Dwarka Expressway M3M Projects: Sectors, HRERA, Prices, Status 2026

M3M has 11 HRERA registrations on Dwarka Expressway, all in Sectors 111, 113 and 114, plus the older Woodshire in Sector 107 with a 2017 OC. Homes run from ₹2.75 crore asked in listings for M3M Capital to M3M's own ₹15 crore entry price for Elie Saab, with RERA dates from December 2026 to February 2032.

By Preeti Pandey · Edited by Rakesh Mahajan · · 13 min read

Illustration of tall residential towers rising beside an elevated expressway in Gurugram Illustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show any project named in this post.

Which M3M projects are on Dwarka Expressway?

M3M has 11 HRERA registrations in the Dwarka Expressway sectors, all in Sectors 111, 113 and 114. Seven are homes or mixed towers, such as M3M Crown, M3M Capital, M3M Mansion and the branded M3M Residences by Elie Saab. The other four are commercial. The older M3M Woodshire in Sector 107 is complete, with OCs from 2017.

HRERA, the Haryana Real Estate Regulatory Authority under the RERA Act, keep the Gurugram register, used here as of 27 November 2026. An OC, or occupation certificate, is the permission to move in from DTCP, Haryana's town planning department.

Most of the homes sit in SCDA (Smart City Delhi Airport), M3M's own name for its block in Sectors 111 and 113. M3M Capital Walk, the shop strip, has no registration of its own, its shops sit inside the three Capital phases. M3M Jacob & Co. Residences, announced for Sector 111 on 18 November 2026, is not registered yet.

M3M Soulitude in Sector 89 and M3M 84 Market in Sector 84 are near the expressway, not on it. Antalya Hills and Golf Hills is in Sector 79 on SPR. Our map of projects on Dwarka Expressway covers every builder, and the M3M developer page lists the rest.

M3M Dwarka Expressway projects: HRERA number, status, price and possession

M3M has put out prices only for Elie Saab and Jacob & Co. The other figures are asking prices in listings, and a listing label like 3 BHK don't match M3M's own 3.5 BHK.

ProjectSectorType and sizeStatusHRERA numberPrice (whose figure, when)RERA completion date
M3M Crown Phase 11111,332 flats, 11 towersUnder constructionRC/REP/HARERA/GGM/687/419/2023/31₹3.41 to 5.53 crore, listings, Oct 202631 Jan 2028
M3M Residences by Elie Saab111296 flats, 3 towersUnder constructionRC/REP/HARERA/GGM/992/724/2025/95From about ₹15 crore, M3M, Jan 202629 Feb 2032
M3M Jacob & Co. Residences111120 homesAnnounced, not registeredNoneFrom ₹26 crore, M3M, Nov 2026Not published
M3M Capital Phase 1113750 flats and shops, 5 towersUnder construction, extendedRC/REP/HARERA/GGM/531/263/2022/06₹2.75 to 3.5 crore, listings, Oct 202629 Jun 2027
M3M Capital Phase 21131,760 flats and shops, 6 towersUnder constructionRC/REP/HARERA/GGM/612/344/2022/87Not published31 Dec 2026
M3M Capital Phase 3113328 flats and shops, 2 towersUnder constructionRC/REP/HARERA/GGM/825/557/2024/52Not published29 Feb 2028
M3M Mansion113968 flats and penthouses, 8 towersUnder constructionRC/REP/HARERA/GGM/802/534/2024/29₹3.85 to 15.73 crore, listings, Oct 202631 Mar 2030
M3M St. Andrews at SCDA113244 golf suites, 2 towersUnder constructionRC/REP/HARERA/GGM/916/648/2025/19Not published28 Feb 2031
M3M Capital Financial Centre113165 offices and shopsNew launchRC/REP/HARERA/GGM/1077/809/2026/49Not published30 Jun 2033
M3M 113 Market113105 SCO plotsCC 8 Nov 2023RC/REP/HARERA/GGM/365/97/2019/59Not published30 Apr 2023
M3M 114 Market11473 SCO plotsCC 19 Nov 2024RC/REP/HARERA/GGM/585/317/2022/60₹3.03 to 3.19 crore, listings, Oct 202631 Aug 2024
M3M Xpressway 11411444 SCO plotsCC 27 Aug 2025RC/REP/HARERA/GGM/718/450/2023/62₹3.02 to 5.04 crore, listings, Oct 202630 Apr 2025
M3M Woodshire107FlatsOCs of 2017Not registered₹1.34 to 3.54 crore, resale listings, Oct 2026Delivered

HRERA's Order 9/1-2026 of 11 August 2026 adds four months to projects registered by 31 July 2026 and due on or after 28 February 2026. The register still shows old dates.

