Does New Infrastructure Raise Property Prices? What Official Data Shows

Gurugram’s official valuation of flats in the Dwarka Expressway sectors rose 157% between FY2021-22 and FY2026-27, and new RERA projects there rose 44% after the road opened. Mumbai’s official rates show no such effect near new metro lines. Property Nivesh Research compared government records for 16 major projects.

Published
9 October 2026
Last updated
9 October 2026
Data period
FY2021-22 – FY2026-27
Datasets
4 official sources

By Property Nivesh Research Team · Reviewed by Rakesh Mahajan

Summary

People often say a new expressway, airport or metro line pushes up property prices nearby. We tested that claim with official records only: the rates state governments use to value property for stamp duty, the new projects registered with RERA, and the dates each project was approved, started and opened.

The clearest signal is the Dwarka Expressway in Gurugram. After the road opened on 11 March 2024, the government’s rate for flats in sectors 104 to 115 rose 67% in a single revision — the biggest single rise of any of the 57 flat lines in Gurugram’s lists. New projects registered in the sectors along the road also rose. But in Kadipur tehsil, whose list also prices expressway sectors, the corridor’s rate rose about as much as its neighbours’, so the road does not explain everything.

Around the new Jewar airport, new RERA projects in Gautam Buddha Nagar rose 84%. In Mumbai, the government raised flat rates by the same amount near new metro lines as elsewhere. Circle rates are not market prices, and none of this shows what homes actually sold for. It shows how official records moved.

Key findings

Each finding stands on its own and may be quoted with credit to Property Nivesh Research. Link one with its anchor (#finding-1, #finding-2 …).

  1. 1

    Gurugram’s collector rate for flats in sectors 104–115, along the Dwarka Expressway, rose from ₹3,000 per sq ft in FY2021-22 to ₹7,700 in FY2026-27, a rise of 157%. The rate for group housing in central Gurugram rose 131% over the same years.

  2. 2

    The expressway opened on 11 March 2024. Gurugram’s next list kept the sectors 104–115 rate at ₹4,200; the revision in force from 1 August 2025 raised it 67% to ₹7,000, against 38% for central Gurugram.

  3. 3

    From FY2024-25 to FY2026-27, sectors 104–115 had the largest rise (83%) of the 17 sector-group flat lines in Gurugram’s collector-rate lists. The median line rose 25%.

  4. 4

    The tehsil mattered as much as the road. The same revisions raised Gurugram-tehsil lines by 78% to 83% but Manesar lines by about 10%. In Kadipur, the expressway line (Sectors 99–110) rose 33%, close to the 30% median of Kadipur’s other lines.

  5. 5

    New RERA projects in Gurugram sectors 99–115 averaged 23 a year in 2024–2025, up from 16 a year in 2021–2023, a rise of 44%. Their share of all new projects in Gurugram district rose from 14% to 18%.

  6. 6

    In Gautam Buddha Nagar, where Noida International Airport stands, new RERA projects rose from an average of 31 a year in 2021–2023 to 57 a year in 2024–2025, a rise of 84%. The airport first opened on 28 March 2026.

  7. 7

    Mumbai’s ready reckoner shows no metro premium. From FY2022-23 to FY2026-27, the median flat rate rose 10% in suburbs named after Metro 2A and 7 stations, 10% near Metro 3 and 10% in the other suburbs. In the FY2025-26 revision, 61% of all sub-zones rose by exactly 10%.

  8. 8

    Of the 28 project sections in our data with both an official construction start and an opening, the median took 5.3 years to open. 11 of them had at least one official delay or revised target date; 20 more have started and not yet opened.

  9. 9

    The Dwarka Expressway (Haryana) took 5.3 years from construction start (29 November 2018) to opening, with 3 official revisions of its target. Noida International Airport took 4.3 years from its foundation stone (25 November 2021); Navi Mumbai International Airport opened 18.5 years after its first approval (July 2007).

  10. 10

    Where official records are missing — circle rates for Noida and Greater Noida, Ghaziabad and Meerut along the Delhi–Meerut RRTS, and Bengaluru’s Peripheral Ring Road — this report does not estimate an effect.

