Raheja Developers Dwarka Expressway Projects: Status, OC, RERA 2026
Raheja Developers has three projects in the Dwarka Expressway sectors: Vanya in Sector 99A, under construction with all four HRERA tower registrations lapsed, and Atharva in Sector 109 and Vedaanta in Sector 108, which Raheja lists as ready to move without a dated OC on record. Shilas Low Rise inside Atharva has been in a project-only insolvency process since 19 November 2024, and none of the projects named in the ED case is on the expressway.
By Akansha Singh · Edited by
Rakesh Mahajan · · 13 min read
Illustrative image Which Raheja Developers projects are on Dwarka Expressway?
Raheja Developers has three projects in the Dwarka Expressway sectors: Raheja Vanya in Sector 99A, Raheja Atharva in Sector 109 and Raheja Vedaanta in Sector 108. Raheja lists Atharva and Vedaanta as ready to move. Vanya is still under construction, and all four of its HRERA registrations have lapsed.
One thing first. Raheja Developers is not K Raheja Corp, they are separate companies. Every HRERA, insolvency and ED record in this guide is about Raheja Developers Ltd, whose own profile sits on our Raheja Developers page.
HRERA Gurugram is the Haryana Real Estate Regulatory Authority for the district, and its register holds a project's dates, status and cases. Sector 99A is carved out of Sector 99 beside the road, so we count it as an expressway sector.
| Project | Sector | Type | Status | HRERA | OC on record | Price (kind, month) |
|---|---|---|---|---|---|---|
| Raheja Vanya (Gulmohar A, Amaltaas B, Palash C, Chandan D) | 99A | Apartments, 639 filed | Under construction, per Raheja | 8(A) of 2018, 18 of 2017, 7(A) of 2018, 19 of 2017; all lapsed | None on record | Asking price in listings, Rs 11,150 per sq ft, August 2025 |
| Raheja Atharva | 109 | Apartments, 774 units per Raheja | Ready to move, per Raheja | Not on the register | Raheja says received; no date on record | Resale asking price, Rs 10,800 per sq ft, September 2026 |
| Shilas Low Rise, inside Atharva | 109 | Independent floors, 94 | In insolvency since 19 Nov 2024 | 90 of 2017; lapsed | Claimed in a press release, no date | Resale asking price under the Shilas name, Rs 14,500 per sq ft, September 2026 |
| Raheja Vedaanta (with Vedas and Vedaanta Floors) | 108 | Apartments and floors, about 598 units per Raheja | Ready to move, per Raheja | Not on the register | No date on record | Resale asking price, Rs 12,350 per sq ft, September 2026 |
Raheja Vanya, Sector 99A: four towers and four lapsed RERA registrations
Vanya is the one Raheja project on the expressway that's still being built. Its four HRERA rows is its four towers: Gulmohar (Tower A), Amaltaas (Tower B), Palash (Tower C) and Chandan (Tower D). The licensed area is 12.48675 acres under DTCP licences 64 of 2013 and 72 of 2014. Four individual licensees hold it under a collaboration agreement.
| Tower | HRERA registration | Apartments filed | Acres | Booked when filed, January 2020 | Registration now | HRERA monitoring cases |
|---|---|---|---|---|---|---|
| Gulmohar (A) | 8(A) of 2018 | 140 | 2.28 | 88 | Lapsed; validity ended 31 Dec 2022 | 6 |
| Amaltaas (B) | 18 of 2017 | 139 | 2.21 | 23 | Lapsed; validity ended 5 Jul 2022 | 6 |
| Palash (C) | 7(A) of 2018 | 140 | 2.28 | 59 | Lapsed; validity ended 31 Dec 2022 | 6 |
| Chandan (D) | 19 of 2017 | 220 | 4.68 | Filed as a project not yet started | Lapsed; no validity date shown | 6 |
Each tower's Form REP-I, the form a builder files with HRERA, set completion at 31 December 2022. On 27 November 2026, 47 months after that date, Raheja's own site still list Vanya among its residential projects under construction. No OC, or occupation certificate, for any tower is on the HRERA record.
The filings give carpet area, the floor inside your walls. A 1 BHK is 55.61 sq m, about 599 sq ft, and a 2 BHK is 74.93 to 90.601 sq m. 3 BHK homes are 91.45 to 116.25 sq m and penthouses 155.75 to 182.876 sq m. Chandan's types runs from 70.62 to 198.23 sq m.
Raheja's page puts Vanya about 500 m from Dwarka Expressway, with what it calls a proposed metro station about 1.5 km away. The same page says 3 towers of ground plus 19 floors, while HRERA hold four tower registrations. The last asking price from listings is Rs 11,150 per sq ft, and it's from August 2025, so old.