Which M3M group companies are the promoters on HRERA?

None of these projects is registered under M3M India. Each sits under a group company, whose name is on the HRERA certificate.

Illustration of a high-floor living room with a view of an expressway skylineIllustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show any project named in this post.
Company on the HRERA recordM3M projects on Dwarka Expressway
Metro Education & Welfare Pvt Ltd (M3M calls it a wholly owned subsidiary)Crown Phase 1 and Residences by Elie Saab, Sector 111
Union Buildmart Pvt Ltd (collaborator; licences held by Vibrant Infratech and Targe Buildcon)Capital Phases 1 to 3, Mansion, St. Andrews and Capital Financial Centre, Sector 113
Lekh Buildtech Pvt Ltd113 Market, Sector 113
Golden Gate Propbuild Pvt Ltd114 Market, Sector 114
Generous Realtors Pvt LtdXpressway 114, Sector 114
Cogent Realtors Pvt Ltd (licensee, licence 33 of 2012)Woodshire, Sector 107

HRERA's judgements list is kept by company too. A copy saved on 6 November 2026 shows 10 decisions against Metro Education & Welfare from 2024 to 2026, 9 of them on complaints. It shows 5 against Union Buildmart. The list doesn't say which project each one concern. On the register, Crown has 1 monitoring case, now disposed, while Capital Phase 1, Phase 2 and Mansion has 1 each, still pending.

How many units are booked in M3M Crown, Capital and Mansion?

The clearest numbers come from M3M's own companies. In HRERA's Form REP-I, a promoter seeking a new registration lists its projects of the last five years and their bookings. The forms of 27 May and 4 June 2026 gives these counts.

ProjectSectorUnits bookedTotal unitsPromoter filing
M3M Crown Phase 11111,2841,3324 Jun 2026
M3M Residences by Elie Saab111182964 Jun 2026 (revised form)
M3M Capital Phase 111373075027 May 2026
M3M Capital Phase 21131,6811,76027 May 2026
M3M Capital Phase 311330132827 May 2026
M3M Mansion11385396827 May 2026
M3M St. Andrews at SCDA11313524427 May 2026

They're the promoter's declarations, not an audit. Still, Crown and the three Capital phases have few fresh units left with M3M, so a buyer there today is more likely to meet a resale seller. Listings in October 2026 showed 174 resale units in Crown and 269 across Capital. Elie Saab is the reverse, with most of its stock that still is with M3M.

M3M Crown and Elie Saab in Sector 111: price and RERA possession

M3M Crown was registered on 2 February 2023, with a RERA date of 31 January 2028. It has 11 towers and 1,332 flats on 11.6023 acres. M3M label the homes 3.5 and 4.5 BHK and publishes no sizes and no launch price.

Listings in October 2026 quoted 3 BHK units of 1,555 to 2,050 sq ft super area at ₹3.41 crore to ₹4.49 crore. The 4 BHK units, 2,270 to 2,525 sq ft, were quoted at ₹4.97 crore to ₹5.53 crore. Super area adds a share of lobbies and common space to the carpet area, the usable floor inside the flat.

Crown's DTCP licence, 213 of 2022, is valid only to 26 December 2027, about a month before the RERA date, so it need renewing. No OC is on HRERA yet.

M3M Residences by Elie Saab is the branded tower in what M3M calls its Billionaires' Block. HRERA's addendum of 3 July 2026 cut it from 336 homes to 296, in three towers. Six are three-bedroom flats of 179.4 sq m carpet, and 290 are four-bedroom flats of 204.11 to 228.54 sq m.

M3M's launch price in January 2026 was ₹37,000 per sq ft, basis not stated (Business Today, 13 January 2026). Homes start from about ₹15 crore. The register gives 29 February 2032 for completion, but M3M's own schedule show possession from February 2030.

Is M3M Jacob & Co. Residences in Sector 111 RERA registered?

No. M3M announced its second Jacob & Co. project on 18 November 2026, for the Billionaire's Block in Sector 111. As of 27 November it was not on the HRERA Gurugram register. No public notice of a HRERA application exists either.

Illustration of a pool and garden between residential towersIllustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show any project named in this post.

M3M's figures are 120 homes averaging about 7,300 sq ft, with prices from ₹26 crore. It expects an average of ₹40,000 per sq ft (Business Standard, 18 November 2026). The 170 acres in some reports is the whole enclave, not this project.

Under Section 3 of the RERA Act, a project cannot be booked or sold before registration. So there is no HRERA number, promoter or possession date to check yet. An EOI, meaning an expression of interest, have nothing on the register to attach to.

