Anant Raj Estate Phase V, Sector 63A Gurgaon
Anant Raj Estate Phase V launch date and possession timeline, Sector 63A Gurgaon
Anant Raj Estate Phase V in Sector 63A Gurgaon has no launch date as of 23 November 2026. Anant Raj's investor presentation of 28 October 2026 says approvals for the phase's 9.11875 acres are expected in Q4 FY27, which is January to March 2027. No possession date exists either, because the phase isn't registered with HRERA, Haryana's real estate regulator.
That approval target has already slipped twice in 2026. This page sets out the dated record so far, what must happen between an approval and a launch, how a RERA possession date differs from a developer's date, and what could push the calendar again.
- Launch date
- Not announced as of 23 November 2026
- Approval target
- Q4 FY27 (January to March 2027), per company
- HRERA status
- Not registered; no application on record
- Possession date
- None published
- Land area
- 9.11875 acres (company); 5.7625 acres (HRERA, 2025)
- Product type
- Not stated by the company
The short answer
- Anant Raj Estate Phase V had no launch date, EOI or HRERA registration as of 23 November 2026.
- Anant Raj said on 28 October 2026 that approvals for 9.11875 acres are expected in Q4 FY27, or January to March 2027.
- The approval target was Q4 FY2026 in January 2026 and Q2 FY27 in May 2026, so it has slipped twice.
- No possession date exists because neither a registration certificate nor an agreement for sale has been issued for the phase.
- Phase IV, the preceding plotted phase, was registered on 17 October 2025 with validity to 31 December 2030.
- HRERA's 2025 project report shows Phase V as 5.7625 acres, which conflicts with the company's figure of 9.11875 acres.
When will Anant Raj Estate Phase V launch?
Nobody has published a launch date. The only dated statement is Anant Raj's line of 28 October 2026 that approvals for Phase V are expected in Q4 FY27. An approval is not a launch. A sale can only open after HRERA registers the phase, and no application for it was on record up to 23 November 2026.
Q4 FY27 is the January to March 2027 quarter of the financial year ending 31 March 2027. The company gave it as a target for receiving approvals and did not say which approvals it meant. No DTCP licence is on record for the land. DTCP is Haryana's town planning department, which licenses a colony before RERA comes into play.
There's a second unknown. The company has not said whether Phase V will be plots, independent floors, villas or apartments. Without a product type there's no layout, unit count or price to hang a launch on. The overview sums up what is known, and the RERA page tracks the registration status.
What has happened so far, in order?
Phase V sits at the end of a long chain. The township's main licence dates from 28 December 2011, the land HRERA linked to Phase V was licensed on 18 October 2023, and Phase IV was registered on 17 October 2025. Phase V itself has only company statements, the latest from 28 October 2026.
| Date | Event | Where it is recorded |
|---|---|---|
| 28 December 2011 | DTCP licence 119 of 2011 for 100.262 acres of the plotted colony | HRERA registration certificate 106 of 2025 |
| 2012 and 2013 | Plots sold in pockets A and B (2012); Estate Villas launched (2013) | Anant Raj company timeline |
| 5 May 2014 | Part completion granted for 65.1125 acres | HRERA Form REP-I, 2022 |
| 2016 | First villa handed over | Anant Raj company timeline |
| 28 August 2017 | 43.012 acres registered as RERA 142 of 2017 | HRERA Gurugram |
| September 2021 | 2.08125 acres registered as RERA 58 of 2021 | HRERA Gurugram |
| 18 October 2023 | Licence 211 of 2023 for 11.8375 acres | HRERA registration certificate 106 of 2025 |
| 2025 | Project report lists Phase V as 5.7625 acres, 'balance area to be applied later' | HRERA project report |
| 11 August 2025 | First Phase IV application returned for want of an approved phasing plan | HRERA hearing brief |
| 17 October 2025 | Phase IV (6.075 acres, 62 units) registered as 106 of 2025, valid to 31 December 2030 | HRERA registration certificate |
| 22 January 2026 | Company expects Phase V approvals in Q4 FY2026 | Anant Raj investor presentation |
| 11 May 2026 | Target restated as Q2 FY27 | Anant Raj investor presentation |
| 10 August 2026 | 2.25 acres of unregistered licence 211 land moved into The Estate One | HRERA order |
| 20 August 2026 | The Estate One registered as RERA 56 of 2026 | HRERA; company stock exchange filing |
| 28 October 2026 | Target restated as Q4 FY27 for 'additional 9.11875 acres' | Anant Raj investor presentation |
| 23 November 2026 | No HRERA registration, application or public notice for Phase V | Property Nivesh check of HRERA records |
Read the table with one caution. HRERA's 2025 project report and the company describe different areas for Phase V, 5.7625 acres against 9.11875 acres. Which parcels make up the larger figure isn't public. The master plan page explains how the township's licences fit together.
