Chennai Metro Corridor 5 Viaduct Done: What It Means for Buyers in Chennai
CMRL has finished the raised concrete structure on a 14.5-km section of Corridor 5, from Koyambedu Market to Alandur. This is a real construction milestone, but the line is not yet ready to carry passengers.
By Rachna Gupta · Edited by Rakesh Mahajan · Source: The New Indian Express
Published
Figures checked against the source report and our project research · Editorial standards
Illustrative What happened?
The New Indian Express reported that Chennai Metro Rail Limited has placed every one of the 606 precast concrete spans needed for the elevated section between Koyambedu Market and Alandur. The section is part of Corridor 5 under Phase II, and the viaduct structure on this 14.5-km stretch is now complete.
According to the newspaper, the final span went up on Sunday between Butt Road and Kathipara on Paul Wells Road. Two 550-tonne hydraulic cranes did the lift, and CMRL announced it in a statement on Monday. Launching girders were used at some points and heavy cranes at others.
The New Indian Express also reported that the work was difficult along Kaliamman Koil Street, Butt Road and Paul Wells Road. Traffic, utility lines above and below ground, and little working space all slowed things down, and the flyover on Mount Poonamallee Road added to the complexity. At one span near a school, CMRL briefly used part of the campus during the festival holidays and brought in a 1,000-tonne crane after the smaller cranes could not reach.
Which sectors are affected?
- Chennai Metro Phase II, Corridor 5
- Koyambedu Market to Alandur elevated stretch
- Butt Road, Kathipara and Paul Wells Road
- Mount Poonamallee Road
Distance from the projects
Distances as sourced on our research pages.
| Project | To | Distance |
|---|---|---|
| Casagrand Mercury | Perambur Metro | 2 km |
Potential impact
A finished viaduct removes one of the hardest construction risks on this section, since the most congested stretches have now been crossed. It does not mean trains will run soon. Tracks, stations, power and signalling work, and safety trials usually still lie ahead, and the source gives no opening date.
For property, the effect is likely to build slowly. Buyers and renters tend to price in a metro station only as opening becomes credible, so any lift in demand or rents near stations would probably come later and unevenly. Chennai's average price in our data is 9200 per sq ft with a rental yield of 3.3 percent, and neither can be assumed to move because of one structural milestone. Locations that already sit in busy, congested corridors may gain more from a reliable rail link than quieter pockets.
Last updated:
Source
-
The New Indian Express · 24 Nov 2026, 7:47 am IST
“Chennai Metro completes erection of 606 U-girders on Corridor 5”
https://www.newindianexpress.com/cities/chennai/2026/Nov/24/chennai-metro-completes-erection-of-606-u-girders-on-corridor-5