Key numbers

Rise in the flat collector rate, Dwarka Expressway sectors 104–115
157%
FY2021-22 to FY2026-27
Rise in the first revision after opening
67%
in force from 1 August 2025
Rise in new RERA projects a year, sectors 99–115
44%
2024–2025 against 2021–2023
Rise in new RERA projects a year, Gautam Buddha Nagar
84%
2024–2025 against 2021–2023
Rise in Mumbai flat rates near Metro 2A and 7
10%
median, FY2022-23 to FY2026-27 — the same as elsewhere
Construction start to opening
5.3 years
median of 28 project sections

What we measured, and what we did not

No public source publishes market prices for every locality in India over the last five years. So instead of guessing, we used three kinds of official record.

  • Government valuations. States set a minimum value for every area — called collector rates in Haryana and ready-reckoner rates in Maharashtra — to charge stamp duty. When a state raises them, it is saying it believes values there have risen.
  • New project supply. Every new housing project must register with the state RERA authority. A rise in registrations near a project shows developers moving in.
  • Official timelines. For 106 infrastructure projects in India we recorded 299 dated milestones from government and project-authority releases: approvals, foundation stones, construction starts, delays and openings.

These records lag the market and are not sale prices. They can show where official views and builders moved. They cannot show what any home sold for.

Dwarka Expressway: the clearest official signal

Gurugram’s collector-rate lists price flats in group housing by sector group. The line for sectors 104 to 115 — the sectors the Dwarka Expressway runs through — started from the lowest base of the three lines Gurugram tehsil has priced every year: ₹3,000 per sq ft in FY2021-22, against ₹5,000 for central Gurugram.

The road opened on 11 March 2024. The 2024 list left the corridor’s rate unchanged at ₹4,200. The revision in force from 1 August 2025 then raised it 67%, the biggest single rise of any of the 57 flat lines in Gurugram’s lists, and the list from 1 April 2026 took it to ₹7,700. Over five years the corridor’s rate rose 157%, against 131% for central Gurugram and 74% for the Housing Board colony.

Gurugram collector rates for group-housing flats, ₹ per sq ftThe three flat lines Gurugram tehsil has priced in every list since FY2021-22, plotted at the date each list took effect where it prints one (otherwise 1 April). The Dwarka Expressway (Haryana) opened on 11 March 2024; the 2024 list left sectors 104–115 unchanged, and the revision in force from 1 August 2025 was the first to raise them.
Gurugram collector rates for group-housing flats, ₹ per sq ftCollector rates for flats in three Gurugram group-housing lines, FY2021-22 to FY2026-27. ₹0₹2,000₹4,000₹6,000₹8,000₹10,000₹12,000FY2021-22FY2022-23FY2023-24FY2024-25FY2025-26FY2026-27Expressway opensSectors 104–115 (Dwarka Expressway), FY 2021-22: ₹3,000Sectors 104–115 (Dwarka Expressway), FY 2022-23: ₹3,500Sectors 104–115 (Dwarka Expressway), FY 2023-24: ₹4,200Sectors 104–115 (Dwarka Expressway), FY 2024-25: ₹4,200Sectors 104–115 (Dwarka Expressway), FY 2025-26: ₹7,000Sectors 104–115 (Dwarka Expressway), FY 2026-27: ₹7,700Sectors 1–43 group housing (central Gurugram), FY 2021-22: ₹5,000Sectors 1–43 group housing (central Gurugram), FY 2022-23: ₹5,500Sectors 1–43 group housing (central Gurugram), FY 2023-24: ₹6,500Sectors 1–43 group housing (central Gurugram), FY 2024-25: ₹6,500Sectors 1–43 group housing (central Gurugram), FY 2025-26: ₹9,000Sectors 1–43 group housing (central Gurugram), FY 2026-27: ₹11,550Housing Board colony, FY 2021-22: ₹3,800Housing Board colony, FY 2022-23: ₹4,000Housing Board colony, FY 2023-24: ₹4,800Housing Board colony, FY 2024-25: ₹4,800Housing Board colony, FY 2025-26: ₹6,000Housing Board colony, FY 2026-27: ₹6,600Sectors 104–115 (Dwarka Expressway)Sectors 1–43 group housing (central Gurugram)Housing Board colony Source: Property Nivesh Research · propertynivesh.in/research
Embed this chart

The tehsil matters as much as the road

The sectors along the expressway are split between revenue tehsils, and each tehsil has its own list. Looking at every sector-group line priced in both the FY2024-25 and FY2026-27 lists, the median rose 25%. Sectors 104–115 rose most, at 83%.

