Market Trends
Upcoming Infrastructure Projects in Rohini: Metro and Road Status
The biggest of the upcoming infrastructure projects in Rohini is the Phase 4 metro from Rithala to Narela and Kundli: sanctioned on 3 January 2025 and tendered in 2026, it had no main civil award or construction start by 28 November 2026, and its target of about 2029 is tentative. Smaller works such as the Mukarba Chowk underpass (inaugurated 29 September 2026), the Madhuban Chowk skywalk, UER-II service roads and DDA roads and drains in Sectors 27 and 28 are tracked here with dated status.
By Pranav Adhikari · Edited by
Rakesh Mahajan · · 14 min read
Illustrative image Where the Rithala to Narela to Kundli Metro Stands Today
The biggest of the upcoming infrastructure projects in Rohini is the Phase 4 metro from Rithala to Narela and Kundli. It was sanctioned on 3 January 2025, yet on 28 November 2026 it still had no main civil contract award and no construction start on record. Around it sit smaller, dated works: the Mukarba Chowk underpass, the Madhuban Chowk skywalk, the Magenta Line gap, UER-II service roads and DDA (Delhi Development Authority) work in Phase IV and V.
The Union Cabinet approved the line on 6 December 2024, says the Press Information Bureau (PIB). It is 26.463 km with 21 new stations, all elevated, at ₹6,230 crore, and it extend the Red Line past Rithala under DMRC (Delhi Metro Rail Corporation).
Eight of the new stations is in Rohini: Rohini Sector 25, 26, 31, 32, 36, Barwala, 35 and 34, in PIB's order. That matters most for the outer sectors, because DNA India reported in 2017 that Rithala was 7 km from Sectors 34 and 35.
Rohini Metro Phase 4: Tenders, Station Names and the 2029 Target
Most of 2026 went in tenders, not in building. The first contract on record is a 30 March 2026 utility-shifting award of about ₹17.21 crore, Construction World reported. The main Rohini civil package, D2C-04, was invited on 25 August 2026 for about 11.30 km of viaduct and 10 elevated stations from UER-II to Bawana Industrial Area - 1 Sector 1,2, with 36 months of work (Metro Rail News, 31 August 2026).
Technical bids was opened on 13 October 2026, per a secondary report, but no award is on record. The Narela to Nathupur package, D2C-05 (about ₹1,373.36 crore, Construction World, 21 August 2026), the rolling stock and the Sanoth depot were also only tendered. On 12 August 2026 DDA approved a 19.63 ha land-use change in Narela for the depot, which still needs notification by MoHUA (the Union Ministry of Housing and Urban Affairs), The Tribune reported.
Station names may still change: a secondary report of the D2C-04 tender (September 2026) lists Rohini Sector-28 and Rohini Sector-29-30 instead of Sectors 32 and 36. DMRC hasn't confirmed it, so this post use PIB's names. Rithala becomes the change point to the old Red Line (see our guide to the best residential sectors near Rithala metro station), and the far end is weighed up in Rohini vs Narela.
On timing, PIB said 4 years from sanction, which from the 3 January 2025 order give about January 2029. ThePrint (PTI) wrote on 22 May 2026 that the corridors are expected "around 2029 depending on approvals, land acquisition and construction progress". With civil work unawarded, call 2029 a tentative target.
Costs differ by source: ₹6,230 crore per PIB, ₹6,230.99 crore per Metro Rail Today (19 January 2026) and ₹6,830 crore from MP Yogender Chandolia in June 2026.
Status Tracker: Upcoming Metro and Infrastructure Developments in Rohini
The table below put each project in one row, with cost and status as its source gives them, to 28 November 2026. Sources are PIB, DMRC, DDA and NHAI (National Highways Authority of India) tender listings and the newspapers named in each row.
