Real Estate Projects'. On 22 November 2026 it showed 50,109 results.
  2. For a builder's full list, use the 'Search Promoters' page. If your agreement names a different company than the brochure, search that company name also.
  3. Each result card shows an 'Extension Certificate' link or 'N/A'. Open the cards with a certificate first.
  4. Click 'View Details', enter the CAPTCHA, and find 'Proposed Completion Date (Original)' and 'Proposed Completion Date (Revised)'.
  5. Scroll to 'Promoter Past Experience Details', which has 'Original Proposed date of completion' and 'Actual Date of Completion' for other projects. On paper it is the most direct track-record table of the three portals.

Watch for three banners: abeyance (bank account frozen), revoked, and deregistered. MahaRERA also says building details are self-updated by the promoter. Take a screenshot of both dates once you are inside, it saves you from doing whole process again.

RERA completion date check: reading original vs extended dates

Measure delay from the completion date declared at registration, not from the latest date on the page. Under Sections 4(2)(l)(C) and 5(3) of the RERA Act, registration runs for the period the promoter declared. That first date is the promise.

Extensions come in three kinds. Each of them mean something different for a buyer. Section 6 allows extension for force majeure, or without default by the promoter, capped at one year in aggregate. Authorities extend further under Section 7(3). And blanket orders added time to all projects automatically.

Blanket orderDateTime added
TNRERA COVID-19 circularsApril and May 20206 months in total
MahaRERA Orders 13/2020 and 14/2020April and May 20206 months in total
MahaRERA Order 21/2021 (second wave)August 20216 months
K-RERA COVID-19 orderNot located9 months on 45 Sobha Limited rows, 6 months on 6
MahaRERA, K-RERA and TNRERA West Asia orders7 to 10 August 20264 months

On 22 November 2026 the K-RERA rows we checked did not yet show the 2026 four months. So the date on a row may be already old, and the authority's orders are worth reading too.

Tamil Nadu adds rules of its own. A first Section 7(3) extension can run up to one year only if Section 6 was not used. Later ones run six months at a time. Once extensions pass one year in total, TNRERA wants an extra 20% of buyer collections put in the separate account.

Worked example: Sobha Lake Gardens Phase 2

Sobha Lake Gardens Phase 2, by Sobha Limited, was approved in June 2018 with 296 apartments. Its completion date at registration was 31 March 2024. The COVID extension took it to 31 December 2024, and a Section 6 extension moved it to 30 December 2025.

K-RERA gives the delay reason as 'Shortage of Building Materials, Concrete, Jalli etc' and answers 'NO' on compensation to buyers. The OC was received on 14 November 2025, and the latest quarterly update shows 296 of 296 units booked.

Sobha Lake Gardens Phase 2: OC date against each completion dateSobha Lake Gardens Phase 2: OC date against each completion date 05101520OC after date at registration (31-03-2024) OC after date at registration (31-03-2024): 20 19.5 monthsOC after COVID-extended date (31-12-2024) OC after COVID-extended date (31-12-2024): 11 10.5 monthsOC ahead of Section 6 date (30-12-2025) OC ahead of Section 6 date (30-12-2025): 2 1.5 months Source: K-RERA project details, read 22 November 2026; months are our arithmetic on the dates shown
The OC of 14 November 2025 came 19.5 months after the first date but before the Section 6 extended date.

The chart shows the OC came 19.5 months after the first date, 10.5 after the COVID date, and 1.5 before the Section 6 date.

So the OC came before the extended deadline but after the first one. We always discuss about both readings with a buyer. More of the builder's record is on our Sobha developer page.

Checking complaints and orders against the builder

Read complaints at the promoter level, not only for your project, then open a few orders. A refund or delay-interest order under Section 18 tells you more than a raw count.

