Dholera International Airport: Latest Progress and Impact on Property Prices
Dholera International Airport has not opened as of 29 November 2026; a Gujarat government release of 16 November 2026 says it is expected to become operational by the end of 2026, a tentative target with no DGCA licence or airline schedule reported. No dated study shows its impact on land prices nearby, so price claims tied to the airport are sales claims, not measured facts.
By Rachna Gupta · Edited by
Rakesh Mahajan · · 12 min read
Illustrative image Dholera International Airport: where things stand on 29 November 2026
Dholera International Airport is still not open as of 29 November 2026. A Gujarat government release of 16 November 2026 still calls it upcoming and says it is expected to become operational by the end of 2026, a target best read as tentative. No DGCA aerodrome licence or airline schedule has been reported yet.
So the airport is close, but it is not a working airport for passengers. The runway, taxiway and control tower were reported done in July 2026, and the first aircraft, an AAI flight, landed on 5 June 2026. What remain is the licence, the airlines and the first scheduled flight.
This post are a tracker. It sets out where the airport is, who build and runs it, what it cost, how far work has got with dates, and what is actually on record about land prices near it. It does not forecast prices, because nobody has published a price study for land around the airport.
Dholera airport location: Navagam, the expressway and DSIR
The Dholera airport location is near Navagam, described by DeshGujarat (30 March 2026) as about 20 km from DSIR, the Dholera Special Investment Region. DSIR itself spans about 920 sq km in Ahmedabad district, per the DSIRDA and DICDL FAQ, so "near Dholera" can mean very different spots on the map.
Road access come from the 109 km Ahmedabad-Dholera Expressway, which was inaugurated on 31 March 2026. Its Pipli interchange links to the airport by a 9.56 km road, and the Ambli interchange gives direct access to DSIR, as DeshGujarat reported on 30 March 2026. The same report put the Ahmedabad to Dholera drive at about 45 minutes, which is an expected time and not a measured one.
By air, DeshGujarat (14 June 2022) put the site about 80 km from Ahmedabad airport. A further link is planned too: a 134 km semi-high-speed rail line from Sarkhej to Dholera, approved by the Cabinet Committee on Economic Affairs on 13 May 2026 with a 2030-31 target, is meant to tie DSIR, the airport and Lothal together, ThePrint (PTI) reported.
One thing to be clear. Land that sits close to the airport is not automatic inside a DSIR town planning scheme. The airport site and the planned city is separate things on the map.
Who builds and runs it, and what it costs
The Union Cabinet approved Phase I on 14 June 2022 at ₹1,305 crore, to be finished within 48 months, DeshGujarat reported that day. The builder and operator is Dholera International Airport Company Ltd, a joint venture where AAI holds 51%, the Government of Gujarat 33% and NICDIT 16%. AAI is the Airports Authority of India, and NICDIT is the national industrial corridor trust that backs DSIR.
| Item | What is on record | Source and date |
|---|---|---|
| Approval | Phase I approved by the Union Cabinet | DeshGujarat, 14 June 2022 |
| Phase I cost | ₹1,305 crore | DeshGujarat, 14 June 2022 |
| Build period | Within 48 months of approval | DeshGujarat, 14 June 2022 |
| Company and shares | Dholera International Airport Company Ltd: AAI 51%, Government of Gujarat 33%, NICDIT 16% | DeshGujarat, 14 June 2022 |
| Passenger terminal | 25,000 sq m, designed for 2 million passengers a year | DeshGujarat, 14 July 2026 |
| Cargo terminal | 2,500 sq m | DeshGujarat, 14 July 2026 |
| Airside works | Runway, taxiway and ATC tower reported complete | DeshGujarat, 14 July 2026 |
| Runway length | Not published in an official record | Ask DIACL or AAI |
Notice the gap in the last row. Runway length figures do float around in sales material, but no official document gives one, so treat any number you hear with suspicion untill AAI publish it.
Free property updates
Never Miss a Property Opportunity!
Get the latest property news, investment opportunities, new launches and government plot scheme updates directly.