But the biggest differences were between tehsils, not between corridors. By tehsil, the median rise was Gurugram 81%, Wazirabad 38%, Kadipur 32%, Harsaru 27%, Badshahpur 21% and Manesar 10%. In Kadipur, the expressway line (Sectors 99–110) rose 33% — close to the 30% median for Kadipur’s other lines. Harsaru’s two lines rose 27%. So the official data shows a strong corridor effect in one list, not in all of them.

Change in Gurugram flat collector rates, FY2024-25 to FY2026-27Every sector-group line priced in both lists, in the tehsil list that prices it. Gold: lines for sectors 99–115, which the Dwarka Expressway runs through.
Change in Gurugram flat collector rates, FY2024-25 to FY2026-27Change in Gurugram flat collector rates, FY2024-25 to FY2026-27 0%20%40%60%80%100%Sectors 104–115 (Gurugram) Sectors 104–115 (Gurugram): 83% +83%Sectors 1, 2, 3, 3A, 4 + 19 more (Gurugram) Sectors 1, 2, 3, 3A, 4 + 19 more (Gurugram): 78% +78%Sectors 58, 59, 60, 61, 62 + 2 more (Wazirabad) Sectors 58, 59, 60, 61, 62 + 2 more (Wazirabad): 55% +55%Sectors 71, 72A, 73, 74, 75, 75A (Kadipur) Sectors 71, 72A, 73, 74, 75, 75A (Kadipur): 33% +33%Sectors 99–110 (Kadipur) Sectors 99–110 (Kadipur): 33% +33%Sectors 37C, 37D (Kadipur) Sectors 37C, 37D (Kadipur): 30% +30%Sectors 36A, 84, 88, 88A, 89, 89A (Harsaru) Sectors 36A, 84, 88, 88A, 89, 89A (Harsaru): 27% +27%Sectors 36A, 84, 88B, 89B, 90 + 8 more (Harsaru) Sectors 36A, 84, 88B, 89B, 90 + 8 more (Harsaru): 27% +27%Sectors 9, 9A, 9B, 10, 10A + 6 more (Kadipur) Sectors 9, 9A, 9B, 10, 10A + 6 more (Kadipur): 25% +25%Sectors 33, 38, 47, 48, 49, 50 (Badshahpur) Sectors 33, 38, 47, 48, 49, 50 (Badshahpur): 21% +21%Sectors 15, 27, 28, 30, 31 + 16 more (Wazirabad) Sectors 15, 27, 28, 30, 31 + 16 more (Wazirabad): 21% +21%Sectors 62, 65, 66, 69, 70 + 3 more (Badshahpur) Sectors 62, 65, 66, 69, 70 + 3 more (Badshahpur): 21% +21%Sectors 63, 63A, 64, 67, 67A + 4 more (Badshahpur) Sectors 63, 63A, 64, 67, 67A + 4 more (Badshahpur): 21% +21%Sector 90 (Manesar) Sector 90 (Manesar): 11% +11%Sector 36A (Manesar) Sector 36A (Manesar): 10% +10%Sectors 76, 77, 78, 80, 81 + 5 more (Manesar) Sectors 76, 77, 78, 80, 81 + 5 more (Manesar): 10% +10%Sectors 79, 85, 86, 87, 89 (Manesar) Sectors 79, 85, 86, 87, 89 (Manesar): 10% +10%Dwarka Expressway sectors (99–115)Other sector groups Source: Property Nivesh Research · propertynivesh.in/research
Embed this chart

More projects registered along the expressway

We placed each project registered with HRERA Gurugram in the sector named in its filed address. From 2021 to 2023, sectors 99–115 drew 16 new projects a year, 14% of the district’s total. In 2024–2025, after the road opened, they drew 23 a year, 18% of the total, while new projects across the whole district changed by +13%. The numbers are small, and a few large launches can move them.