M3M Capital, Mansion and St. Andrews in Sector 113: RERA dates, extension and OC

Sector 113 holds the most of M3M's homes on the expressway. M3M Capital is planned in four phases on a mixed land use colony of 15.0625 acres. It comes under Haryana's TOD (transit oriented development) policy.

Capital Phase 1, with 750 units in 5 towers, was due on 30 June 2026. HRERA's Extension No. 10 of 2026, dated 23 April 2026, moved it to 29 June 2027. That was without prejudice to buyers' section 18 rights, because the promoter failed to prove reasonable circumstances for the delay. So the registration stay valid, and buyers keep their delay claim under that section.

Phase 2, with 763 flats and 997 commercial units, is due on 31 December 2026. Phase 3, with 268 flats and 60 shops, is due on 29 February 2028. Listings in October 2026 quoted Capital's 2 BHK, which M3M call 2.5 BHK, at ₹2.75 crore to ₹2.79 crore. Those are 1,310 to 1,330 sq ft of super area.

So far the only OC on M3M's Sector 113 registrations is DTCP's OC of 26 May 2026. It covers the colony's retail area and two basements, which is the Capital Walk shops. No M3M housing tower in Sector 113 has an OC on HRERA yet.

M3M Mansion has 961 homes and 7 shops in 8 towers plus an EWS (economically weaker section) block. It is due on 31 March 2030, but its licence runs only to 1 November 2028. Listings in October 2026 quoted its flats at ₹3.85 crore to ₹7.59 crore for 1,638 to 3,230 sq ft. Penthouses of 4,290 to 6,695 sq ft were quoted at ₹10.08 crore to ₹15.73 crore.

St. Andrews at SCDA was registered as Mansion Phase 2 and renamed on 1 May 2025. Its 244 golf suites and penthouses, 138.89 to 386.94 sq m carpet, are due on 28 February 2031, with no price published.

What has M3M completed on Dwarka Expressway? Woodshire and the plot markets

M3M Woodshire in Sector 107 is M3M's older, finished project on the expressway. HRERA orders names Cogent Realtors Pvt Ltd as licensee and record OCs dated 20 April 2017 and 24 July 2017. It is not on the HRERA register. Resale asking prices in listings, October 2026, ran from ₹1.34 crore for a 2 BHK to ₹3.54 crore for a 4 BHK.

The three commercial plot colonies are the M3M projects fully done on HRERA's record, each with a CC, or completion certificate. They are SCO colonies, SCO meaning shop-cum-office, where the plot owners builds on their own plots.

ProjectSectorPlotsRERA dateCC dateTiming
M3M 113 Market113105 plots of 48.169 to 365.218 sq m30 Apr 2023 (extended)8 Nov 2023About 6 months after the extended date
M3M 114 Market11473 plots31 Aug 202419 Nov 2024About 3 months after the date
M3M Xpressway 11411444 plots of 60 to 108.31 sq m30 Apr 202527 Aug 2025About 4 months after the date

Capital Walk's shop count depend on the paper. M3M's page says 876 shops on about 1 km of frontage, while the three Capital certificates hold 1,107 commercial units. Our guide to Dwarka Expressway commercial projects covers shops and offices.

How is M3M's SCDA cluster on Dwarka Expressway different from Golf Course Extension Road?

SCDA puts several kind of property under one M3M name. There are mid-size flats in Capital, bigger ones in Crown and Mansion, branded towers, a high street and an office tower. By M3M's own drive times it is 3 minutes from UER-II, 5 from Yashobhoomi (the India International Convention Centre) and 7 from IGI Airport.

Illustration of blank floor plans and a hard hat on a site office tableIllustrative image
Illustrative image: an AI-generated picture made for this guide. It does not show any project named in this post.

ANAROCK's September 2026 report names M3M India the largest supplier on the corridor from 2021 to H1 2026, with 6 projects and 4,280 units. ANAROCK's average quoted rate for Dwarka Expressway was ₹14,180 per sq ft in Q2 2026, on super built-up area. Asking prices in listings for September 2026 averaged ₹16,700 per sq ft in Sector 111 and ₹16,100 in Sector 113.

M3M's branded prices sits far above both, at ₹37,000 per sq ft for Elie Saab and an expected ₹40,000 for Jacob & Co. India Sotheby's International Realty and CRE Matrix put the corridor's sales of homes of ₹10 crore and above at ₹8,347 crore in 2025. That was up from ₹383 crore in 2024, counted by value.