Each tower carries 6 HRERA monitoring cases, 24 in all. Every tower has 2 pending, and the rest are at first hearing or not yet received at the office. Vanya is not in any insolvency process today. The company-wide process of 21 August 2025 left out only Shilas Low Rise. Then on 10 April 2026 NCLAT confined it to the Krishna Housing Scheme in Sohna.
Don't mix Vanya up with Vanya City, also in Sector 99A. That one is a different developer, Betterchoice Realtors, and its registration also lapsed.
Raheja Atharva (Sector 109) and Vedaanta (Sector 108): ready to move, but is there an OC?
Raheja lists Atharva as ready to move, as "Sector-109, Dwarka Expressway". Its page gives 774 units in 11 towers on 14.81 acres. It says the occupancy certificate is received and over 400 families live there.
Illustrative imageBut Atharva is not on the HRERA register. No OC date for it is on the HRERA or DTCP record, so ask Raheja for it. DTCP is Haryana's Department of Town and Country Planning, which issue OCs. One more trap: the Atharva page shows HRERA numbers that belong to Vanya's towers, which look like a template error. Those numbers are not Atharva's.
Listings show 1 to 5 BHK homes of 1,045 to 4,370 sq ft super area, the area that adds common spaces to carpet. Resale asking prices were Rs 10,800 per sq ft in September 2026, against a Sector 109 listing average of Rs 13,550. Quoted rents for 2 to 4 BHK homes is Rs 29,000 to 45,000 a month.
There is one dated HRERA step on Atharva. In September 2022 HRERA summoned Raheja's directors to appear on 4 October 2022, on the residents' association's grievances. The association had asked for a structural audit in October 2021. No outcome of that hearing has been reported.
Vedaanta, with Raheja Vedas and Vedaanta Floors, is in Sector 108. Raheja gives about 598 units in 10 towers on 10.67 acres, a mix of high-rise and low-rise, and lists it as ready to move. It's not on HRERA neither, and no OC date is on record.
In November 2016 Raheja's CMD said about 1,300 units had been delivered across Vedaanta, Vedas, Vedaanta Floors, Atharva and Shilas. Today listings show 2 BHK flats to 5 BHK penthouses of 1,365 to 5,534 sq ft super area. Resale asking prices were Rs 12,350 per sq ft in September 2026, under the Sector 108 listing average of Rs 17,450. Quoted rents run Rs 12,000 to 53,000 a month.
For scale, ANAROCK's quarterly series put the average quoted rate for new homes on the corridor at Rs 14,180 per sq ft in Q2 2026. That counts builder stock, not resale. So it is a different measure from the asks above and not a like for like comparison.
Raheja Shilas Low Rise: insolvency since 2024 and an OC date not confirmed
Shilas Low Rise is a block of independent floors inside Atharva, with 94 apartments on 3.66 acres registered as 90 of 2017. Its registration validity ended on 27 August 2022, and it's on the lapsed list. Form REP-I says construction started on 7 January 2011. Completion was first set for 7 January 2015 and later revised to 7 April 2017.
A CIRP, or corporate insolvency resolution process, put a resolution professional in charge and suspends the board. On 19 November 2024 the NCLT Principal Bench ordered one on a plea by over 40 Shilas Low Rise flat buyers. Two days later an interim NCLAT order confined it to Shilas.
On 20 March 2026 NCLAT's final order kept the process confined to Shilas Low Rise. It declined to close it, because flat-buyer issues were unresolved, and other projects' creditors may pursue separate cases.
Now the OC. Raheja's press release of 19 November 2025, published as a paid item, says the OC "has been granted" and handovers have begun. It gives no OC date. Raheja's counsel also told NCLAT the OC was obtained. No OC is on the DTCP or HRERA record, so the OC date isn't confirmed.
The Shilas towers is a separate thing. Raheja describes 3 towers with 153 units of 3 BHK condominiums, and those are not on HRERA. On 27 November 2026 Raheja's under-construction list still showed "Raheja Shilas Independent Floors, Sector 109".
Listings under the Shilas name asked Rs 14,500 per sq ft in September 2026, up from Rs 8,750 in December 2025. They mix towers and floors though, which point to a thin sample. Shilas Low Rise also carries 6 HRERA monitoring cases: 2 pending, 3 at first hearing and 1 not yet received.
Raheja Developers insolvency and ED case: the dated record
Here is the legal record in date order, as filed and reported. Each row gives what was decided or done, and where it stands now.