New RERA projects in Gurugram: sectors 99–115 and the rest of the districtProjects registered with HRERA Gurugram each calendar year, placed by the sector in their filed address (complete years to 2025).
New RERA projects in Gurugram: sectors 99–115 and the rest of the districtNew RERA project registrations per year in Gurugram sectors 99–115 and elsewhere in Gurugram district. 020406080100120Sectors 99–115 (Dwarka Expressway), 2018: 1616Rest of Gurugram district, 2018: 47472018Sectors 99–115 (Dwarka Expressway), 2019: 2222Rest of Gurugram district, 2019: 56562019Sectors 99–115 (Dwarka Expressway), 2020: 66Rest of Gurugram district, 2020: 42422020Sectors 99–115 (Dwarka Expressway), 2021: 1515Rest of Gurugram district, 2021: 77772021Sectors 99–115 (Dwarka Expressway), 2022: 1717Rest of Gurugram district, 2022: 1141142022Sectors 99–115 (Dwarka Expressway), 2023: 1515Rest of Gurugram district, 2023: 1021022023Sectors 99–115 (Dwarka Expressway), 2024: 1919Rest of Gurugram district, 2024: 1051052024Sectors 99–115 (Dwarka Expressway), 2025: 2626Rest of Gurugram district, 2025: 1051052025Sectors 99–115 (Dwarka Expressway)Rest of Gurugram district Source: Property Nivesh Research · propertynivesh.in/research
Embed this chart

Jewar airport and Gautam Buddha Nagar

Noida International Airport at Jewar had its foundation stone laid on 25 November 2021 and first opened on 28 March 2026, after 3 official revisions or delays. UP RERA’s list shows new projects in Gautam Buddha Nagar — which covers Noida, Greater Noida and the Yamuna Expressway area — at 35, 28 and 29 in 2021, 2022 and 2023, then 51 in 2024 and 62 in 2025.

The rise lines up with the airport’s final years of construction, but registrations count projects, not homes, and the district has other drivers too. We do not yet hold Noida’s or YEIDA’s circle rates, so we cannot say how official valuations near the airport moved.

New RERA projects in Gautam Buddha Nagar (Noida, Greater Noida, Yamuna Expressway)Projects registered with UP RERA in the district each calendar year. Construction of Noida International Airport began in November 2021; it opened in 2026.
New RERA projects in Gautam Buddha Nagar (Noida, Greater Noida, Yamuna Expressway)New RERA project registrations per year in Gautam Buddha Nagar district, 2021–2025. 0102030405060702021: 353520212022: 282820222023: 292920232024: 515120242025: 62622025 Source: Property Nivesh Research · propertynivesh.in/research
Embed this chart

Mumbai: no metro premium in the ready reckoner

Mumbai opened Metro Lines 2A and 7 between April 2022 and January 2023, and Metro Line 3 from 5 October 2024. If official valuations reacted, sub-zones near stations should have risen more. They did not. Matching suburban villages to the stations named after them, the median flat rate rose 10% near Metro 2A and 7, 10% near Metro 3 and 10% in the other suburbs between FY2022-23 and FY2026-27. The island city rose 5%.

Maharashtra revises its rates in near-uniform steps: in FY2025-26, 61% of all sub-zones rose by exactly 10%. That makes the ready reckoner a poor tool for spotting local effects — a limit of the data, not proof that the metro had no effect on market prices.