| Project | Cost (as reported) | Status, with date | Next step |
|---|---|---|---|
| Phase 4 metro, Rithala to Narela to Nathupur (Kundli) | ₹6,230 crore (PIB) | Sanctioned 3 Jan 2025; tendered 2026; no main award by 28 Nov 2026 | Civil awards, then about 36 months of work |
| Magenta Line gap, Krishna Park Extension to Deepali Chowk | Not stated | Under construction; Peeragarhi about 90% done (Swarajya, 4 Oct 2026) | Opening expected by end-2026 |
| Madhuban Chowk skywalk | ₹9.62 crore | 60% done on 23 Aug 2026 (The Pioneer) | Target 30 Nov 2026; not confirmed |
| Mukarba Chowk underpass | Part of a ₹1,941 crore set of projects | Inaugurated 29 Sep 2026 (ThePrint, PTI) | In use; one report says work continues |
| UER-II service roads | ₹121 crore for 19 km | Detailed project report stage 10 Jan 2026 (PIB); bids closed 11 Jun 2026 | Award not on record |
| UER-II to Delhi-Dehradun Expressway link | About ₹3,500 crore | Alignment stage (ANI, 28 May 2026) | Start targeted by Dec 2026 |
| Khera Kalan rail overbridge | About ₹109 crore | In-principle approval (The Week, PTI, 18 Nov 2025) | No timeline |
| DDA works, Sectors 27 and 28 | About ₹47.98 crore | Tendered; bids due 28 May 2026 (tender listing) | Award, then 365 days of work |
| Ayurveda research campus (CARI) with 100-bed hospital, Sector 28 | About ₹185 to 187 crore | Under construction since 5 Jan 2025 (The Tribune, Jun 2026) | No completion date |
| Keshav Puram to Rohini Sector 34 metro | Not stated | Proposal awaiting the Centre (Hindustan Times, 18 Nov 2026) | Study, DPR, Cabinet sanction |
Free property updates
Never Miss a Property Opportunity!
Get the latest property news, investment opportunities, new launches and government plot scheme updates directly.
You're subscribed
One last tap so our WhatsApp updates reach you:
Say hello on WhatsAppIt opens a chat with +91 79824 13588, our main number. Save it in your contacts.
Inner Rohini: The Magenta Line Gap and the Madhuban Chowk Skywalk
Inner Rohini already has metro, so its upcoming items close gaps. The Magenta Line's Deepali Chowk to Majlis Park section opened on 8 March 2026 (PIB), with interchanges at Pitampura (Madhuban Chowk), Haiderpur Badli Mor and Majlis Park. Which station suit which sector is in our lookup of the nearest metro stations to Rohini residential sectors.
Illustrative imageThe missing link, Krishna Park Extension to Deepali Chowk, is still under construction. Swarajya, citing DMRC, reported on 4 October 2026 that Peeragarhi station was about 90% done and expected ready for passengers by the year end. When it opens, Rohini's Magenta stations get a one-line ride to Janakpuri West and Terminal-1 IGI Airport.
The Madhuban Chowk skywalk is small project but a handy one. The Pioneer reported on 23 August 2026 that this ₹9.62 crore PWD (Public Works Department) link between Pitampura metro, Madhuban Chowk metro and Rohini District Court was 60% complete, with a 30 November 2026 target. Its completion isn't confirmed yet.
Mukarba Chowk Underpass and Other Road Works Near Rohini
The Mukarba Chowk underpass on the Outer Ring Road was inaugurated on 29 September 2026, ThePrint (PTI) reported, among five projects worth ₹1,941 crore combined. About 15,800 vehicles a day was expected, and it lets Badli and Rohini traffic reach Azadpur and Jahangirpuri without the interchange. Our note on the Delhi road openings has the commuter side.
One caution: the same report also says an underpass there "is being constructed", while News On AIR and Construction World treat it as opened. Further back, PWD and Northern Railway plan a four-lane overbridge of about 800 m and a 5 m underpass at Khera Kalan nearby Rohini (about ₹109 crore), approved in principle with no timeline (The Week, PTI, 18 November 2025).
UER-2 in Rohini: What Is Open and What Is Still Coming
UER-II (Urban Extension Road-II) is open already, so for Rohini the upcoming part are the access around it. PIB says its Alipur to Dichaon Kalan stretch, about ₹5,580 crore, was inaugurated at Rohini on 17 August 2025. A 2019 Delhi High Court ruling quotes DDA calling it Delhi's third ring road, running past Rohini Sector 38.
Local access is where the work remain. PIB said the service roads for villages and colonies were at DPR (detailed project report) stage on 10 January 2026. ANI reported on 28 May 2026 an approval for a 19 km two-lane road at ₹121 crore, and a 26 km plan at ₹6,500 crore, a figure that looks doubtful for service roads alone. NHAI bids closed on 11 June 2026, a tender listing shows; no award is on record.
