Emaar Projects in Gurgaon 2026: All 44 by Status, Sector and HRERA

Emaar India, formerly Emaar MGF, has 44 projects and planned sites in our Gurugram list, 27 housing and 17 commercial. Its 2025 housing launches are Urban Ascent in Sector 112 and Serenity Hills in Sector 86; five more projects are under construction, two Marbella plot phases were registered on HRERA in 2026 without a launch, and most older townships are ready.

By Divyangna Pathak · Edited by Rakesh Mahajan · · 11 min read

Bar chart of homes or plots per recent Emaar housing project in Gurugram, from HRERA registrations
Property Nivesh developer guide

How many Emaar projects are there in Gurgaon, and which are registered?

Emaar India, called Emaar MGF until 2020, has 44 projects and planned sites in our Gurugram list: 27 housing and 17 commercial. Of the housing, 2 launched in 2025 (Urban Ascent in Sector 112 and Serenity Hills in Sector 86), 5 are under construction, 3 are registered but not launched, 2 are part-ready, 11 are ready and 4 are only planned. No housing project has launched in 2026 so far.

Every launched or under-construction Emaar housing project have a regular HRERA Gurugram registration. HRERA is the Haryana Real Estate Regulatory Authority, and section 3(1) of the RERA Act bars any booking or sale before a project is registered. Older townships mostly sit on interim numbers from 2017 and 2018, The Palm Springs was delivered in 2011 before RERA, and the 4 planned items have no registration, so none can be booked.

Of the 23 existing housing projects, all but The Palm Springs on Golf Course Road sits on Golf Course Extension Road (Sectors 62, 65 and 66), the Dwarka Expressway (Sectors 102 and 112) or in Sectors 77, 83 and 86. Our Emaar India developer profile covers the company itself.

Emaar India projects by statusNumber of Emaar India projects, homes and commercial, in each status, as of November 2026 0510152025Ready: 2121ReadyPart ready: 22Part readyUnder construction: 1010Under constructionLaunched: 33LaunchedRegistered: 44RegisteredPlanned: 44Planned Source: Property Nivesh research, November 2026
Emaar India projects, homes and commercial, grouped by where they stand today.

The chart counts Emaar's Gurugram projects by status.

Which Emaar housing projects in Gurugram are launched, under construction or ready?

Below is all 23 housing projects, newest status first. Completion is the date declared on HRERA. An OC (occupation certificate) is the approval to move in, a CC is a colony's completion certificate, and EWS homes are for the economically weaker section. Most newer ones sit on Golf Course Extension Road.