Mumbai ready-reckoner rates for flats: median change at each revisionMedian change across sub-zones in each group. Suburban sub-zones are grouped by whether their revenue village carries the name of a Metro 2A / 7 or Metro 3 station.
Mumbai ready-reckoner rates for flats: median change at each revisionMedian change in Mumbai flat ready-reckoner rates by group and revision. 0%2%4%6%8%10%Metro 2A / 7 stations, 2022-23 → 2023-24: 0%0Metro 3 stations (suburbs), 2022-23 → 2023-24: 0%0Other suburban sub-zones, 2022-23 → 2023-24: 0%0Island city, 2022-23 → 2023-24: 0%02022-23 → 2023-24Metro 2A / 7 stations, 2023-24 → 2024-25: 0%0Metro 3 stations (suburbs), 2023-24 → 2024-25: 0%0Other suburban sub-zones, 2023-24 → 2024-25: 0%0Island city, 2023-24 → 2024-25: 0%02023-24 → 2024-25Metro 2A / 7 stations, 2024-25 → 2025-26: 10%10Metro 3 stations (suburbs), 2024-25 → 2025-26: 10%10Other suburban sub-zones, 2024-25 → 2025-26: 10%10Island city, 2024-25 → 2025-26: 5.2%52024-25 → 2025-26Metro 2A / 7 stations, 2025-26 → 2026-27: 0%0Metro 3 stations (suburbs), 2025-26 → 2026-27: 0%0Other suburban sub-zones, 2025-26 → 2026-27: 0%0Island city, 2025-26 → 2026-27: 0%02025-26 → 2026-27Metro 2A / 7 stationsMetro 3 stations (suburbs)Other suburban sub-zonesIsland city Source: Property Nivesh Research · propertynivesh.in/research
Embed this chart

How long big projects take

Official timelines are the part of the infrastructure story buyers can check before they buy. Across 28 project sections with a recorded construction start and opening, the median took 5.3 years; the longest was Navi Mumbai International Airport at 7.5 years. 11 of them had at least one official delay or revised target date.

The Delhi–Meerut RRTS opened its first section 4.4 years after construction began. The Sohna–Dausa stretch of the Delhi–Mumbai Expressway opened in 3.4 years. Atal Setu took 5.8 years from construction start to opening, but its first approval dates back to 4 February 2009. The Bengaluru Peripheral Ring Road is under construction.

From construction to opening: the projects we followEach bar runs from the official construction start (or first approval, where no start is recorded) to the first section opening; a dotted bar is still waiting. Red dots are official delay statements or revised target dates. The Yamuna Expressway (approved 2003, opened 2012) is in the table below.
From construction to opening: the projects we followTimelines of 15 infrastructure projects from official milestones. 20132015201720192021202320252027Noida International Airport (Jewar)Noida International Airport (Jewar) — Construction start: 2021-11-25Noida International Airport (Jewar) — Official delay: 2024-06-24Noida International Airport (Jewar) — Target date revised: 2025-01-03Noida International Airport (Jewar) — Target date revised: 2026-05-01Noida International Airport (Jewar) — First opening: 2026-03-28Dwarka Expressway (Haryana)Dwarka Expressway (Haryana) — Construction start: 2018-11-29Dwarka Expressway (Haryana) — Target date revised: 2021-03-04Dwarka Expressway (Haryana) — Target date revised: 2022-07-11Dwarka Expressway (Haryana) — Target date revised: 2023-05-18Dwarka Expressway (Haryana) — First opening: 2024-03-11Dwarka Expressway (Delhi)Dwarka Expressway (Delhi) — Construction start: 2019-10-17Dwarka Expressway (Delhi) — Target date revised: 2023-05-18Dwarka Expressway (Delhi) — Target date revised: 2025-03-13Dwarka Expressway (Delhi) — First opening: 2025-05-29Delhi–Mumbai ExpresswayDelhi–Mumbai Expressway — Construction start: 2018-12-10Delhi–Mumbai Expressway — Target date revised: 2021-09-16Delhi–Mumbai Expressway — Target date revised: 2022-11-01Delhi–Mumbai Expressway — Target date revised: 2023-04-01Delhi–Mumbai Expressway — Target date revised: 2024-07-31Delhi–Mumbai Expressway — First opening: 2023-02-12DME: Sohna – Dausa stretchDME: Sohna – Dausa stretch — Construction start: 2019-09-05DME: Sohna – Dausa stretch — First opening: 2023-02-12DME link to Jewar airportDelhi–Meerut RRTSDelhi–Meerut RRTS — Construction start: 2019-06-01Delhi–Meerut RRTS — First opening: 2023-10-21DMIC township, Greater NoidaDMIC township, Greater Noida — First opening: 2020-12-01Bengaluru Peripheral Ring RoadBengaluru Peripheral Ring Road — Target date revised: 2026-03-01Gurugram Metro (MCC – Cyber City)Gurugram Metro (MCC – Cyber City) — Construction start: 2025-09-05Gurugram Metro (MCC – Cyber City) — Target date revised: 2025-09-05Noida Metro Aqua LineNoida Metro Aqua Line — Construction start: 2015-08-05Noida Metro Aqua Line — First opening: 2019-01-26Mumbai Metro Line 3 (Aqua)Mumbai Metro Line 3 (Aqua) — Target date revised: 2025-05-09Mumbai Metro Line 3 (Aqua) — First opening: 2024-10-05Atal SetuAtal Setu — Construction start: 2018-03-23Atal Setu — First opening: 2024-01-13Navi Mumbai International AirportNavi Mumbai International Airport — Construction start: 2018-07-07Navi Mumbai International Airport — Target date revised: 2024-01-13Navi Mumbai International Airport — First opening: 2025-12-25Pune Metro Lines 1 and 2Pune Metro Lines 1 and 2 — Construction start: 2017-05-03Pune Metro Lines 1 and 2 — First opening: 2022-03-06Construction startOpened (first section)Official delay or revised date Source: Property Nivesh Research · propertynivesh.in/research
Embed this chart

