PropertyNivesh.in

Brokerage back offer

Get your brokerage back on Navraj The Antalyas

Leave your name and mobile number. Our advisor calls you back with the current price and a time for a site visit.

Unbiased advice. Your data is never sold to builders or brokers.

*Conditions apply. Brokerage is part of the discussion with our advisor.

Navraj The Antalyas, Sector 37D Gurgaon

Navraj The Antalyas review, Sector 37D Gurgaon: pros, cons and the developer's record

Navraj The Antalyas in Sector 37D Gurgaon is a RERA-registered low-rise project of 200 apartments in 11 blocks, now officially named The Analia. Its paperwork is on public record, but its developer, Navraj Infratech, has no delivered project in Gurugram yet. So this review rests on filings, not on finished homes.

HRERA Gurugram, the Haryana authority that registers projects under the RERA law, approved the new name by a corrigendum dated 29 July 2024. Its register header still reads THE ANTALYAS, and registration No. 79 of 2023 is unchanged.

Below we set out what counts for the project, what counts against it, the developer's record, the complaint position and the kind of buyer it fits. We give no ratings and quote no residents, because none could be verified.

By Preeti Pandey, Property Nivesh Team Reviewed by Rakesh Mahajan Published Updated
RERA registration
No. 79 of 2023, dated 24 July 2023
Registration valid to
30 April 2027
Size on record
200 apartments, 11 blocks, 5.43 acres
Navraj projects delivered in Gurugram
None found
Allottees by July 2024
173 against 200 registered units
Complaints naming the project
None found in HRERA document searches

The short answer

  • HRERA Gurugram registered the project as No. 79 of 2023 on 24 July 2023, valid to 30 April 2027.
  • The official name has been The Analia since 29 July 2024, though the register header still shows THE ANTALYAS.
  • No delivered Navraj project in Gurugram was found; Navraj Infratech Pvt Ltd was incorporated on 8 October 2020.
  • HRERA recorded 173 allottees against 200 registered units by July 2024.
  • No complaint or order naming the project turned up in HRERA document searches on 23 November 2026.
  • The developer has published no price list, payment plan or brochure; market quotes of Rs 2.33 crore to Rs 3.1 crore are indicative.

Is Navraj The Antalyas a good project?

On the record, it's a properly registered project from a first-time developer. HRERA Gurugram's certificate covers 200 apartments on 5.43 acres in Sector 37D Gurgaon and runs to 30 April 2027. What can't be checked from public sources is build progress, the price list and the payment plan. Those gaps shape this review.

We sorted every fact into three piles: what a regulator's document shows, what is only quoted in the market, and what nobody has published. A review that mixes those piles misleads. The table keeps them apart.

What this review rests on
ItemWhat we haveStanding
RegistrationNo. 79 of 2023, valid to 30 April 2027On record (HRERA certificate)
Size200 apartments, 11 blocks, 5.43 acresOn record (HRERA certificate)
Carpet areas132.88 sq m (140 units), 149.85 sq m (60 units)On record (HRERA Form Part C)
Allottees173 by July 2024On record (HRERA corrigendum)
3 BHK and 4 BHK labels, super areas2,071 to 2,553 sq ft super areaQuoted in the market, indicative
PricesRs 2.33 crore to Rs 3.1 crore in most quotesIndicative; no developer price list
Payment plan and booking amountNot publishedAsk the promoter in writing
Construction progressNo quarterly progress report foundNot confirmed as of 23 November 2026
HRERA's form does not label the two carpet sizes by BHK type.

The project overview has the full fact sheet, and the RERA page walks through the certificate.

What are the pros and cons of Navraj The Antalyas?

The pros are a valid registration, a low-rise plan of 200 homes, 173 allottees on HRERA's record and an expressway that is now open. The cons are a developer with nothing delivered, no published price or payment terms, unconfirmed progress and no licence renewal on file. The table sets them side by side.