Illustrative image How many times has the Phase V approval date moved?
Twice in 2026. In January the company expected approvals in Q4 FY2026. By May, and in the Annual Report 2025-26, the target was Q2 FY27. The 28 October 2026 presentation moved it to Q4 FY27. That's a shift of four quarters, about a year, between the first target and the current one.
| Company document | Date | Approval target | Calendar months |
|---|---|---|---|
| Investor presentation Q3 FY26 | 22 January 2026 | Q4 FY2026 | January to March 2026 |
| Investor presentation Q4 FY26; Annual Report 2025-26 | 11 May 2026 (presentation) | Q2 FY27 | July to September 2026 |
| Investor presentation Q2 FY27 | 28 October 2026 | Q4 FY27 | January to March 2027 |
The company hasn't explained the slips in any published document. The transcript of its October 2026 earnings call wasn't on its site, so there is no management commentary beyond the single presentation line. Treat the current quarter as a target with a history of moving.
What is the possession date of Anant Raj Estate Phase V?
There isn't one. A possession date needs either a RERA registration, which carries a completion date the promoter has committed to, or an agreement for sale that names a handover date. Phase V has neither. Any possession year you hear for it today has no document behind it.
RERA date versus developer date
RERA is the law that makes a developer register a project before selling it, and HRERA Gurugram is the authority that applies it here. Each registration certificate carries a validity date. That is the regulator's date: the promoter has to finish by then or go back for an extension.
The developer date is the handover date that appears in sales talk, a brochure or the agreement. The written due date matters most. In Complaint 4003 of 2021, HRERA took 16 July 2016 as the due date for an Anant Raj Estate plot and ordered interest for each month of delay from that day.
| Registration | Registered on | First validity date | What happened later |
|---|---|---|---|
| 142 of 2017 (43.012 acres, plots) | 28 August 2017 | 27 August 2022 | Extended to 27 February 2023, then 27 February 2024; continued to 27 February 2026 |
| 58 of 2021 (2.08125 acres, plots) | September 2021 | 31 March 2024 | Extended to 31 March 2025; project report says continued to 31 March 2026 |
| 106 of 2025 (Phase IV, 6.075 acres) | 17 October 2025 | 31 December 2030 | No change on record |
| 56 of 2026 (The Estate One) | 20 August 2026 | Validity date not available | Not applicable |
| Phase V | Not registered | None | None |
Two things stand out. Phase IV got a little over five years between registration and its validity date. Older registrations in the same township needed more than one extension. Neither fact tells you what Phase V's date will be. The reviews page covers the delivery record and complaints in detail.
What are the next milestones before Phase V can launch?
Going by how Phase IV moved through HRERA, four things have to appear on record in order: the approvals the company is waiting for, an application to HRERA, a public notice of that application, and a registration certificate. None of the four had shown up for Phase V by 23 November 2026.
- Approvals for the land. The company expects these in Q4 FY27. Watch for a DTCP licence or approved layout that names the Phase V area.
- An HRERA application. This should show the product type, unit count, land area and a proposed completion date for the first time.
- A public notice. For Phase IV, HRERA issued one on 1 July 2025 about the registration application.
- The registration certificate. Phase IV's came on 17 October 2025, about three and a half months after its notice.
- Launch documents. A brochure, price list, payment plan and draft agreement for sale that match what was filed with HRERA.
- Construction and handover. Progress is then measured against the registered date, ending with completion or an occupancy certificate (OC), the sign-off that a building can be lived in.