How to read these findings

Official valuations move in revisions, often long after the market. A big jump in a circle rate usually means the government is catching up with prices that have already risen. A flat line can mean prices did not change, or that the state did not revise. New project registrations show where developers are building, which also depends on land, approvals and interest rates.

Use these records alongside, not instead of, current prices for the specific project, its RERA registration and the official status of any infrastructure it advertises. This report does not forecast prices or recommend buying or selling any property.

Data tables

Gurugram collector rates for group-housing flats by sector group, ₹ per sq ft As printed in each financial year’s list (— = line not in that year’s list). Lines are kept in the tehsil list that prices them: the same sector can fall in more than one tehsil.
Sector group (tehsil list)2021-222022-232023-242024-252025-262026-27Change 2024-25 → 2026-27
★ Sectors 104–115 (Gurugram)3,0003,5004,2004,2007,0007,700+83%
★ Sectors 99–110 (Kadipur)———4,5005,5006,000+33%
Sectors 33, 38, 47, 48, 49, 50 (Badshahpur)——7,1508,2509,10010,000+21%
Sectors 62, 65, 66, 69, 70 + 3 more (Badshahpur)——5,0005,7506,3006,950+21%
Sectors 63, 63A, 64, 67, 67A + 4 more (Badshahpur)——4,6005,3005,8006,400+21%
Sectors 1, 2, 3, 3A, 4 + 19 more (Gurugram)5,0005,5006,5006,5009,00011,550+78%
Sectors 36A, 84, 88, 88A, 89, 89A (Harsaru)———5,5006,5007,000+27%
Sectors 36A, 84, 88B, 89B, 90 + 8 more (Harsaru)———5,5006,5007,000+27%
Sectors 37C, 37D (Kadipur)———5,0006,0006,500+30%
Sectors 71, 72A, 73, 74, 75, 75A (Kadipur)———4,5005,5006,000+33%
Sectors 9, 9A, 9B, 10, 10A + 6 more (Kadipur)———6,0007,0007,500+25%
Sector 36A (Manesar)——7,0007,7007,7008,500+10%
Sector 90 (Manesar)——6,8007,5007,5008,300+11%
Sectors 76, 77, 78, 80, 81 + 5 more (Manesar)——5,5007,0007,0007,700+10%
Sectors 79, 85, 86, 87, 89 (Manesar)——5,5007,0007,0007,700+10%
Sectors 15, 27, 28, 30, 31 + 16 more (Wazirabad)——7,7008,9009,80010,780+21%
Sectors 58, 59, 60, 61, 62 + 2 more (Wazirabad)——5,5006,4009,0009,900+55%
New RERA project registrations by district and year Complete calendar years from each authority’s registered-project list.
DistrictAuthority20212022202320242025
GurugramHRERA Gurugram92131117124131
Gautam Buddha NagarUP RERA3528295162
LucknowUP RERA3544435662
Bengaluru UrbanK-RERA256368374374404
Bengaluru RuralK-RERA32748272117
ChennaiTNRERA251381351262260
ChengalpattuTNRERA128351309302387
KancheepuramTNRERA120254203176202
TiruvallurTNRERA152213221183194
AhmedabadGujRERA581537503569514
JaipurRERA Rajasthan183305304260454