Navraj The Antalyas (The Analia): pros and cons from the record
AreaIn its favourAgainst it
Legal statusHRERA registration No. 79 of 2023, valid to 30 April 2027Renewal of DTCP Licence 12 of 2009 beyond 20 May 2024 not seen
DeveloperA second group project, The Kingstown Heights, registered on 20 February 2025No delivered Navraj project found in Gurugram; company formed on 8 October 2020
FormatLow-rise: stilt plus 5 floors, 200 homes on 5.43 acresArea shown as 5.4529 acres in other filings; correction applied for
Buyer protectionsCarpet-area sale, all-inclusive price, no separate EDC/IDCRegistration took eight hearings and a 450% late fee
Demand173 allottees by July 2024Current availability not published
TransparencyPlans, specifications and construction chart are on the HRERA pageNo developer website, brochure, price list or payment plan found
TimelineProjected OC 28 February 2027No progress report or OC found as of 23 November 2026
CorridorDwarka Expressway fully open since 17 August 2025About 10,770 units of available inventory on the corridor in H1 2026 (ANAROCK)
ComplaintsNone naming the project foundComplaint register is not open to direct search
Every entry comes from HRERA or DTCP documents or named research; nothing here is a rating.
An illustrative picture of a landscaped garden walkway in a community of low-rise residential blocks of stilt plus five floors in the evening Illustrative image
Illustrative image, not a picture of Navraj The Antalyas.

The points in its favour, explained

Four things stand in its favour, and each comes from a regulator's file, not a sales pitch: a live registration with buyer-friendly conditions, a low-rise layout, sales evidence recorded by HRERA, and a corridor whose main road is now open. Here is what sits behind each one.

A registration with conditions that protect buyers

The certificate says apartments are sold on carpet area only. Carpet area is the usable floor inside the flat's walls, the measure RERA recognises. The total price must include all charges, with no separate EDC/IDC (external and infrastructure development charges) billed to buyers. The promoter can't take more than 10% before a registered agreement for sale, and 70% of buyer money goes to a separate RERA account.

A low-rise layout with modest density

Eleven blocks of stilt plus 5 floors hold 200 homes. On 5.43 acres that works out to about 37 homes per acre. HRERA's form shows 0.82 acres of parks and playgrounds and 0.135 acres of club house land. The master plan page explains the layout.

Sales evidence that comes from the regulator

At the hearing of 24 July 2023 the promoter said there was 'no sale' in the phase. By the name-change application of July 2024, HRERA recorded 173 allottees against 200 registered units. That's 86.5% in roughly a year. It's a rare demand figure that doesn't depend on marketing.

An expressway that has opened

The Delhi section of Dwarka Expressway was inaugurated on 17 August 2025, completing the 29 km signal-free corridor. ANAROCK puts the corridor's average at Rs 14,180 per sq ft in H1 2026, against Rs 13,350 for Gurugram. The project is quoted in the market at about 1.5 km from the expressway; no official distance exists. More on the location page.

The points against it, explained

The weak spots are mostly about what hasn't been shown. Navraj has no finished project to inspect, the developer has published no commercial terms, a few approvals need fresh copies, and the corridor carries a lot of supply. None of these is a finding of wrongdoing. Each is a question to ask.

No commercial terms from the developer

No developer website, brochure, price list or payment plan is public. The web address in the HRERA form didn't resolve on 23 November 2026. The HRERA upload titled 'PAYMENT PLAN' holds a DTCP building plan memo instead. DTCP is Haryana's Department of Town and Country Planning, which licenses colonies. The price and payment plan pages cover what is quoted.

Market quotes that disagree

Sizes quoted in the market don't match the filing. HRERA lists 132.88 sq m (about 1,430 sq ft) and 149.85 sq m (about 1,613 sq ft) of carpet. Market quotes show carpet of 1,276, 1,421 and 1,600 sq ft, and super areas of 2,071 to 2,553 sq ft. Super area adds a share of common spaces and isn't the RERA measure. Indicative asking rates of both Rs 12,450 and Rs 11,000 per sq ft are in circulation.

Approvals that need fresh copies

  • DTCP Licence 12 of 2009: the certificate records it as valid up to 20 May 2024. No renewal beyond that date appears in the uploaded papers.
  • Airport height clearance: the hearing brief shows it expired on 12 January 2022. Newer letters were uploaded on 1 April 2024, but their dates and validity are not readable on the HRERA page.
  • Fire scheme: 'Not Submitted' at registration. A document with that title was uploaded on 1 April 2024.
  • Site area: 5.43 acres in the certificate, 5.4529 acres in the DTCP order. The promoter applied to DTCP for a correction.

Plenty of supply nearby

ANAROCK counted about 10,770 units of available inventory on the corridor in H1 2026, close to 18 months of sales at the current pace. Buyers have choices, which matters for resale. The investment page has the corridor numbers.

What is Navraj The Antalyas's delivery record in Gurugram?

There is no delivery record to review yet. No completed Navraj project in Gurugram was found, and the promoter told HRERA in its January 2023 application that it had launched nothing in the previous five years. Navraj Infratech Pvt Ltd was incorporated on 8 October 2020, about six years ago.