  • K-RERA: the project's 'Complaints' tab shows 'Complaints On this Promoter (n)' and 'Complaints On this Project (n)'. For Sobha Lake Gardens Phase 2 it showed 230 on the promoter and 4 on the project, for a promoter with 122 Karnataka rows. 'Services' > 'Search Orders' finds orders by project or promoter.
  • MahaRERA: 'Complaint Redressal' > 'Complaints' > 'Promoter Wise' gives a 'Number of Complaints' per name. On 22 November 2026 it listed 5,573 promoters. Orders are under 'MahaRERA Order/Judgements'.
  • TNRERA: the project page has no complaints tab. Orders sit under 'Complaints' > 'Complaint (Form-M)-Bench-1' or 'Bench-2' > 'Orders', by year, so type the promoter's name into each list.

What to look for: same complaint repeating across many projects of a builder, and refund orders. A name on K-RERA's 'Revenue Recovery Certificate List', which covers unpaid amounts the authority ordered, is worth asking about. A builder with big portfolio will always have some complaints, so the pattern matters more than the count.

Verifying the OC and CC before possession

Of the three portals, K-RERA's project page is the only one we found that shows the OC date and the OC itself. For Chennai and Mumbai we found no public OC search. Ask the builder for a copy and check it with the body that approved the plan.

Illustration of a completed apartment building ready for possessionIllustrative image
Illustrative image: an AI-generated picture of a completed apartment building. It does not show any project named in this guide.
  • Bengaluru: once the promoter applies for completion, 'Completion Details' shows 'Occupancy certificate received?', the date and the OC as a PDF. 'Approving Authority' names the issuer, such as BBMP, BMRDA or BIAPPA.
  • Chennai: completion certificates come from CMDA, DTCP, local planning authorities or local bodies, and TNRERA's 'Approval Details' tell you which. For Brigade Stellaris in Velachery, planning permission is from CMDA and the building permit from Greater Chennai Corporation.
  • Mumbai: on MahaRERA's project view, 'CC' is the commencement certificate, as in 'CC Issued up-to (No. of Floors)'. We found no OC field in the view's code.

Section 11(4)(b) makes the promoter obtain the certificate and share it with buyers. Under Section 19(10), you must take possession within two months of the OC. So ask for the OC copy early, before final demand letter comes, and keep it with your agreement.

Red flags in a builder's RERA record

Act on red flags that have a legal basis, because you can quote the section when you question the builder.

Illustration of an unfinished apartment frameIllustrative image
Illustrative image: an AI-generated picture of an unfinished apartment frame. It does not show any project named in this guide.
Red flagWhere to checkLegal basis
Current completion date later than the date at registrationDate columns or extension textSections 4(2)(l)(C), 5(3), 6
Extensions past one year in total, or repeatedK-RERA 'FURTHER EXTENSION DATE'; TNRERA extension textSection 6 cap; Section 7(3)
Date passed, no extension, no completion applicationK-RERA expired and default lists; MahaRERA abeyance listsSection 7
Quarterly reports missing or stale'Progress of Work as on' month; 'Quarterly Updates'Section 11(1)
More than 10% asked before a registered agreementPayment schedule against agreement dateSection 13(1)
Demand letter names a different bank accountProject bank details on the portalSection 4(2)(l)(D)

On 22 November 2026, K-RERA's 'Completion Date Expired Projects' tab had 3,009 rows, 2,585 of them marked 'Not Applied for Completion'. MahaRERA's abeyance list for missed quarterly reports ran to 1,632 rows.

K-RERA Project Extension Status, 22 November 2026K-RERA Project Extension Status, 22 November 2026 0500100015002000250030003500Extensions approved Extensions approved: 990 990 projectsExtensions rejected Extensions rejected: 69 69 projectsExtensions under process Extensions under process: 158 158 projectsCompletion date expired Completion date expired: 3009 3009 projects Source: K-RERA, Services, Project Extension Status, read 22 November 2026
Projects past their completion date far outnumber approved extensions on K-RERA.

The chart shows K-RERA's extension tabs: 990 approved, 69 rejected and 158 under process, against 3,009 projects past their completion date.