Mumbai ready-reckoner rates for flats, change FY 2022-23 → FY 2026-27 Sub-zones with a flat rate in both lists; ambiguous source rows left out.
GroupSub-zonesMedian changeMiddle half of sub-zones
Metro 2A / 7 stations156+10%+10% to +10%
Metro 3 stations (suburbs)55+10%+10% to +10%
Other suburban sub-zones351+10%+5% to +10%
Island city264+5%0% to +10%
Project timelines from official milestones First official approval, construction start (or foundation stone), first section opening, and the number of official delay statements or revised target dates. “Years” is construction start to first opening.
ProjectWhereFirst approvalConstruction startFirst openedYearsDate revisionsStatus
Noida International Airport (Jewar)Jewar, Gautam Buddha Nagar24 Jun 201725 Nov 202128 Mar 20264.33Open
Yamuna ExpresswayGreater Noida – Agra2001—9 Aug 2012—0Open
Dwarka Expressway (Haryana)GurugramMar 201829 Nov 201811 Mar 20245.33Open
Dwarka Expressway (Delhi)Delhi17 Dec 201817 Oct 201929 May 20255.62Open
Delhi–Mumbai ExpresswayDelhi – Mumbai—10 Dec 201812 Feb 20234.24Partly open
DME: Sohna – Dausa stretchGurugram – Dausa5 Mar 20195 Sep 201912 Feb 20233.40Open
DME link to Jewar airportFaridabad – Jewar1 Aug 2022———0Under construction
Delhi–Meerut RRTS (Namo Bharat)Delhi – Ghaziabad – Meerut19 Feb 2019Jun 201921 Oct 20234.40Open
DMIC township, Greater NoidaGreater Noida20 Jan 2014—Dec 2020—0Open
Bengaluru Peripheral Ring RoadBengaluruFeb 2024———1Under construction
Gurugram Metro (Millennium City Centre – Cyber City)Gurugram13 Aug 20205 Sep 2025—1.1+1Under construction
Noida Metro Aqua LineNoida – Greater Noida24 May 20175 Aug 201526 Jan 20193.50Open
Mumbai Metro Line 3 (Aqua)Mumbai28 Jun 2013—5 Oct 2024—1Open
Atal Setu (Mumbai Trans Harbour Link)Mumbai – Navi Mumbai4 Feb 200923 Mar 201813 Jan 20245.80Open
Navi Mumbai International AirportNavi MumbaiJul 20077 Jul 201825 Dec 20257.51Open
Pune Metro Lines 1 and 2Pune7 Dec 20163 May 20176 Mar 20224.80Open

Methodology

Data. Gurugram collector rates for flats in group housing, FY2021-22 to FY2026-27, as printed in the district’s lists (dataset version 1.0); rates for 2021-22 and 2022-23 come from the earlier-year columns reprinted in later lists, and 2024-25 rates are the 2024 values as reprinted in the 2025 lists, because the 2024 lists were published as drafts. Maharashtra ready-reckoner rates for residential flats in Mumbai, by sub-zone (dataset version 1.0), converted from ₹ per sq m to ₹ per sq ft; rows the source lists twice with different rates are left out. RERA project registrations from HRERA Gurugram (to 14 September 2026) and the district counts of UP RERA and other authorities (dataset version 1.0). Infrastructure milestones from government and project-authority releases (dataset version 1.0).