ProjectSectorTypeStatusHRERA numberCompletion or possessionHomes
Urban Ascent112ApartmentsLaunched, Jan 2025RC/REP/HARERA/GGM/898/630/2025/0130 Nov 2031816, plus 160 EWS
Emaar Serenity Hills86ApartmentsLaunched, Nov 2025RC/REP/HARERA/GGM/993/725/2025/96 (Phase 1); RC/REP/HARERA/GGM/994/726/2025/97 (Phase 2)30 Sep 2032997 (581 plus 416)
Urban Oasis62 and 65ApartmentsUnder constructionRC/REP/HARERA/GGM/741/473/2023/85 (Phases 1 and 2); RC/REP/HARERA/GGM/888/620/2024/115 (Phase 4)30 Sep 2028 (Phases 1 and 2), 30 Sep 2029 (Phase 4); no OC525
Amaris62ApartmentsUnder constructionRC/REP/HARERA/GGM/885/617/2024/11230 Aug 2030522
The 88112ApartmentsUnder constructionRC/REP/HARERA/GGM/791/523/2024/1831 Mar 202988, plus 16 EWS
Marbella Phase 265 and 66PlotsUnder constructionRC/REP/HARERA/GGM/440/172/2021/0831 Dec 2027; no CC501 plots
Emerald Hills Phase 262 and 65PlotsUnder constructionRC/REP/HARERA/GGM/716/448/2023/6010 Aug 2027473 plots
Marbella Terraces66PlotsRegistered, not launchedRC/REP/HARERA/GGM/1068/800/2026/4031 Dec 2031247 plots
Marbella Phase 766PlotsRegistered, not launchedRC/REP/HARERA/GGM/1080/812/2026/52Certificate valid to 31 Dec 203112 plots
Emerald Nuevo65 and 62Not statedRegistered; lapsed on HRERARC/REP/HARERA/GGM/387/119/2020/03NoneNot stated
Emerald Hills62 and 65Plots, floorsPart-ready162 of 2017 (interim)Partly delivered; rest to 28 Feb 2030831 (continued area)
Palm Heights77ApartmentsPart-readyRC/REP/HARERA/GGM/297/2018/29OC 17 Mar 2023 for 198 flats297
Marbella (villas)65 and 66Villas, plotsReady307 of 2017 (interim)Villas handed over; OCs undatedNot stated
Emerald Estate, with Emerald Floors Premier65Apartments, floorsReady104 of 2017 (interim)OCs 5 Mar 2019; CC 15 Apr 2026Not stated
Emerald Classic65Duplex apartmentsReadyRC/REP/HARERA/GGM/362/94/2019/56OC 26 Oct 2021; CC 15 Apr 2026Not stated
Emaar Digihomes62ApartmentsReadyRC/REP/HARERA/GGM/337/69/2019/31OC 11 Apr 2023369, plus 135 EWS
Palm Hills (with Palm Select, Palm Premier)77ApartmentsReady256 of 2017; 01 of 2018; RC/REP/HARERA/GGM/396/128/2020/12; RC/REP/HARERA/GGM/382/114/2019/76OCs of 2019 and 2020Not stated
Palm Gardens83ApartmentsReady330 of 2017 (interim)CC 30 Dec 2025Not stated
The Palm Drive and Palm Terrace Select66Apartments, villasReadyRC/REP/HARERA/GGM/408/140/2020/24OC 25 Jan 2018720, plus 48 EWS
Palm Terraces Select66ApartmentsReady19 of 2018 (interim)OCs 8 Mar and 8 Aug 2019Not stated
Gurgaon Greens102ApartmentsReady36(A) of 2017 (interim)OCs 30 May 2019 to 16 Aug 2021Not stated
Imperial Gardens (two phases)102ApartmentsReady208 of 2017; RC/REP/HARERA/GGM/320/52/2019/14OCs 17 Oct 2018 and 17 Oct 2019; CC 18 Sep 2025Not stated
The Palm Springs54, Golf Course RoadApartments, villasReadyNone (before RERA)Delivered 2011Not stated

Emerald Nuevo, registered in January 2020, is marked lapsed. At Marbella Phase 2, Emaar told HRERA on 6 July 2026 that Phases 1 and 2 are complete, yet no CC is on the portal, and its booking figures are not matching: 52 of 501 plots in April 2026 against 137 in its 2024-25 forms.

Emaar India housing projects by year of RERA registrationNumber of Emaar India housing projects first registered with HRERA Gurugram in each year 012345672017: 7720172018: 2220182019: 2220192020: 2220202021: 1120212023: 2220232024: 2220242025: 2220252026 so far: 222026 so far Source: HRERA Gurugram registrations, as researched by Property Nivesh, November 2026
Emaar India projects by the year of their first registration. A registration usually comes just before sales open.

The chart counts housing projects by year of first HRERA registration; 2017 is mostly old townships.

What did Emaar launch in Gurgaon in 2025 and 2026, and how much is booked?

Two, both in 2025, and none yet in 2026. Urban Ascent, which the CEO called the year's first launch (PTI, 26 January 2025), has 816 flats and 160 EWS flats on 9.164 acres in Sector 112 on the Dwarka Expressway, and Emaar's HRERA filing shows 657 of the 816 booked by April 2026.

It is Phases 2 and 3 of the colony whose Phase 1 is The 88, where Emaar declared 84 of 88 flats booked. Carpet sizes runs from 1,001 to 1,861 sq ft. At registration its environment clearance had expired, so ask to see the renewal.

