TGRERA Orders Against 17 Builders: What It Means for Buyers in Hyderabad
Telangana's RERA authority has passed orders in 17 complaints, mostly against smaller developers, covering refunds, plot registration, parking and unfinished amenities. For Hyderabad buyers, the orders show what the authority will enforce and where it will not step in.
By Rahul Mishra · Edited by Rakesh Mahajan · Source: Siasat and The New Indian Express
Published
Figures checked against the source report and our project research · Editorial standards
Illustrative What happened?
Siasat reported that the Telangana Real Estate Regulatory Authority (TGRERA) passed orders across 17 cases. The combined refunds, penalties and interest came to a little over Rs 1.5 crore. The cases involved plots that were never registered, missing parking, unfinished amenities and projects sold without registration.
The New Indian Express reported that 38 members of the Elite BHEL Employees Housing Society won the right to have their allotted plots registered in the Magnus Elite Homes project. The authority did not accept the argument that their claims had lapsed after December 31, 2022. Buyers must clear dues within 30 days, and the promoter must execute sale deeds within 15 days of payment.
Among the refunds, Siasat said Sand Stone Infra must return Rs 47 lakh to a plot buyer in Shankarpally, with interest at 10.85 per cent a year. It said dishonoured cheques do not count as a refund. Sudheesha Constructions was told to refund Rs 10 lakh and pay a penalty of Rs 8,24,585. RDB Hyderabad Infrastructures faces a penalty of Rs 1,000 per day. Sree Builders and Honer Developers were told to give promised parking spaces. Ayyappa Builders must fix drainage, a septic tank and generator backup within 60 days.
The authority also declined some claims. Siasat reported that assured-return and security-deposit disputes, as in the Kapil Business Park case, fall outside RERA's jurisdiction. A plot buyer who holds a registered sale deed cannot also seek a refund.
Which sectors are affected?
- Hyderabad residential plots and layouts
- Under-construction apartments in Hyderabad and nearby districts
- Medchal-Malkajgiri, Shankarpally, Gopanpally, Puppalguda and Bibinagar projects named in the orders
- Small and mid-sized developers
Potential impact
These are individual orders against specific promoters, not a change in the rules. Even so, they show how the authority reads the law. Dishonoured cheques are not a refund, and a completion certificate or handover to the residents' body does not end a builder's duty to fix defects. Builders marketing unregistered plots or villas also face penalties. Developers who sell without registration or delay amenities may find the cost of non-compliance rising.
The effect on prices is likely to be small and indirect. Hyderabad's average price in our data is Rs 9,800 per sq ft, and a handful of orders will not move that. The more practical change is in how buyers assess risk. Registered projects with clear approvals may be preferred over cheaper unregistered layouts. Enforcement also takes time, and recovery is not guaranteed.
Last updated:
Sources
-
Siasat · 18 Nov 2026, 9:09 pm IST
“TG RERA slaps over Rs 1.5 cr in refunds and fines on 17 builders”
https://www.siasat.com/tg-rera-slaps-over-rs-1-5-cr-in-refunds-and-fines-on-17-builders-3580700/
-
The New Indian Express · 19 Nov 2026, 10:21 am IST
“Telangana RERA penalises 17 builders for violations, delayed compliance”
https://www.newindianexpress.com/cities/hyderabad/2026/Nov/19/telangana-rera-penalises-17-builders-for-violations-delayed-compliance