Definitions. “Dwarka Expressway sectors” are Gurugram sectors 99 to 115, the band the road runs through; the official project statement names sectors 99 and 113 on its route, and Gurugram’s lists price sectors 99–110 and 104–115 as groups. A collector-rate line counts as an expressway line when at least half its sectors are in that band. Mumbai suburban sub-zones are grouped by whether their revenue village carries the name of a Metro 2A, 7 or 3 station. Calculations. Changes are the later rate divided by the earlier, minus one, for lines priced in both lists. Medians are across lines or sub-zones. Registration counts are complete calendar years. Construction time runs from the official construction start (or foundation stone) to the first section opening. Nothing is estimated or carried forward.

How we collect, check and publish research data: Property Nivesh research methodology.

Data sources

  • Deputy Commissioner-cum-Collector, Gurugram — collector rate lists for 2021-22 to 2026-27.
  • Department of Registration and Stamps, Government of Maharashtra — Annual Statement of Rates (ready reckoner), Mumbai City and Mumbai Suburban, 2021-22 to 2026-27.
  • Haryana Real Estate Regulatory Authority, Gurugram — registered and cancelled project lists.
  • Uttar Pradesh Real Estate Regulatory Authority; Karnataka, Tamil Nadu, Gujarat and Rajasthan RERA authorities — registered project lists.
  • Press Information Bureau; Ministry of Civil Aviation; National Highways Authority of India; National Capital Region Transport Corporation; MMRDA; Maha-Metro; Noida Metro Rail Corporation; Yamuna Expressway Industrial Development Authority; NICDC; CIDCO; state government releases — project milestones.

Limitations

  • Circle rates are government minimum values for stamp duty, not market prices, and they lag the market.
  • Gurugram’s rates are set tehsil by tehsil; the same sector can appear in more than one list at different rates.
  • Rates for 2021-22 and 2022-23 are available for only three Gurugram flat lines.
  • RERA counts are projects, not homes, and depend on filed addresses; some Gurugram projects could not be placed in a sector.
  • District registration counts cannot separate the effect of one project from other causes.
  • Noida, Greater Noida, Ghaziabad, Meerut and Bengaluru circle rates are not yet in our data.

Download the report

The full report as a PDF — findings, charts, data tables, methodology and sources — updated 9 October 2026.

Download PDF report

Frequently asked questions

Did the Dwarka Expressway raise property values in Gurugram? +

Official records say the government thinks so. Gurugram’s collector rate for flats in sectors 104–115 rose 67% in the first revision after the road opened, and 157% over five years. Collector rates are not sale prices, so this shows official valuations catching up, not what homes sold for.

How has the Jewar airport affected property in Noida and Greater Noida? +

New RERA projects in Gautam Buddha Nagar rose from about 31 a year in 2021–2023 to 57 a year in 2024–2025. We do not yet hold Noida’s or YEIDA’s circle rates, so we cannot measure official valuations near the airport.

Do new metro lines raise property rates in Mumbai? +

Not in the government’s ready-reckoner rates. Between FY2022-23 and FY2026-27, the median flat rate rose 10% near Metro 2A and 7 stations and 10% elsewhere in the suburbs. Maharashtra revises its rates in near-uniform steps, so they do not show local effects.

How long do infrastructure projects take to open in India? +

Across 28 project sections in our data, the median time from official construction start to first opening was 5.3 years, and 11 had at least one official delay or revised target date.

Cite this research

You may quote the findings and reuse the charts under CC BY 4.0. Please credit Property Nivesh Research and link to this page.

Reference (APA style)

Source line

HTML link

Version history. Report v1.0 (2026-10-09): First publication. · Infrastructure projects and their official milestones v1.0 (2026-10-09): First release: 110 projects, 310 dated milestones. · Gurugram collector rates for flats in group housing v1.0 (2026-10-09): First release: 57 lines followed for two or more years (17 sector groups). · New RERA project registrations v1.0 (2026-10-09): First release: 1087 HRERA Gurugram registrations (to 2026-09-14), 2277 district counts from 9 RERA authorities. · Mumbai ready-reckoner rates for residential flats v1.0 (2026-10-09): First release: 1155 sub-zones, FY2021-22 to FY2026-27 (2 ambiguous rows left out).

This research describes official historical data. It is not investment advice, does not forecast prices and does not recommend buying or selling any property. Government circle rates are minimum values for stamp duty, not market prices. See our methodology, editorial standards and disclaimer.