Serenity Hills launched on 12 November 2025, The Tribune reported, on 25.9 acres in Sector 86, New Gurugram. Its 997 flats in seven towers sit in two registrations, Phase 1 with 581 and Phase 2 with 416, and Emaar's HRERA filing of April 2026 shows 111 Phase 1 flats booked and none in Phase 2, so very much flats was still open then.

HRERA lists 3 BHK of 947 to 1,221 sq ft carpet and 4 BHK of 1,576 sq ft in Phase 2 only. It gives completion as 30 September 2032 for both phases, while press reports at launch mentioned June 2030, so get the date in your agreement.

In 2026 HRERA registered two Marbella plot phases in Sector 66, and neither are launched: Marbella Terraces, once Phase 5, with 247 plots on 20.24225 acres (25 June 2026), and Marbella Phase 7 with 12 plots of 3,218 to 4,500 sq ft (5 August 2026). Phase 7's list entry shows completion as 31 December 2026 against 31 December 2031 on the certificate, so ask which one apply. For both, Emaar's CEO gave HRERA an affidavit that no plot was marketed or sold before registration.

Emaar India projects: homes or plots per projectNumber of homes, or plots in plotted colonies, in each Emaar India project that publishes a count 02004006008001,000Emaar Serenity Hills Emaar Serenity Hills: 997 997 homesEmerald Hills Emerald Hills: 831 831 unitsUrban Ascent Urban Ascent: 816 816 homesThe Palm Drive & Palm Terrace Select The Palm Drive & Palm Terrace Select: 720 720 homesUrban Oasis Urban Oasis: 525 525 homesAmaris Amaris: 522 522 homesMarbella Phase 2 Marbella Phase 2: 501 501 plotsEmerald Hills Phase 2 Emerald Hills Phase 2: 473 473 plotsEmaar Digihomes Emaar Digihomes: 369 369 homesPalm Heights Palm Heights: 297 297 homes Source: HRERA Gurugram registrations and developer disclosures, as researched by Property Nivesh, November 2026
Homes, or plots in plotted colonies, in each Emaar India project, as registered or disclosed.

The chart shows homes or plots per project, where HRERA gives a count.

What is Emaar planning in Gurgaon for late 2026 and 2027?

No dated Gurugram launch is published for late 2026 or 2027, and the planned items below have no date or registration, so they cannot be booked.

ProjectSectorWhat is knownSource and dateStatus
Urban Ascent112816 flats; 657 bookedPTI, 26 Jan 2025; HRERA filing, Apr 2026Launched
Emaar Serenity Hills86997 flats; 111 booked in Phase 1, none in Phase 2The Tribune, 12 Nov 2025; HRERA filing, Apr 2026Launched
Marbella Terraces66247 plots; no launch foundHRERA certificate, 25 Jun 2026Registered, not launched
Marbella Phase 76612 plots; no launch foundHRERA certificate, 5 Aug 2026Registered, not launched
Serenity Hills, later phases86About 10.7 acres not registeredHRERA certificate, 16 Oct 2025Planned; no registration
Marbella Phases 3, 4, 6 and 8 to 1165 and 66Unlaunched, Emaar told HRERAHRERA hearing, 6 Jul 2026Planned; no registration
Zen GardenNot statedTied to the MGF settlementIndia Ratings, 12 Aug 2026Planned; no registration
Sector 26 project (unnamed)26Tied to the MGF settlementIndia Ratings, 12 Aug 2026Planned; no registration

Most of it hangs on MGF, Emaar's former partner. India Ratings wrote on 12 August 2026 of "material progress" towards a settlement that would withdraw all litigation and leave the Marbella zones, Zen Garden and Sector 26 with Emaar India; terms were not final. Management puts the development value of the land it could free in Sectors 26, 62 and 65 above ₹30,000 crore; that is company's own figure, quoted by India Ratings.

India Ratings' provisional figures show FY26 pre-sales down about 60%, to about ₹2,706 crore from about ₹6,778 crore. Emaar India's newest launch, Elara, is in Lucknow and not Gurugram, it has 194 three-bedroom flats from ₹2.15 crore and launched on 2 November 2026 (Business Standard).

Which Emaar commercial projects are in Gurugram?