You're subscribed
One last tap so our WhatsApp updates reach you:
Say hello on WhatsAppIt opens a chat with +91 79824 13588, our main number. Save it in your contacts.
What the airport is planned to handle
The 2022 approval came with traffic projections. DeshGujarat (14 June 2022) reported about 3 lakh passengers a year at the start, rising to 23 lakh in 20 years, and cargo rising from 20,000 to 2,73,000 tonnes. These are planning projections from approval time, not counts.
Illustrative imageThe terminal reported in July 2026 is designed for 2 million passengers a year, roughly in line with the 20-year passenger figure. Cargo matter here because DSIR is planned as a industrial city, and the Tata Electronics fab and other units would be the natural cargo users if they come up on time.
People often search for it as an Ahmedabad second airport. That is loose talk. It is a separate greenfield airport in the Dholera region, about 80 km by air from Ahmedabad airport, and no official record says it will take over any of Ahmedabad airport traffic.
Dholera airport progress: the milestones with dates
Here is the dated record, oldest first. Every row is a report or official statement, not our estimate. Where the target date changes, both the old and the new target are shown.
| Date | Milestone or statement | Source |
|---|---|---|
| 14 June 2022 | Union Cabinet approves Phase I at ₹1,305 crore, 48-month build period | DeshGujarat |
| 31 March 2026 | Ahmedabad-Dholera Expressway inaugurated; Pipli interchange has a 9.56 km airport link road | Swarajya; DeshGujarat, 30 March 2026 |
| 5 June 2026 | First aircraft (AAI) lands at the airport | IANS via NewKerala, 16 October 2026 |
| 14 July 2026 | About 80% complete; terminal 75% done; operations targeted for September to October 2026 | DeshGujarat; All India Radio News |
| 14 July 2026 | Civil Aviation Minister says operational within three months | All India Radio News |
| 16 October 2026 | Chief Minister says operational by year-end, after a calibration flight | IANS via NewKerala |
| 16 November 2026 | State release still calls it upcoming, expected operational by end of 2026 | ANI via NewKerala (Gujarat government release) |
| 29 November 2026 | No opening, DGCA aerodrome licence or airline schedule reported | Gujarat government release of 16 November 2026 |
The 80% figure is the latest percentage on record, and it is from July. No newer percentage has been published, so anybody quoting 95% or "fully ready" should be asked where the number come from.
Dholera airport opening: which date to believe
The Dholera airport opening date has moved more than once. A 48-month build from the June 2022 approval points to roughly June 2026. In July 2026 the minister spoke of September to October 2026. By October and November 2026 the state was saying end of 2026.
Illustrative imageSo the honest answer is: end of 2026 is the latest official target, and it is tentative. With about a month left in the year, the airport still needs a DGCA aerodrome licence and airlines willing to fly there. Neither have been reported as of 29 November 2026.
What would settle it? Three things, in order. A DGCA aerodrome licence, a published airline schedule with routes and timings, and a first scheduled passenger flight. Until all three is on record, an "opening" in an advert is a hope and not a fact.
Keep in mind also that an opened airport and a busy airport are not the same. The 2022 projection starts at about 3 lakh passengers a year, which is modest, and traffic numbers will only come once flights runs for a while.
Dholera airport impact on property: what the evidence says
Here the record is thin. No consultancy, government body or newspaper has published a dated price study for land near the airport. So any claim that land near the airport has "doubled" or "jumped" since a milestone is a sales claim, not a measured fact.
What does exist is a few items, and each has limits:
- Business Today (3 July 2026) ran a story headed around rising land prices in Dholera. The figures in it is developer statements: Satyaja Group said it holds 450 acres in and around the project area and started buying in 2014, and RK Group said nearly 90% of its projects are booked by investors. Those are a developers own claims, not market data.
- Construction World (30 May 2025) headlined a tenfold rise in TP Scheme 1 land over a decade. It names no source and the units it prints don't make sense as a per sq yd rate, so it can't be used as a price.
- The only official land prices are DICDL's allotment rates, read on a page updated 24 August 2026: ₹6,000 per sq m for residential, ₹8,000 for the city centre and ₹4,000 for industry. These are for 99-year leases on plots of 1 acre or more, sold by auction or tender, and they are not tied to the airport at all.