This guide doesn't compare M3M's Golf Course Extension Road projects one by one; the M3M developer page lists them. At corridor level, Savills India found Dwarka Expressway rental values up 22% year on year in H1 2026, against 2% for Golf Course Extension Road and SPR. For SCDA, the open question is the metro. The Gurugram Metro spur under construction since September 2025 goes to Sector 101, not to SCDA. The proposed Rezangla Chowk to Dwarka Sector 21 line would stop at Sector 111. But it have only Haryana's approval of its DPR (detailed project report), from 19 October 2022.

What to check before you buy an M3M project on Dwarka Expressway

  1. Match the HRERA number, project name and promoter on your papers with the register. That is Union Buildmart for Capital, Mansion or St. Andrews, and Metro Education & Welfare for Crown or Elie Saab.
  2. In Capital Phase 1, ask which completion date your agreement carry, and keep a copy of Extension No. 10 of 2026.
  3. Ask which OC covers your unit. The OC of 26 May 2026 is for retail space and basements, not for any flat.
  4. For Crown and Mansion, ask how the DTCP licence will be renewed, since both run out before the RERA dates.
  5. Get the carpet area in sq m in writing. M3M's 2.5 and 3.5 BHK labels and the listings' 2 and 3 BHK describes the same flats.
  6. On a resale, confirm with M3M that the booking stands in the seller name and that the dues are clear.
  7. For Jacob & Co., ask for the HRERA number before any token or EOI.
  8. Add the four months of HRERA's August 2026 order to dates due on or after 28 February 2026. Ask M3M which date it works to.

Our stamp duty calculator adds the duty to your price. The Dwarka Expressway locality guide tracks corridor prices by year, and M3M new projects in Gurgaon covers its newest launches elsewhere.

Questions

Frequently Asked Questions

Which M3M projects are on Dwarka Expressway? +

M3M has 11 HRERA registrations in the Dwarka Expressway sectors. M3M Crown and M3M Residences by Elie Saab are in Sector 111. M3M Capital Phases 1 to 3, M3M Mansion, St. Andrews at SCDA, the Capital Financial Centre and 113 Market are in Sector 113, and 114 Market and Xpressway 114 are in Sector 114. M3M Woodshire in Sector 107 is an older, completed project.

Is M3M Crown sold out? +

Nearly. In its HRERA filing of 4 June 2026, the promoter company reported 1,284 of Crown's 1,332 apartments as booked. That is the promoter's own declaration, not an audit. Units still come up on resale: listings in October 2026 showed 174 resale units, and the top ten were quoted between ₹2.4 crore and ₹4.08 crore.

What is the possession date of M3M Capital Phase 1? +

HRERA's register gives 29 June 2027. The original date was 30 June 2026, and Extension No. 10 of 2026, dated 23 April 2026, moved it. HRERA granted the extension without prejudice to buyers' section 18 rights, because the promoter failed to prove reasonable circumstances for the delay. No residential tower in M3M Capital has an OC on HRERA yet.

Has any M3M project in Sector 113 got an OC? +

Only the retail part. DTCP issued an OC on 26 May 2026 for the Capital Walk retail area, from lower ground to second floor, and two basements of the M3M Capital colony. It is uploaded under all three Capital registrations. No M3M housing tower in Sector 113 has an OC on HRERA yet, while the 113 Market plot colony has had a completion certificate since 8 November 2023.

Is M3M Jacob & Co. Residences in Gurugram RERA registered? +

Not as of 27 November 2026. M3M announced the project for Sector 111 on 18 November 2026, with 120 homes of about 7,300 sq ft on average and prices from ₹26 crore. Under Section 3 of the RERA Act a project cannot be booked or sold before registration, so there is no HRERA number for a buyer to check yet.

What is the price of M3M Residences by Elie Saab? +

At the January 2026 launch M3M gave ₹37,000 per sq ft, basis not stated, with homes from about ₹15 crore (Business Today, 13 January 2026). HRERA lists 296 homes: 6 three-bedroom flats of 179.4 sq m carpet and 290 four-bedroom flats of 204.11 to 228.54 sq m. The RERA date is 29 February 2032, while M3M's own schedule shows possession from February 2030.

Which company is the promoter of M3M projects on HRERA? +

It depends on the project. Metro Education & Welfare Pvt Ltd, which M3M calls a wholly owned subsidiary, registered Crown and Elie Saab. Union Buildmart Pvt Ltd registered the Capital phases, Mansion, St. Andrews and the Capital Financial Centre. Lekh Buildtech, Golden Gate Propbuild and Generous Realtors registered the three commercial plot markets in Sectors 113 and 114.