The same ANI report gave two new links: a 17 km, six-lane road to the Delhi-Dehradun Expressway near Tronica City (about ₹3,500 crore, construction targeted by December 2026) and a 17 km link to the Delhi-Amritsar-Katra Expressway (about ₹1,500 crore, targeted from March 2027). Both is targets, not starts.
Barrier-free MLFF (multi-lane free flow) tolling began at the Mundka-Bakkarwala plaza on 11 May 2026 (The Pioneer), and Millennium Post flagged flood-prone stretches near Village Barwala in August 2025. Routes and times to Gurgaon are in our guide to connectivity between Rohini and Gurgaon.
DDA Work in Rohini Phase IV and V, Plus Hospitals and Civic Projects
The outer sectors still needs basic works. A DDA tender, as listed by tender aggregators, covers 400 ha in Phase IV and V, Sectors 27 and 28: storm-water drains, internal roads and a 45 m road in Sector 28, about ₹47.98 crore over 365 days. Bids were due on 28 May 2026, and no award is on record.
Illustrative imageSome civic pieces are done. DDA's Sports Complex in Sector 33 opened on 1 October 2026 (UNI), and the Delhi Transport Corporation's (DTC) Rohini Sector-37 depot was named in October 2026 for new electric buses and public EV charging (ThePrint, PTI), though the roll-out were only announced.
On health, the Central Ayurveda Research Institute (CARI) campus with a 100-bed hospital in Sector 28 is under construction since its 5 January 2025 foundation stone, with no completion date published.
MPD-2047, TOD Rules and Land Pooling: Plans That Shape Rohini
Plan-level items don't pour concrete, but they decides what can rise near the new lines. MoHUA notified the TOD (transit-oriented development) regulations in a gazette copy dated 6 April 2026, The Pioneer reported. They cover 500 m on either side of metro corridors and allow FAR (floor area ratio) up to 500 on plots of 2,000 sq m and above with an 18 m road. Which Rohini sites qualify will show as DDA's TOD committee approves projects; see our note on Delhi's TOD housing push.
MPD-2047's legal status is disputed. DDA approved it on 12 August 2026 and Union Minister Manohar Lal unveiled it on 20 August 2026. The Tribune (21 August 2026) call it "the notified Master Plan", but no gazette number or date has surfaced, and an earlier Property Nivesh record of 31 October 2026 listed it as not notified.
MPD-2047 reportedly aims to take the metro from about 416 km to 695 km by 2047 (see our note on the Delhi metro growth plan), and ANI reported on 16 October 2026 that its land pooling framework includes a High Density Corridor along UER-II. Land pooling, where landowners in greenfield areas joins their land into sectors DDA plans, was notified in 2018; Zone N lies west of Rohini, around Bawana. DDA's October 2026 camps, covered in our note on DDA's land pooling outreach, are an early step, not a building start.
Phase V Metro Proposals for Rohini: Not Sanctioned Yet
Two more metro routes touches Rohini, but neither is sanctioned. Hindustan Times reported on 18 November 2026, citing an RTI (Right to Information) reply seen by PTI, that Keshav Puram to Rohini Sector 34 and Samaypur Badli to Narela are among seven routes with Delhi government approval awaiting the Centre. Our note on the Yashobhoomi to Gurugram metro proposal covers that list.
ThePrint said in May 2026 the Phase 5B DPR was "still at the planning stage", and Construction World reported on 20 July 2026 that DMRC is only to study a double-decker flyover-cum-metro on the 16.5 km route. So the three records differs, and none is an approval.
Timeline and Sectors Served: Upcoming Infrastructure Projects in Rohini
The milestones below come from the sources in each row. Past dates are events; future dates are only targets.