Past growth, even if it was measured, would not predict future growth. The airport is one input among several, along with the expressway, the chip fab and whether the town planning schemes gets built out. For the official rate table by zone, see the Dholera plot prices guide for 2027.
Zones near the airport and what is on record
Here is how the places around the airport compares on the record. The rows follow the map from the airport outward, not any ranking of which is better.
| Zone | What is on record | Price on record | Source and date |
|---|---|---|---|
| Navagam (airport site) | Airport about 20 km from DSIR; no official plot supply data | None published | DeshGujarat, 30 March 2026 |
| Pipli interchange | 9.56 km link road to the airport | None published | DeshGujarat, 30 March 2026 |
| Ambli interchange | Direct access to DSIR from the expressway | None published | DeshGujarat, 30 March 2026 |
| Activation Area (TP 2A and TP 4A) | 22.54 sq km first phase; roads, water, sewage and power listed as completed | DICDL lease rates: ₹6,000 per sq m residential | DSIRDA and DICDL, page updated 24 August 2026 |
| TP schemes outside the Activation Area | Later phases; no trunk services listed as completed | None published | DSIRDA and DICDL FAQ |
| Land next to the DSIR boundary | DSIRDA warns such land is misrepresented as inside DSIR | None published | DSIRDA and DICDL Disclaimer |
The Activation Area is the only part with trunk services built, and the Activation Area post covers what is actually there. For residential plots zone by zone, see best areas to buy residential plots in Dholera SIR. The chip projects that would use the airport cargo side is covered in our Dholera semiconductor post.
Checks before paying for a plot sold as "near the airport"
A plot sold on the airport story need the same checks as any Dholera land, plus a few about distance and boundaries. Run them in this order:
Illustrative image- Ask for the survey number and the TP scheme final plot number, and confirm the zone in the DSIR development plan with DSIRDA.
- Check the land is inside the DSIR boundary. DSIRDA warns that land next to the boundary is sold as inside it.
- Check the 7/12 and 8A extracts on AnyROR and the NA order for non-agricultural use.
- For a layout above 500 sq m, find the project on GujRERA's register and match the number in the advert.
- Ask for any distance to the airport in writing, and check it against the 9.56 km Pipli link road and the map yourself.
- Treat promised fixed returns, referral payouts or an "agreement to sell" with no registered sale deed as warning signs.
- Budget for stamp duty and registration before you sign.
On costs, our state costs table lists Gujarat stamp duty at 4.9% and a 1% registration fee, with women buyers exempt from the registration fee. On a ₹20 lakh deal that come to about ₹98,000 duty plus about ₹20,000 registration. Duty is charged on the higher of the deal value and the jantri value, which is Gujarat's circle rate, so confirm on GARVI or with the stamp duty calculator before paying.
The paperwork steps in detail are in how to buy land in Dholera, and the fraud patterns in Dholera investment scams.
How the airport fits with Ahmedabad
For buyers comparing Dholera with a home in the city, Ahmedabad is the market with real numbers. Our city tracker puts Ahmedabad at an average of ₹6,800 per sq ft in 2026, with 55% growth over five years and a 3.4% rental yield, across the projects and listings we track. See the Ahmedabad city page for the full picture.
Dholera is a different kind of bet. Its mostly land, not flats, and the official land is leasehold. An airport 80 km by air from Ahmedabad airport does not make Dholera a suburb of the city, and the expressway drive of about 45 minutes is an expected time from March 2026.
What to watch next
The next real milestone is the DGCA aerodrome licence, then an airline schedule. If either appear, the end-2026 target starts to look solid; if not, expect the target to be restated again. Until then, read every land advert that leans on the airport with care.
For the wider question of whether Dholera land suits you at all, read is Dholera a good place to invest in land in 2027. It weighs the for and against, while this tracker will stay on the airport.
Questions
Frequently Asked Questions
Is Dholera International Airport open now? +
No. As of 29 November 2026 it has not opened. The Gujarat government release of 16 November 2026 still calls it upcoming and expects it to become operational by the end of 2026, which is a tentative target. No DGCA aerodrome licence or airline schedule has been reported, and both are needed before passenger flights can start.