The Analia is the group's first HRERA-registered project. The second, The Kingstown Heights, was registered to sister company Navraj Township Pvt Ltd on 20 February 2025, also in Sector 37D. So the group has two registered projects and, on the public record, none handed over.

The registration itself wasn't smooth. The application of 27 January 2023 drew a deficiency notice, took eight hearings and carried a late fee of 450% of the registration fee, Rs 26,33,567. Approval came with two Rs 25 lakh securities, bank guarantees or demand drafts, tied to the fire scheme and service plan approvals.

One more structural point. The land is licensed to Ramprastha group companies, and Navraj holds joint development and marketing rights under a DTCP order of 7 December 2022. The Phase-I occupation certificate the promoter mentioned to HRERA belongs to Ramprastha's Primera towers, not to Navraj. The certificate also requires the promoter to clear the land title of any litigation before offering possession. Our Navraj developer page tracks the group.

An illustrative picture of a close view of the facade of low-rise residential blocks of stilt plus five floors with balconies and planters Illustrative image
Illustrative image, not a picture of Navraj The Antalyas.

Are there complaints or HRERA orders?

None naming this project is on record. Searches of HRERA Gurugram's documents on 23 November 2026 turned up no complaint or order naming The Analia or The Antalyas. The complaint register itself isn't searchable without forms, so this is a search result and not a formal clearance.

Navraj Infratech does appear in one older matter, complaint RERA-GRG-4863-2020. It concerned Avenue 34, a plotted development in Sector 34 advertised on Facebook and WhatsApp. The company's counsel stated it 'has never advertised, marketed, booked, sold or offered for sale any plot' there. The final outcome sits in a scanned order that isn't readable, so we draw no conclusion from it.

How to check this yourself

Ask the promoter for a written declaration of pending litigation on the project and the land. Then search the HRERA Gurugram complaint list under both project names and the promoter's name.

Is construction on track for the April 2027 date?

It can't be confirmed from public records. The registration ends on 30 April 2027, about five months from today, and the hearing brief projected the OC (occupation certificate, the permission to occupy) for 28 February 2027. But no quarterly progress report was found on the HRERA page, so the stage on site is unverified.

Dates filed with HRERA and dates quoted
MilestoneDateBasis
Block 1 finishingDecember 2025Promoter's construction chart filed with HRERA
Blocks 2, 3 and 4 finishingMarch, June and September 2026Promoter's construction chart filed with HRERA
Blocks 5 to 11 finishingJuly 2026Promoter's construction chart filed with HRERA
Projected OC28 February 2027HRERA hearing brief
Completion and registration validity30 April 2027HRERA registration certificate
Possession quoted in the marketMostly April 2027; one quote of June 2026Indicative
The chart shows planned dates, not achieved ones.

Every finishing date in the promoter's own chart has now passed. That doesn't tell you the work is done or late; it tells you what to compare a site visit against. We make no forecast of possession. The launch date page has the full timeline.

Who Navraj The Antalyas suits and who it does not

It fits a buyer who wants a low-rise home on the Dwarka Expressway side and is willing to verify a first-time developer's progress in person. It fits less well if you need a proven builder, a ready home, or published terms before you start talking.

A closer fit for

  • End users who prefer six-level blocks over towers and want a larger home: the filed carpet sizes are about 1,430 and 1,613 sq ft.
  • Buyers with budgets near the indicative Rs 2.33 crore to Rs 3.1 crore band who can visit the site before paying.
  • NRIs and outstation buyers, provided someone local can inspect progress and collect documents.

A weaker fit for

  • Buyers who treat a developer's completed projects as a must-have.
  • Anyone who needs to move in now; no OC was found.
  • Investors relying on rent alone: 3 BHK rents in Sector 37D are quoted in the market at about Rs 30,400 a month, which is indicative.

Run your own numbers with the home loan EMI calculator and compare sector rates on our Gurgaon property rates page.

What to check before you rely on any review

A review of an unfinished project is only as good as its documents. Six checks close most of the open points listed above, and each one produces a paper you can keep. Do them before any money moves, and in this order if you can.