Illustrative image| Date | Milestone | Source |
|---|---|---|
| 6 Dec 2024 | Cabinet approves the Rithala to Kundli corridor | PIB |
| 3 Jan 2025 | Sanction order issued | DMRC Annual Report 2024-25 |
| 17 Aug 2025 | UER-II Alipur to Dichaon Kalan opens | PIB |
| 16 Dec 2025 | Lieutenant Governor approves land for the Rithala to Rohini Sector 25 viaduct | The Week (PTI) |
| 8 Mar 2026 | Magenta Line, Deepali Chowk to Majlis Park, opens | PIB |
| 6 Apr 2026 | TOD regulations notified (gazette copy) | The Pioneer |
| 12 Aug 2026 | DDA approves MPD-2047 and the Narela depot land use | The Tribune |
| 25 Aug 2026 | D2C-04 civil tender invited | Metro Rail News |
| 29 Sep 2026 | Mukarba Chowk underpass inaugurated | ThePrint (PTI) |
| 30 Nov 2026 (target) | Madhuban Chowk skywalk | The Pioneer |
| Dec 2026 (target) | Magenta Line gap; Dehradun Expressway link start | PIB; ANI |
| About 2029 (tentative) | Phase 4 line to Narela and Kundli | PIB; ThePrint (PTI) |
This table shows which sectors each project serve, in its own source's words (the tracker's sources, to 28 November 2026).
| Project | Sectors and places served (as the source names them) |
|---|---|
| Phase 4 metro | Rohini Sector 25, 26, 31, 32, 34, 35, 36 and Barwala (PIB); a reported list has Sector-28 and Sector-29-30 in place of 32 and 36 |
| Magenta Line gap | Deepali Chowk, Pitampura (Madhuban Chowk), Haiderpur Badli Mor |
| Madhuban Chowk skywalk | Pitampura, Rohini District Court |
| Mukarba Chowk underpass | Badli and Rohini traffic to Azadpur and Jahangirpuri |
| UER-II service roads and links | Rohini Phase IV and V, villages along UER-II, Alipur |
| DDA works and CARI hospital | Sectors 27 and 28 |
| DTC e-bus depot | Sector 37 |
| Phase V(B) proposals | Rohini Sector 34 and Keshav Puram; Samaypur Badli and Narela |
What Rohini's Upcoming Projects May Mean for Property Prices
Careful here: a project on paper is not a price fact. Our Rohini infrastructure impact report follows these projects against prices, and our plot estimates don't show a clear metro premium so far. The table compare outer sectors with and without a Phase 4 station named after them.
| Sector | Phase 4 station named after it (PIB, 6 Dec 2024) | Median asking price, 2026 to 31 Oct (Property Nivesh estimates, per sq m of plot) |
|---|---|---|
| Sector 34 | Yes | ₹2,15,500 |
| Sector 36 | Yes | ₹2,08,500 |
| Sector 35 | Yes | ₹1,94,500 |
| Sector 37 | No (adjoins Sector 36) | ₹2,10,500 |
| Sector 30 | No (a reported tender list names Sector-29-30) | ₹2,26,500 |
| Sector 29 | No (same reported list) | ₹1,91,000 |
These are Property Nivesh estimates, medians of dated asking prices per sq m of plot, checked to 31 October 2026, with medium confidence. Sectors with a named station run ₹1,94,500 to ₹2,15,500 and those without run ₹1,91,000 to ₹2,26,500, so the two ranges overlap. Past growth does not predict future growth; see Rohini Sector 36 plot rates and the full Rohini property rates for dated detail.
How to Track an Upcoming Metro in Rohini Yourself
Status changes quick, so check any project yourself before you pay a token amount or sign anything.
- Look for a letter of acceptance on DMRC's D2C-04 package; a tender or a bid opening is not a construction start.
- Check DMRC's own D2C-04 papers for station names, since a reported list differs from PIB's.
- Watch for MoHUA's notification of the Narela depot land use and for the MOU with DMRC.
- For UER-II service roads, ask NHAI whether the 19 km road is awarded and where its entry points fall.
- Ask DDA for the MPD-2047 gazette notification number and date before relying on any zoning change.
- For a TOD claim, confirm the plot is within 500 m of a metro corridor and has DDA's TOD committee approval.
- Treat foundation stones and targeted dates as tentative until work is visible on site.
That's the tracker as of 28 November 2026. For your sector's station today, use the nearest metro stations lookup above; for the price history, read our post on future property price trends in Rohini.
Questions
Frequently Asked Questions
When will the Rithala to Narela to Kundli metro open? +
No opening date is fixed. PIB said the line would be completed in 4 years from sanction, and counting from the sanction order of 3 January 2025 gives about January 2029. ThePrint (PTI) reported in May 2026 that the corridors are expected around 2029. With the main civil packages still unawarded on 28 November 2026, treat 2029 as tentative.