Quarterly reports are a early warning, so read each one. TNRERA's circular of 2 November 2026 said some promoters were not uploading them regularly. K-RERA levies ₹25,000 for each missed or late update in 2026-27.

Free checklist: builder delay check you can copy

Copy this list in your notes and tick each line for every project you shortlist. On TNRERA, keep extra time for the year-by-year search.

  1. Note the RERA number from the advertisement and search it on the state portal.
  2. Write down the promoter's exact name and PAN or CIN, and match them with your agreement.
  3. Pull all the promoter's projects: K-RERA promoter search, MahaRERA 'Search Promoters', or every TNRERA year list.
  4. For each project, note the completion date at registration and the current date.
  5. Count the months between them and label each extension: COVID, Section 6, further, or the 2026 blanket order.
  6. For completed projects, note the OC date and how long after the first date it came.
  7. Open the last four quarterly reports for your project and check the completion percentage moves.
  8. Compare units booked with total units.
  9. Read the complaint counts for the promoter and the project, then open three orders.
  10. Search the abeyance, default, revoked and caution lists, including TNRERA's 'Public Caution Notice'.
  11. Match the bank account on your demand letter with the project bank details on RERA.
  12. Check the agent's registration on the same portal, as in our checklist for buying through a broker in another city.

Which is right for you: how deep to check

Both buyer types use the same portals, but the depth differs. A first-time buyer checks one project closely, while an investor reads the builder's whole portfolio.

First-time buyer

Go deep on your project and its promoter: extension history, latest quarterly update, complaints, bank account and OC status. Most first-time buyer get lost in the many tabs, so go tab by tab with the checklist above. If you buy under construction with a loan, a delay can mean rent and EMI together for longer. Try a few extra months on our home loan EMI calculator, and see our guide to ready-to-move vs under-construction apartments.

Investor

Read the portfolio, not one phase. Pull every row for the promoter and count how many show a Section 6 or further extension. On completed phases, compare the date at registration with the OC date. Investors who buys in different cities can reuse the same sheet for each portal. For three large builders side by side, see our builder delivery scorecard. Then test returns on the rental yield calculator with a later handover.

How we evaluated the portals

We opened TNRERA, K-RERA and MahaRERA directly on 22 November 2026, without a login, and followed the menus named here. We also read the RERA Act, 2016, the Tamil Nadu RERA Rules, 2017, a Tamil Nadu government order and the three authorities' circulars and orders on extensions. Market figures are from ICRA Research, and from ANAROCK as reported by Business Today. We did not use resident reviews, company filings or listing prices.

The evidence has limits. MahaRERA's project view needs a CAPTCHA, so this guide has no MahaRERA worked example. K-RERA's COVID-19 order is not linked from its project rows, so the 9-month and 6-month lengths here are what the rows show. We found no public OC search for Chennai, Bengaluru or Mumbai. The single Sobha Limited phase shown illustrates the method; it is not a rating of the builder. Portal menus change, so names may differ when you look.

Conclusion

The way to check builder track record is the same on every portal. Find all the promoter's projects, compare each date at registration with the current date and the OC date, then read the complaints. K-RERA puts most of it in one table.

If you want a second pair of eyes on a builder's RERA history before you book, talk to a Property Nivesh advisor.

Disclaimer: Project details and portal menus change. Check every fact on the RERA portal and the builder's documents, and speak to a lawyer or financial adviser before you decide.