Illustrative image| Date | Forum | What happened | Status |
|---|---|---|---|
| 20 Aug 2019 | NCLT | Insolvency admitted on a Raheja Sampada (Sector 92) buyer's plea | Set aside by NCLAT, January 2020 |
| 19 Nov 2024 | NCLT Principal Bench | CIRP on a plea by Shilas Low Rise buyers | Continuing, confined to Shilas |
| 21 Nov 2024 | NCLAT | Interim order confining the CIRP to Shilas | Interim |
| 27 Jun 2025 | ED | Searches under Section 17 of PMLA | Investigation |
| 21 Aug 2025 | NCLT | CIRP for allottees of all projects except Shilas Low Rise | Later confined to Krishna Housing Scheme |
| 20 Mar 2026 | NCLAT | Final order keeping the Shilas CIRP confined, not closed | CIRP continuing |
| 10 Apr 2026 | NCLAT | 2025 CIRP confined to Krishna Housing Scheme, Sohna | Continuing for that project |
| 28 Apr 2026 | ED | Provisional attachment, about Rs 1,113.81 crore | Provisional |
| 8 Jun 2026 | NCLT | CIRP limited to Raheja Revanta, Sector 78 | CIRP for Revanta |
| 15 Jun 2026 | ED | Provisional attachment, about Rs 503.48 crore | Provisional |
| 31 Jul 2026 | ED | Provisional attachment, about Rs 782.36 crore; total about Rs 2,399.65 crore | Provisional |
| 6 Nov 2026 | ED, Special PMLA court, Saket | Charge sheet (prosecution complaint) filed | Trial not begun |
NCLT is the National Company Law Tribunal, and NCLAT is the appeals tribunal above it. The ED is the Enforcement Directorate, which act under PMLA, the Prevention of Money Laundering Act.
HRERA's own record is counted company-wide. Its judgements list shows 373 decided matters with Raheja Developers as respondent, from 2018 to 2026. They are 284 complaints, 50 execution, 37 adjudication and 2 suo motu. 23 of them is dated 2026. The list doesn't name the project, so the counts can't be split by tower.
Which projects does the Raheja ED case name, and are any on Dwarka Expressway?
The ED filed its charge sheet on 6 November 2026 before the Special PMLA court in Saket. It seeks confiscation of assets worth Rs 2,399.65 crore. It is against the company, members of its promoter family and 16 other persons and entities.
The projects named in the case are Raheja Revanta, Atlantis, Navin Minar and The Delhi Mall. None of them is on Dwarka Expressway. Revanta is in Sector 78, outside the expressway sectors, and has its own CIRP since 8 June 2026.
The attachments are provisional and came in three orders from April to July 2026. ED did not disclose where the last batch of assets are located. So from the press notes alone, a buyer can't tell whether any unit on the expressway is touched.
The charge sheet carries the ED's allegations, which no court has decided yet, and trial has not begun. The company has denied wrongdoing. It says a RERA-supervised forensic audit show it put more into its projects than it collected. Our news report on the Raheja Developers ED case covers what it means for buyers in Delhi and Gurugram.
If you already own a Raheja flat on Dwarka Expressway
Start with where your project stands, because the routes differ. Owners in a project outside insolvency deal mainly with HRERA. Shilas Low Rise owners are inside an insolvency case, which runs on its own rules.
- HRERA complaint. An allottee can file a complaint with HRERA Gurugram over delay, possession or refund. When an order isn't followed, an execution petition is the next step, the 50 execution matters in Raheja's count are of that kind.
- Compensation. Claims for compensation goes to HRERA's adjudicating officer. The 37 adjudication matters in the count are that kind of case.
- Claims in a CIRP. In an insolvency process, the resolution professional invites claims through a public announcement, called Form A. Allottees file with their agreement, receipts and bank proof before the date it gives.
- Other Raheja projects. Krishna Housing Scheme in Sohna and Revanta in Sector 78 have their own separate processes and notices.
- Your file. Keep the agreement, every receipt, demand letters, any possession offer and your HRERA case numbers in one place.
HRERA lists monitoring cases against each registration number on its site, with their status. So a Vanya or Shilas allottee can follow them there. For the basics of a complaint, our guide to what to check on RERA goes deeper.
What to check before you buy a Raheja flat on resale
Illustrative image- Get a copy of the OC for the exact tower, with its date and memo number. For Atharva and Vedaanta no OC date is on the HRERA or DTCP record, so ask Raheja for it.
- Check any HRERA number the seller quotes against the HRERA register. Atharva's page shows Vanya's numbers.
- For a Vanya flat, remember all four registrations has lapsed and no OC is on record. Ask for the tower's latest construction status in writing.
- For Shilas Low Rise, ask the resolution professional in writing whether a transfer can go through while the CIRP is running.
- Ask whether the seller has a pending HRERA case or a claim filed. Agree in writing who keeps any interest or refund.
- Get an encumbrance check on the unit, since the ED didn't disclose where all its attached assets are.
- Compare the ask with its sector in listings for September 2026. Atharva asked Rs 10,800 against Rs 13,550, and Vedaanta Rs 12,350 against Rs 17,450.
- Work out stamp duty and registration with our stamp duty calculator before you agree a price.