Has construction started on the Rohini metro Phase 4 line? +
Not on record. As of 28 November 2026 there was no main civil contract award and no construction start. What has happened is a foundation stone on 5 January 2025 (PIB), a utility-shifting contract on 30 March 2026 (Construction World), and 2026 tenders for the D2C-04 and D2C-05 civil packages, the Sanoth depot and the rolling stock.
Which Rohini sectors will get a Phase 4 metro station? +
PIB's list of 6 December 2024 names Rohini Sector 25, 26, 31, 32, 36, 35 and 34, plus Barwala. A secondary report of the D2C-04 tender in September 2026 lists Sector-28 and Sector-29-30 instead of Sectors 32 and 36. DMRC hasn't confirmed a change, so check its own tender papers before relying on either list.
Is the Mukarba Chowk underpass open now? +
ThePrint (PTI) reported that it was inaugurated on 29 September 2026, with two vehicle underpasses and one pedestrian underpass for Badli and Rohini traffic heading to Azadpur and Jahangirpuri. The same report also says an underpass there is being constructed, while News On AIR and Construction World treat it as opened. A drive through will settle it.
What work is still pending on UER-II near Rohini? +
UER-II opened on 17 August 2025 (PIB), but its service roads were at detailed project report stage in January 2026, and a 19 km, ₹121 crore road had no award on record. ANI reported a Delhi-Dehradun Expressway link targeted to start by December 2026 and a Delhi-Amritsar-Katra link from March 2027. Millennium Post flagged flood-prone stretches near Barwala in August 2025.
Is the Master Plan for Delhi 2047 notified? +
It is disputed. DDA approved MPD-2047 on 12 August 2026 and it was unveiled on 20 August 2026. The Tribune calls it the notified Master Plan, but no gazette number or date has surfaced, and an earlier Property Nivesh record of 31 October 2026 listed it as not notified. Ask DDA for the gazette notification before relying on it.
Is the Keshav Puram to Rohini Sector 34 metro approved? +
No. Hindustan Times reported on 18 November 2026 that it is among seven routes with Delhi government approval awaiting the Centre. ThePrint said in May 2026 that the Phase 5B DPR was at the planning stage, and Construction World said in July 2026 that DMRC is only studying a double-decker flyover-cum-metro on the 16.5 km route.
Have plot prices near planned Rohini stations risen because of the metro? +
Our estimates don't show a clear metro premium yet. In 2026, to 31 October, median asking prices in sectors with a named Phase 4 station ran from ₹1,94,500 to ₹2,15,500 per sq m, while Sectors 29, 30 and 37 ran from ₹1,91,000 to ₹2,26,500. Past growth does not predict future growth.
Is a new hospital coming up in Rohini? +
The Central Ayurveda Research Institute campus with a 100-bed hospital in Sector 28 has been under construction since its foundation stone on 5 January 2025 (The Tribune, June 2026), with no completion date published. Medical Dialogues reported in May 2018 that a Mother and Child block at Dr Baba Saheb Ambedkar Hospital was approved at ₹195 crore; its current status is not on record.
Sources
- Press Information Bureau (Union Cabinet), Cabinet approves Rithala-Kundli corridor of Delhi Metro Phase-IV project (Release ID 2081693), 6 December 2024
- Delhi Metro Rail Corporation, DMRC Annual Report 2024-25 (sanction order dated 3 January 2025), 2025
- Press Information Bureau (Prime Minister's Office), PM inaugurates and lays foundation stone of multiple development projects in Delhi worth over Rs 12,200 crore (Release ID 2090307), 5 January 2025
- Delhi Metro Rail Corporation, DMRC begins the construction work on Lajpat Nagar-Saket G Block Corridor (press release), 12 December 2025
- Metro Rail Today, Delhi Govt releases funds for remaining Delhi Metro Phase IV corridors, 19 January 2026
- Metro Rail Today, Tender issued for 68 Broad Gauge Rolling Stock Cars for Red Line Extn under Delhi Metro Phase 4, 12 February 2026