Where exactly is the Dholera airport located? +
It is near Navagam in Ahmedabad district, described by DeshGujarat in March 2026 as about 20 km from DSIR. The Pipli interchange on the Ahmedabad-Dholera Expressway links to it by a 9.56 km road. By air it is about 80 km from Ahmedabad airport, as DeshGujarat reported when Phase I was approved in June 2022.
How much did Phase I of the Dholera airport cost? +
The Union Cabinet approved Phase I on 14 June 2022 at a cost of ₹1,305 crore, with a build period of 48 months, as DeshGujarat reported that day. The project is built by Dholera International Airport Company Ltd, a joint venture of AAI with 51%, the Government of Gujarat with 33% and NICDIT with 16%.
How complete was the airport at the last official count? +
The latest percentage on record is about 80%, given on 14 July 2026. At that point the runway, taxiway and ATC tower were reported done and the 25,000 sq m terminal was about 75% complete, according to DeshGujarat and All India Radio News. No newer completion percentage has been published since then.
Why has the Dholera airport opening date kept changing? +
The record shows the target moving but gives no official reason. A 48-month build from June 2022 pointed to roughly mid-2026. In July 2026 the minister said September to October 2026, and by October and November the state said end of 2026. Ask for the DGCA licence status rather than trusting any single date.
Have land prices near the Dholera airport gone up? +
No dated price study for land near the airport has been published by a consultancy, government body or newspaper. A July 2026 Business Today story carried developer statements, which are claims and not market data. The only official prices are DICDL lease rates, such as ₹6,000 per sq m for residential land, and they are not linked to the airport.
Is the Dholera airport inside the DSIR town planning schemes? +
The airport near Navagam is described as about 20 km from DSIR, so it is a separate site from the planned city. Land close to the airport is not automatically inside a DSIR town planning scheme. Before paying, get the final plot number and zone and confirm them with DSIRDA, which warns about land near the boundary.
What traffic is the airport planned for? +
The 2022 projections reported by DeshGujarat start at about 3 lakh passengers a year and rise to 23 lakh in 20 years, with cargo rising from 20,000 to 2,73,000 tonnes. The terminal described in July 2026 is designed for 2 million passengers a year. These are planning figures, not actual traffic, because no flights have started.
Sources
- DeshGujarat, Union Cabinet approves development of phase one of Dholera airport in Gujarat, 14 June 2022
- DeshGujarat, Dholera Airport Construction Work 80% Complete, Operations Targeted by Sept - Oct: Minister, 14 July 2026
- All India Radio News, Gujarat: Dholera International Airport to be operational within three months: Union Civil Aviation Minister, 14 July 2026
- IANS via NewKerala, Gujarat CM takes stock of projects in Dholera region, airport, 16 October 2026
- ANI via NewKerala (Gujarat government press release), Dholera SIR accelerates development as India's first semiconductor hub, 16 November 2026
- DeshGujarat, PM Modi to Inaugurate Ahmedabad - Dholera Expressway Built at Rs 5,100 Crore, 30 March 2026
- Swarajya, PM Modi inaugurates Ahmedabad-Dholera Expressway, 31 March 2026
- ThePrint (PTI), Cabinet approves 134-km semi-high-speed rail line between Ahmedabad-Dholera for Rs 20,667 cr, 13 May 2026
- Business Today, Semiconductor chip push, airport milestone, rising land prices: Is Dholera the next real estate hotspot?, 3 July 2026
- Construction World, Dholera's Land Prices Rise Tenfold in a Decade, 30 May 2025
- DSIRDA / DICDL (Government of Gujarat), Land Pricing Policy: Revised Land Allotment Rate (Table A), page last updated 24 August 2026
- DSIRDA / DICDL (Government of Gujarat), Frequently Asked Questions, Dholera SIR; Disclaimer; Infrastructure: Completed Projects
- Government of India (India Code), Real Estate (Regulation and Development) Act, 2016, Section 3
- Property Nivesh state costs table (Gujarat) and Ahmedabad city tracker, 2026