Phase IV's path is a guide to sequence, not to speed. Its first application was returned on 11 August 2025 because there was no approved phasing plan. Objections to registration were also received, and the promoter replied that they were unrelated to that land. The refiled application is the one that was registered.
Illustrative image What could change the dates?
Mostly paperwork. The approval target has moved twice, the land area differs between the company and HRERA, the product type is undeclared, and two township licences had validity dates in 2026 with no renewal on record. Any of these could stretch the gap between an approval and a launch.
- Approval slippage: Q4 FY2026 first, then Q2 FY27, now Q4 FY27.
- Land area: the company says 9.11875 acres. HRERA's 2025 report shows 5.7625 acres, and 2.25 acres of that licence's unregistered land later went to The Estate One, which would leave 3.5125 acres of that balance.
- Phasing plan: Phase IV's first application was returned for lacking an approved one.
- Licence validity: licence 71 of 2014 ran to 28 July 2026 and licence 104 of 2019 to 6 September 2026. Renewals are not on record.
- Company pipeline: a third group housing parcel of 6.38 acres has its own licence expected in Q3 FY27.
Road and metro projects nearby run on their own uncertain calendars. Business Today's report of 17 November 2026 gave no construction timeline for the proposed Greater SPR. These don't decide the launch, but they shape how buyers read it. The location page has the details.
Is there an EOI or new launch offer for Anant Raj Estate Phase V?
No. An EOI, or expression of interest, is a token some developers collect before launch to gauge demand. No EOI, booking window or application form for Phase V is on record as of 23 November 2026. The phase is not RERA registered, and registration has to come before a project is advertised or sold.
If someone offers a 'Phase V' allotment or priority number now, ask for the HRERA registration number first. There isn't one. Once a phase is registered, a promoter cannot take more than 10% of the cost before a registered agreement for sale. The booking page and payment plan page cover that stage.
Registered projects in the township are a different thing
Phase IV (106 of 2025) and The Estate One (56 of 2026) are separate registered projects inside Anant Raj Estate. Their dates, prices and terms do not transfer to Phase V. Township benchmarks are on the price page.
What to ask for once a launch date is announced
Ask for documents, not dates. A launch date means something only when it comes with an HRERA registration number, the certificate's validity date, and a draft agreement that states the handover date. Compare the three. If the sales date is earlier than the RERA date, find out which one the agreement carries.
- The HRERA registration certificate and its 'valid till' date.
- The approved layout showing which acres fall in Phase V.
- The product type and unit count as filed with HRERA.
- The possession clause in the draft agreement for sale.
- The payment plan, to see how instalments track construction stages.
This page will be updated when any milestone lands. Meanwhile, our list of new project launches, the Anant Raj developer page and the Gurgaon city guide give wider context. Short answers to common questions are on the FAQs page.
Questions people ask
When will Anant Raj Estate Phase V launch?
No launch date has been announced. Anant Raj's investor presentation of 28 October 2026 says approvals for the 9.11875 acres of Phase V are expected in Q4 FY27, meaning January to March 2027. After approvals, the phase still needs an HRERA registration before it can be sold. No application was on record as of 23 November 2026.
What is the possession date of Anant Raj Estate Phase V?
No possession date exists for Phase V. A possession date comes from an HRERA registration certificate or an agreement for sale, and the phase has neither. For context only, the earlier Phase IV was registered on 17 October 2025 with validity to 31 December 2030. That date belongs to Phase IV and says nothing binding about Phase V.
Is Anant Raj Estate Phase V RERA registered?
No. As of 23 November 2026 there is no HRERA registration, application or public notice for Phase V, and no DTCP licence for it is on record. Two other projects inside the township are registered, Phase IV and The Estate One, but those certificates cover different land and do not extend to Phase V.
Why has the Phase V approval date kept moving?
The company hasn't given a reason in the documents available. Its January 2026 presentation expected approvals in Q4 FY2026, the May 2026 presentation and the annual report said Q2 FY27, and the October 2026 presentation says Q4 FY27. The October earnings call transcript wasn't on the company's site, so no management explanation is on record.
Is an EOI open for Anant Raj Estate Phase V?
No EOI, booking window or application form for Phase V is on record as of 23 November 2026. The phase isn't registered with HRERA, and registration comes before any sale. Once a project is registered, the promoter cannot accept more than 10% of the cost before a registered agreement for sale. Ask for the registration number before paying anything.