Seventeen, and the most of them are finished. India Business Centre in Sector 61, once IT Colony or Commerce Park, is the only commercial launch of 2025, one tower of 297 units due by 30 September 2031. The newest commercial registration is Emaar Business District (EBD) Next 114, 8 SCO (shop-cum-office) units registered on 7 April 2026.

ProjectSectorStatusHRERA numberCompletion or certificate
India Business Centre61Launched58 of 2017Due 30 Sep 2031
EBD Next 114114RegisteredRC/REP/HARERA/GGM/1055/787/2026/27Due 31 Dec 2029
Plaza 62; EBD 83; EBD 65 NXT62; 83; 65Under constructionRC/REP/HARERA/GGM/887/619/2024/114; RC/REP/HARERA/GGM/777/509/2024/04; RC/REP/HARERA/GGM/751/483/2023/95Due 30 Sep 2029; 31 Dec 2028; 10 Aug 2027
EBD 99, EBD 99 NXT99Under constructionRC/REP/HARERA/GGM/524/256/2021/92; RC/REP/HARERA/GGM/525/257/2021/93Date of 17 Aug 2026 passed
EBD 75A, 89, 89 NXT, 114 NXT75A, 89, 114Ready2021 to 2023 numbersCCs Dec 2024 to Sep 2025
EBD 65, EBD 114, Colonnade, Capital Towers65, 114, 66, MG RoadReady2017 to 2021 numbersOCs 2019 to 2023
Palm Springs Plaza, Emerald Plaza54, 65ReadyNot in our recordsOC 2015 (Palm Springs Plaza)

At EBD 99 and EBD 99 NXT, the portal showed no extension, OC or CC by 6 November 2026, and neither is labelled lapsed.

What does the record show on Emaar's delivery in Gurgaon?

Older-township buyers keep winning delay-interest cases. On 2 July 2026 the Haryana Real Estate Appellate Tribunal held, in Emaar India Ltd v Poonam Goel and linked appeals, that a conveyance deed or possession does not end a buyer's delay-interest claim, and that no limitation period apply before HRERA. A Palm Gardens appeal was decided that day on the same terms.

Two more rulings in July. On 8 July the tribunal gave Gurgaon Greens allottees delay charges from 31 December 2018 to 19 September 2019, and on 24 July it dismissed Emaar's appeal against 10.85% delay interest for Palm Drive buyers. Our report on delay compensation after possession discuss about a similar High Court ruling.

Certificates for the old colonies have came in: completion certificates for Palm Gardens' 21.90-acre colony on 30 December 2025, Imperial Gardens on 18 September 2025, and Emerald Estate and Emerald Classic on 15 April 2026. No residential OC dated 2025 or 2026 appears in HRERA's lists for Emaar's 43 Gurugram registrations.

At Palm Heights the portal shows an OC for 198 flats and none for the remaining of the 297, which were due by 27 February 2024. At Urban Oasis, HRERA shows 30 September 2028 for Phases 1 and 2 and 30 September 2029 for Phase 4, but Emaar's own 2026 filing gives Phases 1 and 2 a likely completion of 30 September 2029 too. At Marbella, Phase 1 allottees objected to layout changes in July 2026, and HRERA left them free to seek compensation.

What do Emaar projects in Gurgaon cost, and what does stamp duty add?

Emaar don't publish prices; its pages show prices on request, and we hold no Property Nivesh asking estimate for its projects. Below are totals reported from the CEO's statements at launch, not per sq ft rates or today's prices.

ProjectStatusReported price per homeSource and date
Amaris, Sector 62Under construction₹3.5 crore to over ₹6 croreBusiness Standard, 15 Nov 2024
Urban Ascent, Sector 112Launched₹2.5 crore to ₹6 crorePTI via Business Standard, 26 Jan 2025
Emaar Serenity Hills, Sector 86Launched₹3 crore to ₹5.7 croreConstruction World, 17 Nov 2025
Urban Oasis, Phases 1 and 2Under construction₹1,723 crore for all 424 flats (sales value)PTI via Business Standard, 17 Dec 2023

Haryana charges 7% stamp duty, about 5% for women, and a 1% registration fee capped at ₹50,000. As an illustration on Serenity Hills' lowest reported ₹3 crore, duty is ₹21 lakh at 7% or ₹15 lakh at 5%, and the registration fee stops on ₹50,000. Try your own price on our stamp duty calculator.