More on Raheja Developers and Dwarka Expressway
Our article on checking a builder's track record on RERA shows how to read the registers used here. The Dwarka Expressway locality guide and the price tracker give the wider market. Our projects on Dwarka Expressway hub lists every builder on the road, sector by sector.
Questions
Frequently Asked Questions
Which Raheja Developers projects are on Dwarka Expressway? +
Raheja Developers has three projects in the Dwarka Expressway sectors: Raheja Vanya in Sector 99A, Raheja Atharva in Sector 109, which includes Shilas Low Rise, and Raheja Vedaanta in Sector 108. Both appear as ready to move on Raheja's own site. Vanya is under construction, and all four of its HRERA tower registrations have lapsed.
Is Raheja Vanya RERA registered? +
Raheja Vanya's four towers, Gulmohar (A), Amaltaas (B), Palash (C) and Chandan (D), were registered with HRERA Gurugram in 2017 and 2018. All four registrations are now on HRERA's lapsed projects list. Each tower's Form REP-I set completion at 31 December 2022, and Raheja still lists Vanya as under construction in November 2026.
Does Raheja Atharva have an occupation certificate? +
Raheja's page says Atharva has received its occupancy certificate and that over 400 families live there. Atharva is not on the HRERA register, and no OC date is on the HRERA or DTCP record. A buyer can ask Raheja or the seller for a copy of the OC for the exact tower, with its date and memo number.
Is Raheja Shilas under insolvency? +
Yes, Shilas Low Rise is. NCLT ordered a CIRP on 19 November 2024 on a plea by over 40 flat buyers. On 20 March 2026 NCLAT kept the process confined to Shilas Low Rise and declined to close it. Raheja says the OC was granted in November 2025, but the OC date is not confirmed.
Is Raheja Vanya part of the Raheja insolvency case? +
No, not now. The company-wide CIRP ordered on 21 August 2025 left out only Shilas Low Rise, and on 10 April 2026 NCLAT confined it to the Krishna Housing Scheme in Sohna. Vanya's four towers are not in any insolvency process, though all four of their HRERA registrations have lapsed.
Are any Raheja projects in the ED case on Dwarka Expressway? +
No. The ED's charge sheet of 6 November 2026 names Raheja Revanta, Atlantis, Navin Minar and The Delhi Mall, and none of them is on Dwarka Expressway. The ED's provisional attachments total about Rs 2,399.65 crore. These are allegations that no court has decided, and the company denies wrongdoing.
Is Raheja Developers the same as K Raheja Corp? +
No. Raheja Developers Ltd, the company behind Vanya, Atharva and Vedaanta on Dwarka Expressway, is a separate company from K Raheja Corp. The HRERA registrations, insolvency orders and ED case in this guide all concern Raheja Developers Ltd, and none of them concerns K Raheja Corp.
How far is Raheja Vanya from Dwarka Expressway? +
Raheja's own project page puts Vanya about 500 m from Dwarka Expressway, with a proposed metro station about 1.5 km away. Vanya is in Sector 99A, which is carved out of Sector 99 beside the road, so we count it as an expressway sector. HRERA's rows give its address as Sector 99A.
Sources
- HRERA Gurugram, Registered Projects list and Lapsed Projects list, read 27 November 2026
- HRERA Gurugram, Form REP-I filings for the Gulmohar, Amaltaas, Palash and Chandan towers of Raheja Vanya and for Raheja Shilas Low Rise, January and February 2020
- HRERA Gurugram, monitoring case records for the Raheja Vanya towers and Raheja Shilas Low Rise, read November 2026
- HRERA Gurugram, Ruling and Judgements list, read 27 November 2026
- Raheja Developers, project pages for Vanya, Atharva, Vedaanta and Shilas, and its ready-to-move and under-construction lists, read November 2026
- Raheja Developers press release on Shillas Low Rise, published as an advertorial in The Tribune, 19 November 2025
- The Economic Times, NCLAT limits insolvency against Raheja to one project, 22 November 2024
- The Economic Times, insolvency process against Raheja Shilas to continue, 3 April 2026
- Free Press Journal, NCLAT rejects Raheja Developers plea to close insolvency process, 3 April 2026
- The Economic Times, NCLAT sets aside insolvency proceedings against Raheja Developers, 26 January 2020
- IBBI, Form A public announcements for Raheja Developers (August 2025), Krishna Housing Scheme (April 2026) and Raheja Revanta (June 2026)
- Directorate of Enforcement, press releases of 28 April, 15 June and 31 July 2026
- The Week (PTI), ED files charge sheet against Raheja builders, 6 November 2026
- Times of India, HRERA summons directors of Raheja on redress steps, 9 September 2022
- The Tribune, Handing over homes at three projects, 26 November 2016
- ANAROCK, Dwarka Expressway quarterly rates, Q2 2026
- Asking prices and rents in property listings, August 2025 and September to October 2026