Questions

Frequently Asked Questions

how to check builder track record on rera +

Search the promoter's name on the state RERA portal, list all its projects, and compare each project's completion date at registration with its current date and OC date. Then read the complaint counts and a few orders. K-RERA does this in one Project Status search; on TNRERA you search each year list, and on MahaRERA you use 'Search Promoters'.

where does rera show original and extended completion date +

K-RERA shows them as columns: 'PROPOSED COMPLETION DATE AT THE TIME OF REGISTRATION', 'COVID-19 EXTENSION DATE', 'SECTION 6 EXTENSION DATE' and 'FURTHER EXTENSION DATE'. MahaRERA's project view has 'Proposed Completion Date (Original)' and '(Revised)', behind a CAPTCHA. TNRERA shows the current date, with text such as 'Extension given upto 31.12.2026' in the status column or the date cell.

how to check rera project status in tamil nadu +

On the TNRERA website, open 'Registration', then 'Projects', 'Registered Projects - Tamil Nadu' and 'Building'. Pick the online year or an offline year card, type the project or promoter name in the search box, and read 'Project Completion Date' and 'Current Status of the Project'. The status links the latest quarterly report and shows any extension as text.

can a builder extend rera completion date more than once +

Yes. Section 6 caps force majeure or no-default extensions at one year in total, but authorities extend further under Section 7(3). TNRERA allows later Section 7(3) extensions six months at a time, each for 20% of the registration fee. Blanket orders also added time, including four months from MahaRERA, K-RERA and TNRERA in August 2026.

how to check builder complaints on maharera +

Go to 'Complaint Redressal', then 'Complaints', then 'Promoter Wise' or 'Project wise'. Search by state, district and name, and each row shows the 'Number of Complaints' with a 'View' link. For the orders, use 'MahaRERA Order/Judgements', which searches up to one year at a time. On 22 November 2026 the promoter-wise list had 5,573 names.

how to check occupancy certificate online in bangalore +

Open the project on K-RERA, click 'View Project Details' and go to the 'Completion Details' tab. Once the promoter applies for completion, it shows 'Occupancy certificate received?', the date and the OC as a PDF. The 'Approving Authority' field, such as BBMP or BIAPPA, names the body to contact if you want to confirm it.

does a rera extension change the possession date in my agreement +

Not automatically. A RERA extension changes the registration period. MahaRERA's 2020 COVID order deemed possession dates in registered agreements extended by the force majeure period, but that was specific to that order. Read your agreement's delay clause with a lawyer. Section 18 gives interest for each month of delay, or a refund with interest if you withdraw.

is it a red flag if a project's rera completion date has passed +

Yes, if there is no extension and no completion application. K-RERA lists such projects under 'Completion Date Expired Projects', which had 3,009 rows on 22 November 2026, and in its 'DEFAULT PROJECT LIST'. MahaRERA puts them on an abeyance list with the bank account frozen. Check whether the 2026 blanket extension applies before you conclude.

Sources

  1. K-RERA, Project Status results for promoter Sobha Limited (122 rows), Project Extension Status and Default Project List, read 22 November 2026
  2. K-RERA, project details for PRM/KA/RERA/1251/446/PR/180627/001934 (Sobha Lake Gardens Phase 2), read 22 November 2026
  3. K-RERA, Order No. K RERA/ADMIN/10/2026 on force majeure extension, 10 August 2026
  4. TNRERA, Registered Projects (Building) lists and project details for TNRERA/29/BLG/0052/2026 (Brigade Stellaris), read 22 November 2026
  5. TNRERA, Circular No. TNRERA/A2/2761/2025-2 on extension fees, 4 August 2025, and Circular No. TNRERA/A2/2552/2026, 10 August 2026
  6. MahaRERA, Orders No. 14/2020, 21/2021 and 66/2026 on force majeure extensions
  7. MahaRERA, Registered Real Estate Projects search, complaint lists and Abeyance Project List, read 22 November 2026
  8. Government of India, The Real Estate (Regulation and Development) Act, 2016
  9. ICRA Research, Regulatory reforms drive gradual easing of stalled inventory, March 2026
  10. Business Today, reporting ANAROCK Research, West Asia conflict puts record 5.4 lakh housing deliveries at risk in 2026, 11 June 2026
Chat with Us +91 79824 13588
A man reading about property on his phone at home

Free advice

Have a question before you buy?