Is M3M Woodshire on Dwarka Expressway? +

Yes. Woodshire is in Sector 107, one of the expressway sectors, and it is M3M's older, completed project there. HRERA records name Cogent Realtors Pvt Ltd as the licensee and show OCs from 2017. Woodshire is not on the HRERA register, and resale asking prices in listings, October 2026, ran from ₹1.34 crore to ₹3.54 crore.

Sources

  1. HRERA Gurugram, Registered Projects list, read 27 November 2026 (rows to 26 November 2026)
  2. HRERA Gurugram, registration certificates for M3M Crown Phase 1 (No. 31 of 2023), M3M Capital (No. 06 of 2022, 2 February 2022), M3M Capital Phase-2 (No. 87 of 2022), M3M Capital Phase-3 (No. 52 of 2024) and M3M Mansion (No. 29 of 2024), read 27 November 2026
  3. HRERA Gurugram, Form REP-I for M3M Crown Phase 1, M3M Capital (Phase 1), M3M Mansion, M3M Mansion Ph-2 (St. Andrews at SCDA), M3M 113 Market, M3M 114 Market and M3M Xpressway 114, read 27 November 2026
  4. HRERA Gurugram, revised Form REP-I for M3M Residences by Elie Saab, submitted 4 June 2026, and Form REP-I for M3M Capital Financial Centre, submitted 27 May 2026 (Part G booking lists)
  5. HRERA Gurugram, Extension of Registration No. 10 of 2026 dated 23 April 2026, M3M Capital Phase-1
  6. HRERA Gurugram, addendum to registration certificate GGM/992/724/2025/95 (revision in building plans), 3 July 2026
  7. HRERA Gurugram, corrigendum and OC/CC records for M3M Capital, Capital Phase-2 and Phase-3, Mansion Ph-2, Elie Saab, 113 Market, 114 Market and Xpressway 114, read 27 November 2026
  8. DTCP Haryana, Occupation Certificate memo dated 26 May 2026 for the retail area and basements of the Sector 113 colony, uploaded on HRERA
  9. HRERA Gurugram, Order No. 9/1-2026 dated 11 August 2026 (automatic four-month extension of registrations)
  10. HRERA Gurugram, order in Complaint No. 1586 of 2019 (M3M Woodshire), decided 18 December 2020, and proceedings in CR/5654/2022
  11. HRERA Gurugram, monitoring cases shown on the Registered Projects list, and the Ruling and Judgements list (copy saved 6 November 2026)
  12. M3M India, project pages for M3M Crown, M3M Capital, M3M Capital Walk, M3M Mansion and M3M Residences by Elie Saab (construction schedule updated 1 September 2026), read November 2026
  13. Business Today, 'M3M eyes Rs 8,300 crore from Elie Saab-branded residences in Gurugram, Noida', 13 January 2026
  14. Business Standard, 'Rs 26 cr onwards: M3M, Jacob & Co. launch 2nd housing project in Gurugram', 18 November 2026, and Construction World, 18 November 2026
  15. Business Standard, 'M3M India to invest Rs 600 crore to build commercial project in Gurugram', 30 July 2026
  16. Business Standard (ANI/NewsVoir press release), M3M Dwarka Expressway investment and Capital Walk launch, 22 October 2022
  17. Listing portal project pages for M3M Crown, M3M Capital, M3M Mansion, M3M Woodshire, M3M 114 Market and M3M Xpressway 114, last updated October 2026, and sector asking averages for September 2026 (asking prices, resale counts and sector rents; portal not named)
  18. HRERA Gurugram, orders in complaints on M3M Woodshire recording OCs of 20 April 2017 and 24 July 2017
  19. ANAROCK, Dwarka Expressway report, September 2026, and ANAROCK quarterly average quoted rate, Q2 2026
  20. India Sotheby's International Realty and CRE Matrix, sales of homes of Rs 10 crore and above, 2024 and 2025 (Business Today, 8 November 2026)
  21. Savills India, Gurugram residential report, H1 2026 (rental value change year on year)
  22. Haryana Government press releases on the Rezangla Chowk to Dwarka Sector 21 metro (DPR approval 19 October 2022; future plans, September 2025) and Gurugram Metro Phase 1 progress reports, 2025 and 2026

Mentioned here

Projects in this analysis

Chat with Us +91 79824 13588
A man reading about property on his phone at home

Free advice

Have a question before you buy?

Get straight answers from our advisor on projects, prices, home loans and paperwork. Free, with no obligation.

Unbiased advice. Your data is never sold to builders or brokers.

Prefer WhatsApp? Chat with Us: +91 79824 13588