  1. Match registration No. 79 of 2023 on the HRERA site under both names, The Antalyas and The Analia.
  2. Ask for the latest quarterly progress report and compare it with the construction chart dates.
  3. Ask for the licence renewal beyond 20 May 2024, the current airport height clearance and the fire scheme approval.
  4. Get the price in writing on carpet area, all-inclusive, with PLC (preferential location charge), club, parking and maintenance spelt out. None of these is published.
  5. Ask for the payment plan and the draft agreement for sale before paying anything. The 10% cap applies until the agreement is registered.
  6. Walk the site and count the blocks at finishing stage.

If you'd like help collecting these papers, talk to our advisor. Buyers who book through Property Nivesh can get the brokerage back; brokerage is part of the discussion with our advisor. The booking page explains the steps.

Questions people ask

Is Navraj The Antalyas RERA registered?

Yes. HRERA Gurugram registered it as No. 79 of 2023 on 24 July 2023, covering 200 apartments in 11 blocks on 5.43 acres in Sector 37D. The registration is valid to 30 April 2027, the completion date the promoter declared. A corrigendum of 29 July 2024 changed only the name, to The Analia.

Has Navraj delivered any project in Gurugram?

No delivered Navraj project in Gurugram was found. Navraj Infratech Pvt Ltd was incorporated on 8 October 2020 and told HRERA in January 2023 that it had launched no projects in the previous five years. The Analia is the group's first registered project. A sister company registered The Kingstown Heights, also in Sector 37D, on 20 February 2025.

Are there any complaints against Navraj The Antalyas?

Searches of HRERA documents on 23 November 2026 show no complaint or order naming The Analia or The Antalyas. The complaint register itself isn't open to direct search, so treat this as a search result, not a clean certificate. Navraj Infratech was a respondent in one earlier complaint about a plotted project called Avenue 34, where it denied any role.

When is possession of Navraj The Antalyas due?

The registration runs to 30 April 2027, and the HRERA hearing brief projected the occupation certificate for 28 February 2027. Market quotes mostly say April 2027. No occupation certificate or progress report was found as of 23 November 2026, so the actual stage on site isn't confirmed from public records. Ask for the latest quarterly progress report.

Are there resident reviews or ratings for Navraj The Antalyas?

No. No occupation certificate is on record, so there are no residents whose experience could be checked, and we publish no ratings for the project. This review uses HRERA and DTCP documents, plus market quotes marked as indicative. Once homes are handed over, finishing quality and maintenance will be the real test, and those can only be judged on site.

Why does Navraj The Antalyas have two names?

The project was registered as The Antalyas. HRERA Gurugram approved a change to The Analia on 29 July 2024, after 118 of the 173 allottees consented and a fee of Rs 5,000 was paid. The corrigendum says only the name changes. The register header still shows THE ANTALYAS, so search under both names and match the registration number.

What are the main concerns with Navraj The Antalyas?

The main open point is execution by a developer with no completed project in Gurugram. Around it sit smaller ones: no published price list or payment plan, no progress report found, a colony licence with no renewal on file beyond 20 May 2024, and market quotes that disagree with each other. Each can be closed with a document request.

More on Navraj The Antalyas

Related on Property Nivesh

Talk to an advisor about Navraj The Antalyas

Tell us what you are looking for in Navraj The Antalyas. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.

Unbiased advice. Your data is never sold to builders or brokers.

Sources

  • HRERA Gurugram, Registration Certificate No. 79 of 2023, The Antalyas, 24 July 2023
  • HRERA Gurugram, project hearing brief and proceedings for registration, 24 July 2023
  • HRERA Gurugram, corrigendum on change of name from The Antalyas to The Analia, 29 July 2024
  • HRERA Gurugram, Form REP-I Part A-H project preview, submitted 27 January 2023, read 23 November 2026
  • HRERA Gurugram (promoter upload), PERT chart for construction of Blocks 1 to 11, uploaded 1 April 2024
  • HRERA Gurugram, order in complaint RERA-GRG-4863-2020 (Avenue 34, Sector 34), hearing 5 July 2021
  • DTCP Haryana, order granting joint development and marketing rights to Navraj Infratech, 7 December 2022
  • Outlook Money (ANAROCK Research), Dwarka Expressway residential corridor report, 9 September 2026

Property Nivesh is an independent property research and advisory site. This guide is not the website of Navraj Group and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.

Chat with Us +91 79824 13588
A couple going through a price list with a property advisor

Latest price list

Get the latest price list for Navraj The Antalyas

Prices and payment plans change often. Our advisor shares the current Navraj The Antalyas price list and books a site visit if you want one.

Unbiased advice. Your data is never sold to builders or brokers.

Prefer WhatsApp? Chat with Us: +91 79824 13588