Pages going round online put Serenity Hills at ₹16,000 to ₹18,000 per sq ft, with EOIs (expressions of interest) of ₹10 lakh for 3 BHK and ₹15 lakh for 4 BHK labelled indicative. These are claims only: section 3(1) of the RERA Act bars booking before registration, and this is very much important for the later Serenity Hills phases, which are not registered.

Is Emaar India the same company as Emaar Properties of Dubai?

No. Emaar India is the Indian company behind these projects, and its parent, Emaar Properties of Dubai, holds 77.01% via two subsidiaries. It began in February 2005 as Emaar MGF Land, a venture with Shravan Gupta's MGF, and became Emaar India on 7 October 2020 after the split.

Under both names search HRERA, as older projects are mostly in Emaar MGF Land Ltd's name. Many newer ones, the land is licensed to other firms, such as Pyramid Infratech Pvt Ltd and Gallium Propbuild Pvt Ltd at Serenity Hills, so match the promoter and licensee on your agreement to the record.

What to check before you book with Emaar

  • On the HRERA Gurugram site, check that the number, project name, phase and promoter all agree, since marketing pages can show a wrong number.
  • Take the completion date from your agreement, not from a brochure, as a brochure date is only a brochure date.
  • Pay nothing for an unregistered phase. HRERA Gurugram warned buyers on 14 August 2026 against pre-launch schemes and booking offers in unregistered projects.
  • For a ready flat, ask the OC covering your tower.
  • On a resale flat in an older township, ask whether delay interest was claimed or paid.
  • Check if your phase's land falls in the 225.445 acres the Enforcement Directorate attached in 2024.

Our RERA checklist for 2026 goes step by step, the home loan EMI calculator does the loan sums, and Gurgaon property rates shows asking prices by sector.

Questions

Frequently Asked Questions

Which Emaar projects in Gurgaon are new launches? +

Emaar's housing launches in Gurugram since 2025 are Urban Ascent in Sector 112, launched in January 2025 with 816 flats, and Serenity Hills in Sector 86, launched in November 2025 with 997 flats. In 2026 HRERA registered two Marbella plot phases in Sector 66, Marbella Terraces and Marbella Phase 7, but Emaar has launched neither, and no dated launch is published for 2027.

Is Emaar Serenity Hills registered with HRERA, and when is completion? +

Yes. Serenity Hills has two HRERA Gurugram registrations dated 16 October 2025: RC/REP/HARERA/GGM/993/725/2025/96 for Phase 1, with 581 flats, and RC/REP/HARERA/GGM/994/726/2025/97 for Phase 2, with 416 flats. HRERA gives completion as 30 September 2032 for both phases, while press reports at launch mentioned June 2030, so take the date written in your agreement.

Is Emaar Urban Oasis ready to move in? +

No. Urban Oasis in Sectors 62 and 65 is under construction, and the HRERA portal shows no OC for it. HRERA gives completion as 30 September 2028 for Phases 1 and 2 and 30 September 2029 for Phase 4, and Emaar's own 2026 filing gives Phases 1 and 2 a likely completion of 30 September 2029. PTI reported that all 424 Phase 1 and 2 flats sold in 2023.

What is the price of Emaar's new flats in Gurgaon? +

Emaar publishes no price, and its pages show prices on request. The ranges reported from the CEO at launch were ₹3.5 crore to over ₹6 crore at Amaris (Business Standard, November 2024), ₹2.5 crore to ₹6 crore at Urban Ascent (PTI, January 2025) and ₹3 crore to ₹5.7 crore at Serenity Hills (Construction World, November 2025). Haryana adds 7% stamp duty.