- Construction World, DMRC Awards Rs172.1 Mn Contract For Rithala-Kundli Utility Shifting, 30 March 2026
- Metro Rail News, DMRC Floats Rs 144.88 cr Tender for Sanoth Depot Infrastructure Under Delhi Metro Phase IV Rithala-Kundli Corridor, 14 April 2026
- Metro Rail News, Delhi Metro's Rithala-Narela-Kundli Line Enters Construction Stage: Civil Tender Floated for 10 Stations and Viaduct, 31 August 2026
- Construction World, Rithala to Kundli Corridor Secures Rs 13,733.6 Million Tender (a tender invitation), 21 August 2026
- ThePrint (PTI), DMRC eyes December rollout for key Phase 4 corridors, fixes target for Phase 5 expansion, 22 May 2026
- The Week (PTI), Major hurdle cleared for Rithala-Narela-Kundli Metro corridor as LG approves land allotment, 16 December 2025
- The Tribune, DDA approves Delhi Master Plan 2047, 13 August 2026
- DNA India, Don't come here, it's a trap, 15 July 2017
- Press Information Bureau (Prime Minister's Office), PM to inaugurate Majlis Park - Maujpur Babarpur (Pink Line) and Deepali Chowk - Majlis Park (Magenta Line) corridors of Delhi Metro (Release ID 2236008), 6 March 2026
- Press Information Bureau (Union Cabinet), Cabinet approves three new corridors as part of Delhi Metro's Phase V (A) Project (Release ID 2208096), 24 December 2025
- Swarajya, Peeragarhi to get Green-Magenta metro interchange by year-end as Phase 4 work nears completion, 4 October 2026
- The Pioneer, Construction underway for skywalk, FOB at Madhuban Chowk, 23 August 2026
- ThePrint (PTI), Shah inaugurates Barapullah Phase III, launches Delhi road projects, 29 September 2026
- The Week (PTI), PWD plans flyover and underpass to decongest Northwest Delhi, 18 November 2025
- The Tribune, Rekha unveils Rs 1.25 lakh crore road infra push for Delhi, 5 June 2025
- Press Information Bureau (Prime Minister's Office), PM inaugurates two major National Highway projects worth Rs 11,000 crore at Rohini (Release ID 2157281), 17 August 2025
- High Court of Delhi, Jain vs Union of India and Ors, WP(C) 10199 of 2018, 27 February 2019
- Press Information Bureau (Ministry of Road Transport and Highways), MoS Harsh Malhotra reviews key road infrastructure projects of NHAI and MoRTH and decongestion initiatives for the National Capital (Release ID 2213294), 10 January 2026
- NewKerala (ANI), Making Delhi world-class, congestion-free our goal: CM Rekha, 28 May 2026
- NHAI tender 2026_NHAI_275996_1, Construction of a two lane secondary service road along UER-II, as listed by a tender aggregator, 2026
- The Pioneer, Gadkari launches MLFF tolling on UER-II at Mundka-Bakkarwala plaza, 12 May 2026
- Millennium Post, Min's UER-II review: Safety, service roads, drainage top agenda, 22 August 2025
- DDA NIT 05/EE/RMD-1/DDA/2026-27 (2026_DDA_908355_1), D/o 400 Hect. of land in Phase-IV and V, Sector-27 and 28, Rohini, as listed by tender aggregators, 2026
- UNI, Delhi LG inaugurates DDA sports complex in Rohini, 1 October 2026
- ThePrint (PTI), Delhi govt to launch 150 electric buses soon: Transport Minister Pankaj Singh, 12 October 2026
- The Tribune via Newswav (MP Yogender Chandolia press conference), Rs 18,000-crore projects reshaped North West Delhi, 17 June 2026
- Medical Dialogues, Delhi govt to increase bed capacity in 4 hospitals, 11 May 2018
- Delhi Development Authority, Circular dated 23.10.2025: Launch of Phase II of DDA Jan Sadharan Awaas Yojana, 2025, 23 October 2025
- The Pioneer, MoHUA notifies new TOD policy, charges, 8 April 2026
- The Tribune, Khattar unveils Master Plan for Delhi 2047, 21 August 2026
- NewKerala (ANI), Master Plan Delhi 2047: DDA begins month-long drive (land pooling outreach camps), 16 October 2026
- Hindustan Times (citing an RTI reply seen by PTI), Yashobhoomi to Gurugram among 8 routes proposed under Delhi Metro's new project, 18 November 2026
- Construction World, DMRC To Study Double Decker Metro Flyover Corridor, 20 July 2026
- Property Nivesh, Rohini plot rates by sector (dataset pn-rohini-plot-prices, medians of dated asking prices per sq m of plot), checked to 31 October 2026