Will Phase V be plots, floors or apartments?
The company hasn't said. It describes Anant Raj Estate only as a luxury residential development on Golf Course Extension Road. The township already mixes villas, plots, independent floors and group housing, and the preceding Phase IV was plotted, with 61 residential plots. The product type should first appear in the HRERA application, whenever it is filed.
How big is Anant Raj Estate Phase V?
Two figures exist. Company presentations and the Annual Report 2025-26 say an 'additional 9.11875 acres'. HRERA's 2025 project report lists Phase V as a 5.7625-acre balance under licence 211 of 2023, and 2.25 acres of that licence's unregistered land went into The Estate One in August 2026. The exact parcels aren't public.
What is the first sign that a Phase V launch is near?
Going by Phase IV, an HRERA public notice of the registration application. HRERA issued one for Phase IV on 1 July 2025 and the certificate followed on 17 October 2025, after an earlier application was returned. For Phase V, no such notice had appeared by 23 November 2026. Approvals for the land would come before that.
More on Anant Raj Estate Phase V
- Anant Raj Estate Phase V: overview What Anant Raj Estate Phase V is, who builds it, where it sits and its status today.
- Anant Raj Estate Phase V: price No official Phase V price yet: township benchmarks, their basis and the full Haryana buying cost.
- Anant Raj Estate Phase V: payment plan No Phase V payment plan is published yet; see the 10% RERA rule and a worked sample.
- Anant Raj Estate Phase V: location Where Phase V sits in Sector 63A, the roads and metro on record, and the distances sources state.
- Anant Raj Estate Phase V: rera No HRERA number yet for Phase V: what the register shows and how to check it.
- Anant Raj Estate Phase V: reviews Pros, cons, delivery record and HRERA orders behind Anant Raj Estate Phase V, with no invented ratings.
- Anant Raj Estate Phase V: brochure No Phase V brochure exists yet: what a real one must show and which documents bind.
- Anant Raj Estate Phase V: booking Booking is not open: the steps, the 10% rule, documents and refund checks for Phase V.
- Anant Raj Estate Phase V: floor plan No Phase V floor plans are published yet; see what is on record and how to read sizes.
- Anant Raj Estate Phase V: master plan Phase V land figures, township phasing and what the unpublished site plan must show.
- Anant Raj Estate Phase V: amenities Township club, pools and parks sorted by user, and why Phase V has no amenity list yet.
- Anant Raj Estate Phase V: highlights Ten sourced Phase V facts, split into regulator record, company claim and market quote.
- Anant Raj Estate Phase V: investment Area price benchmarks, buying costs and the real risks of Phase V, with no forecasts.
- Anant Raj Estate Phase V: faqs 28 buyer questions on Phase V answered: price, RERA status, possession, location and what isn't out yet.
Related on Property Nivesh
Talk to an advisor about Anant Raj Estate Phase V
Tell us what you are looking for in Anant Raj Estate Phase V. Our advisor calls you with what is confirmed so far and answers your questions on price, plans and paperwork.
✓
Request received
A senior property advisor will reach you within 4 working hours. No spam, no builder hand-offs — your details stay with our advisory desk only.
Sources
- Anant Raj Limited, Investor Presentation Q2 FY27, 28 October 2026
- Anant Raj Limited, Investor Presentation Q4 FY26, 11 May 2026
- Anant Raj Limited, Investor Presentation Q3 FY26, 22 January 2026
- Anant Raj Limited, Annual Report 2025-26, July 2026
- HRERA Gurugram, Project Report for the plotted colony Anant Raj Estate (phase-wise table), 2025
- HRERA Gurugram, Registration Certificate 106 of 2025 and hearing brief for Phase IV, October 2025
- HRERA Gurugram, Order in Complaint 4003 of 2021, 8 August 2023
- Business Today, report on Greater SPR and Gurugram developers, 17 November 2026
Property Nivesh is an independent property research and advisory site. This guide is not the website of Anant Raj and is not connected with the developer. Facts are as of 23 November 2026 and come from the sources listed on each page; prices quoted in the market are indicative. Pictures marked "Illustrative image" are AI-generated and do not show the project.