Can I buy a plot in Emaar Marbella Terraces? +

Not through a launch so far. Marbella Terraces in Sector 66 was registered with HRERA on 25 June 2026 as RC/REP/HARERA/GGM/1068/800/2026/40, for 247 plots, but we found no launch announcement. Emaar's CEO told HRERA by affidavit that no plot had been advertised, booked or sold before registration, so look for Emaar's own launch and price list and check the HRERA record before paying anything.

Is Emaar India the same company as Emaar Properties? +

No. Emaar India, formerly Emaar MGF Land, is the Indian company that registers and develops the Gurugram projects. Emaar Properties, listed in Dubai, is its parent and holds 77.01% through two subsidiaries. Older HRERA registrations carry the Emaar MGF Land name and newer ones Emaar India Limited, so search the register under both names.

Has Emaar lost delay-interest cases in Gurgaon? +

Yes, several in 2026. On 2 July 2026 the Haryana Real Estate Appellate Tribunal held that a conveyance deed does not end a buyer's delay-interest claim, and it decided a Palm Gardens appeal on those terms. On 8 July it gave Gurgaon Greens buyers delay charges, and on 24 July it upheld 10.85% delay interest for Palm Drive buyers.

Sources

  1. HRERA Gurugram registered projects list, read on the portal, 6 November 2026
  2. Property Nivesh copy of the HRERA Gurugram register, to 14 September 2026
  3. HRERA Gurugram registration certificates and Form REP-I for Urban Ascent (8 January 2025), The 88 (4 March 2024), Amaris (14 November 2024), Urban Oasis Phases 1 and 2 (7 August 2023) and Phase 4 (22 November 2024), Serenity Hills Phases 1 and 2 (16 October 2025), Marbella Terraces (25 June 2026) and Marbella Phase 7 (5 August 2026)
  4. HRERA Gurugram, Form REP-I Part G declarations by Emaar India in the Serenity Hills (September 2025), Marbella Terraces (24 April 2026) and Marbella Phase 7 (30 April 2026) applications
  5. HRERA Gurugram project proceedings: Urban Ascent (8 January 2025), Serenity Hills Phase 1 (13 October 2025), Marbella Terraces (25 May and 9 June 2026), Marbella Phase 7 (6 July 2026)
  6. HRERA Gurugram OC, CC and corrigendum lists for Emaar registrations, including DTCP Haryana completion certificates for Palm Gardens (30 December 2025) and Imperial Gardens (18 September 2025)
  7. Haryana Real Estate Appellate Tribunal: Appeal 946 of 2024, Emaar India Ltd v Poonam Goel (2 July 2026); Appeal 432 of 2024 (2 July 2026); Appeal 650 of 2024 (8 July 2026); Appeal 1584 of 2025 (24 July 2026)
  8. Business Standard (PTI), Emaar India eyes Rs 900 crore luxury housing project in Gurugram, 17 December 2023
  9. Business Standard, Emaar India unveils Amaris, 15 November 2024
  10. Business Standard (PTI), Emaar India to invest Rs 1,600 cr on new housing project in Gurugram, 26 January 2025
  11. The Tribune, Emaar to invest Rs 1,600 crore in Gurugram luxury housing, 12 November 2025
  12. Construction World, Emaar India to invest Rs 16 billion in Gurugram project, 17 November 2025
  13. India Ratings and Research, rating action on Emaar India, 12 August 2026
  14. Business Standard, Emaar Properties rules out stake sale in India, 19 September 2025
  15. Business Standard, Emaar launches 194 luxury flats in Lucknow, 3 November 2026
  16. HRERA Gurugram public advisory on unregistered projects, 14 August 2026
  17. The Real Estate (Regulation and Development) Act, 2016, section 3(1)
  18. Emaar India project pages for Urban Ascent, Amaris and Serenity Hills, read 2026
  19. Haryana stamp duty and registration fee rates, Property Nivesh state cost table, 2026
  20. Property Nivesh developer profile of Emaar India, checked October 2026
A happy family in their new home with the money they got back

Brokerage back offer

Book your home with us and get the brokerage back*

Builders pay a brokerage to whoever brings them a buyer. Book through Property Nivesh and we give it back to you.

*Brokerage is part of the discussion with our advisor.

Unbiased advice. Your data is never sold to builders or brokers.